Capital One construction progress

The registered completion date for Capital One in Motor City is February 2027. At the last site inspection, in October 2026, it was 20% built. The developer is The Circuit Real Estate Development.

20%

Built, at the site inspection of 8 October 2026

Running behind its date

Registered completion date
February 2027
Finish at recent pace
August 2030
Construction started
December 2024
First registered
December 2024
Developer
The Circuit Real Estate Development
Community
Motor City
Units
257
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
كابيتال ون
Project number
3407
Site inspections
5

Schedule

Between December 2025 and October 2026 the site added about 1.7 points a month. At that rate it would finish around August 2030, more than three months after its registered date of February 2027.

0%25%50%75%100%202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

8 October 2026

20%+8.9 pts

  • Capital One construction site, inspection photo 1, 8 October 2026
  • Capital One construction site, inspection photo 2, 8 October 2026
  • Capital One construction site, inspection photo 3, 8 October 2026
  • Capital One construction site, inspection photo 4, 8 October 2026

2 July 2026

11%+4.8 pts

  • Capital One construction site, inspection photo 1, 2 July 2026
  • Capital One construction site, inspection photo 2, 2 July 2026
  • Capital One construction site, inspection photo 3, 2 July 2026
  • Capital One construction site, inspection photo 4, 2 July 2026

23 March 2026

6.3%+3.7 pts

  • Capital One construction site, inspection photo 1, 23 March 2026
  • Capital One construction site, inspection photo 2, 23 March 2026
  • Capital One construction site, inspection photo 3, 23 March 2026
  • Capital One construction site, inspection photo 4, 23 March 2026

3 December 2025

2.6%+2.6 pts

  • Capital One construction site, inspection photo 1, 3 December 2025
  • Capital One construction site, inspection photo 2, 3 December 2025

19 November 2024

0%

  • Capital One construction site, inspection photo 1, 19 November 2024
  • Capital One construction site, inspection photo 2, 19 November 2024

All 22 site photos, by inspection date

Context

Motor City has 11 projects under construction, 20% built on average.

Own a unit in Capital One?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Capital One handover date?
The registered completion date is February 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2030. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Capital One?
Capital One was 20% built at the site inspection on 8 October 2026. The site has been inspected 5 times since November 2024. The Land Department took 22 site photos at its inspections.
Is Capital One delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of February 2027.
Who is building Capital One?
The registered developer is The Circuit Real Estate Development.
Which bank holds the escrow account for Capital One?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.