Velos Residence construction progress

The registered completion date for Velos Residence in Motor City is October 2028. At the last site inspection, in August 2026, it was 6.6% built. The developer is City View Urban Real Estate Development.

6.6%

Built, at the site inspection of 4 August 2026

Running behind its date

Registered completion date
October 2028
Finish at recent pace
April 2035
Construction started
September 2025
First registered
September 2025
Developer
City View Urban Real Estate Development
Community
Motor City
Units
413
Escrow bank
United Bank Limited
Name in Arabic
فيلوس ريزيدنس
Project number
3816
Site inspections
3

Schedule

Between March 2026 and August 2026 the site added about 0.9 points a month. At that rate it would finish around April 2035, more than three months after its registered date of October 2028.

0%25%50%75%100%202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

4 August 2026

6.6%+3.8 pts

  • Velos Residence construction site, inspection photo 1, 4 August 2026
  • Velos Residence construction site, inspection photo 2, 4 August 2026
  • Velos Residence construction site, inspection photo 3, 4 August 2026
  • Velos Residence construction site, inspection photo 4, 4 August 2026

27 March 2026

2.8%+2.8 pts

  • Velos Residence construction site, inspection photo 1, 27 March 2026

2 July 2025

0%

  • Velos Residence construction site, inspection photo 1, 2 July 2025
  • Velos Residence construction site, inspection photo 2, 2 July 2025

All 7 site photos, by inspection date

Context

Motor City has 11 projects under construction, 20% built on average.

Own a unit in Velos Residence?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Velos Residence handover date?
The registered completion date is October 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around April 2035. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Velos Residence?
Velos Residence was 6.6% built at the site inspection on 4 August 2026. The site has been inspected 3 times since July 2025. The Land Department took 7 site photos at its inspections.
Is Velos Residence delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of October 2028.
Who is building Velos Residence?
The registered developer is City View Urban Real Estate Development.
Which bank holds the escrow account for Velos Residence?
United Bank Limited. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.