15 Cascade construction progress
15 Cascade in Motor City is 5.5% built at the Land Department inspection of July 2026. Developer Iman Developers. Completion registered for September 2028.
5.5%
Built, at the Land Department site inspection of 2 July 2026
Running behind its date
- Completion date (Land Department)
- September 2028
- Finish at recent pace
- October 2038
- Construction started
- March 2025
- Registered with the Land Department
- June 2025
- Developer
- Iman Developers
- Community
- Motor City
- Units
- 442
- Escrow bank
- Emirates NBD
- Name in Arabic
- 15 كاسكيد
- Land Department project number
- 3528
- Land Department site inspections
- 3
Schedule
Between December 2025 and July 2026 the site added about 0.6 points a month. At that rate it would finish around October 2038, more than three months after the September 2028 date registered with the Land Department.
Site inspections
2 July 2026
5.5%+4.0 pts
25 December 2025
1.5%+1.5 pts
28 January 2025
0%
Context
Motor City has 11 projects under construction, 18% built on average.
Iman Developers has 9 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in 15 Cascade?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will 15 Cascade be completed?
- The completion date registered with the Dubai Land Department is September 2028. At the pace of its recent inspections the site would reach 100% around October 2038. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of 15 Cascade is built?
- 5.5%, measured at the Land Department site inspection on 2 July 2026. The Land Department engineers have inspected the site 3 times since January 2025.
- Is 15 Cascade delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2028.
- Who is building 15 Cascade?
- The registered developer is Iman Developers. It has 8 other projects under construction in Dubai.
- Which bank holds the escrow account for 15 Cascade?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- 10 Oxford By ImanAlso by Iman Developers. 91%.
- Gardens 2Also by Iman Developers. 68%, Due December 2025, passed.
- One Park Central By ImanAlso by Iman Developers. 20%, Due June 2027.
- One Sky Park By ImanAlso by Iman Developers. 9.0%, Due March 2028.
- The Community Motor CityNearby in Motor City. 95%.
- Sobha OrbisNearby in Motor City. 18%, Due December 2028.
- TakayaNearby in Motor City. 16%, Due December 2027.
- Sobha SolisNearby in Motor City. 13%, Due December 2028.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)



.jpeg&w=3840&q=75)