Monarch construction progress

Monarch in Motor City was registered to complete in October 2026 and is still under construction. At the last site inspection, in October 2026, it was 32% built. The developer is Zane Developments.

32%

Built, at the site inspection of 22 October 2026

2 months past its registered completion date

Registered completion date
October 2026
Finish at recent pace
April 2028
Construction started
April 2025
First registered
May 2025
Developer
Zane Developments
Community
Motor City
Units
47
Escrow bank
Mashreq Bank
Name in Arabic
مونارك
Project number
3598
Site inspections
6

Schedule

Monarch was registered to complete in October 2026, 2 months ago, and is still under construction. Over the last year of inspections it has added about 3.7 points a month. Kept at that rate, the site would reach 100% around April 2028.

0%25%50%75%100%2026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

22 October 2026

32%+12 pts

  • Monarch construction site, inspection photo 1, 22 October 2026
  • Monarch construction site, inspection photo 2, 22 October 2026
  • Monarch construction site, inspection photo 3, 22 October 2026
  • Monarch construction site, inspection photo 4, 22 October 2026

26 August 2026

20%+12 pts

  • Monarch construction site, inspection photo 1, 26 August 2026
  • Monarch construction site, inspection photo 2, 26 August 2026
  • Monarch construction site, inspection photo 3, 26 August 2026
  • Monarch construction site, inspection photo 4, 26 August 2026

20 April 2026

7.6%+5.7 pts

  • Monarch construction site, inspection photo 1, 20 April 2026
  • Monarch construction site, inspection photo 2, 20 April 2026
  • Monarch construction site, inspection photo 3, 20 April 2026
  • Monarch construction site, inspection photo 4, 20 April 2026

16 February 2026

1.9%+1.9 pts

  • Monarch construction site, inspection photo 1, 16 February 2026
  • Monarch construction site, inspection photo 2, 16 February 2026
  • Monarch construction site, inspection photo 3, 16 February 2026
  • Monarch construction site, inspection photo 4, 16 February 2026

2 August 2025

0%

  • Monarch construction site, inspection photo 1, 2 August 2025
  • Monarch construction site, inspection photo 2, 2 August 2025
  • Monarch construction site, inspection photo 3, 2 August 2025

19 March 2025

0%

  • Monarch construction site, inspection photo 1, 19 March 2025
  • Monarch construction site, inspection photo 2, 19 March 2025

All 31 site photos, by inspection date

Context

Motor City has 11 projects under construction, 20% built on average.

Own a unit in Monarch?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Monarch handover date?
The registered completion date was October 2026, and the register still lists Monarch as under construction. At the pace of its recent inspections the site would reach 100% around April 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Monarch?
Monarch was 32% built at the site inspection on 22 October 2026. The site has been inspected 6 times since March 2025. The Land Department took 31 site photos at its inspections.
Is Monarch delayed?
Yes. Its registered completion date of October 2026 has passed and the project is still listed as under construction.
Who is building Monarch?
The registered developer is Zane Developments.
Which bank holds the escrow account for Monarch?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.