15 Cascade construction progress

15 Cascade in Motor City is 5.5% built at the Land Department inspection of July 2026. Developer Iman Developers. Completion registered for September 2028.

5.5%

Built, at the Land Department site inspection of 2 July 2026

Running behind its date

Completion date (Land Department)
September 2028
Finish at recent pace
October 2038
Construction started
March 2025
Registered with the Land Department
June 2025
Community
Motor City
Units
442
Escrow bank
Emirates NBD
Name in Arabic
15 كاسكيد
Land Department project number
3528
Land Department site inspections
3

Schedule

Between December 2025 and July 2026 the site added about 0.6 points a month. At that rate it would finish around October 2038, more than three months after the September 2028 date registered with the Land Department.

0%25%50%75%100%202620272028
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

2 July 2026

5.5%+4.0 pts

  • 15 Cascade construction site, Land Department inspection photo 1, 2 July 2026
  • 15 Cascade construction site, Land Department inspection photo 2, 2 July 2026
  • 15 Cascade construction site, Land Department inspection photo 3, 2 July 2026
  • 15 Cascade construction site, Land Department inspection photo 4, 2 July 2026

25 December 2025

1.5%+1.5 pts

  • 15 Cascade construction site, Land Department inspection photo 1, 25 December 2025
  • 15 Cascade construction site, Land Department inspection photo 2, 25 December 2025
  • 15 Cascade construction site, Land Department inspection photo 3, 25 December 2025
  • 15 Cascade construction site, Land Department inspection photo 4, 25 December 2025

28 January 2025

0%

  • 15 Cascade construction site, Land Department inspection photo 1, 28 January 2025
  • 15 Cascade construction site, Land Department inspection photo 2, 28 January 2025
  • 15 Cascade construction site, Land Department inspection photo 3, 28 January 2025

All 15 site photos, by inspection date

Context

Motor City has 11 projects under construction, 18% built on average.

Iman Developers has 9 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in 15 Cascade?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will 15 Cascade be completed?
The completion date registered with the Dubai Land Department is September 2028. At the pace of its recent inspections the site would reach 100% around October 2038. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of 15 Cascade is built?
5.5%, measured at the Land Department site inspection on 2 July 2026. The Land Department engineers have inspected the site 3 times since January 2025.
Is 15 Cascade delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2028.
Who is building 15 Cascade?
The registered developer is Iman Developers. It has 8 other projects under construction in Dubai.
Which bank holds the escrow account for 15 Cascade?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.