Monarch construction progress
Monarch in Motor City is 20% built at the Land Department inspection of August 2026. Developer Zane Developments. Completion registered for October 2026.
20%
Built, at the Land Department site inspection of 26 August 2026
0 months past its registered completion date
- Completion date (Land Department)
- October 2026
- Finish at recent pace
- December 2028
- Construction started
- April 2025
- Registered with the Land Department
- May 2025
- Developer
- Zane Developments
- Community
- Motor City
- Units
- 47
- Escrow bank
- Mashreq Bank
- Name in Arabic
- مونارك
- Land Department project number
- 3598
- Land Department site inspections
- 5
Schedule
Monarch was registered to complete in October 2026, 1 month ago, and is still under construction. Over the last year of inspections it has added about 2.9 points a month. Kept at that rate, the site would reach 100% around December 2028.
Site inspections
26 August 2026
20%+12 pts
20 April 2026
7.6%+5.7 pts
16 February 2026
1.9%+1.9 pts
2 August 2025
0%
19 March 2025
0%
Context
Motor City has 11 projects under construction, 18% built on average.
Own a unit in Monarch?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Monarch be completed?
- The completion date registered with the Dubai Land Department is October 2026. At the pace of its recent inspections the site would reach 100% around December 2028. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Monarch is built?
- 20%, measured at the Land Department site inspection on 26 August 2026. The Land Department engineers have inspected the site 5 times since March 2025.
- Is Monarch delayed?
- Yes. Its registered completion date of October 2026 has passed and the Land Department still lists it as under construction.
- Who is building Monarch?
- The registered developer is Zane Developments.
- Which bank holds the escrow account for Monarch?
- Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- The Community Motor CityNearby in Motor City. 95%.
- Sobha OrbisNearby in Motor City. 18%, Due December 2028.
- TakayaNearby in Motor City. 16%, Due December 2027.
- Sobha SolisNearby in Motor City. 13%, Due December 2028.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.