The Community Motor City construction progress

The Community Motor City in Motor City was registered to complete in October 2025 and is still under construction. At the last site inspection, in May 2026, it was 95% built. The developer is Aqua Properties.

95%

Built, at the site inspection of 12 May 2026

13 months past its registered completion date

Registered completion date
October 2025
Finish at recent pace
July 2026
Construction started
November 2022
First registered
January 2023
Community
Motor City
Units
433
Escrow bank
Mashreq Bank
Name in Arabic
كوميونيتي موتور سيتي
Project number
2532
Site inspections
6

Schedule

The Community Motor City was registered to complete in October 2025, 13 months ago, and is still under construction. Over the last year of inspections it has added about 2.4 points a month. Kept at that rate, the site would reach 100% around July 2026.

0%25%50%75%100%2023202420252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

12 May 2026

95%+45 pts

  • The Community Motor City construction site, inspection photo 1, 12 May 2026
  • The Community Motor City construction site, inspection photo 2, 12 May 2026
  • The Community Motor City construction site, inspection photo 3, 12 May 2026
  • The Community Motor City construction site, inspection photo 4, 12 May 2026

24 October 2024

50%+10 pts

  • The Community Motor City construction site, inspection photo 1, 24 October 2024
  • The Community Motor City construction site, inspection photo 2, 24 October 2024
  • The Community Motor City construction site, inspection photo 3, 24 October 2024
  • The Community Motor City construction site, inspection photo 4, 24 October 2024

11 July 2024

40%+9.9 pts

  • The Community Motor City construction site, inspection photo 1, 11 July 2024
  • The Community Motor City construction site, inspection photo 2, 11 July 2024
  • The Community Motor City construction site, inspection photo 3, 11 July 2024
  • The Community Motor City construction site, inspection photo 4, 11 July 2024

14 March 2024

30%+18 pts

  • The Community Motor City construction site, inspection photo 1, 14 March 2024
  • The Community Motor City construction site, inspection photo 2, 14 March 2024
  • The Community Motor City construction site, inspection photo 3, 14 March 2024
  • The Community Motor City construction site, inspection photo 4, 14 March 2024

23 November 2023

12%+12 pts

  • The Community Motor City construction site, inspection photo 1, 23 November 2023
  • The Community Motor City construction site, inspection photo 2, 23 November 2023
  • The Community Motor City construction site, inspection photo 3, 23 November 2023
  • The Community Motor City construction site, inspection photo 4, 23 November 2023

6 December 2022

0%

  • The Community Motor City construction site, inspection photo 1, 6 December 2022
  • The Community Motor City construction site, inspection photo 2, 6 December 2022
  • The Community Motor City construction site, inspection photo 3, 6 December 2022
  • The Community Motor City construction site, inspection photo 4, 6 December 2022

All 41 site photos, by inspection date

Context

Motor City has 11 projects under construction, 20% built on average.

Aqua Properties has 3 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in The Community Motor City?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the The Community Motor City handover date?
The registered completion date was October 2025, and the register still lists The Community Motor City as under construction. At the pace of its recent inspections the site would reach 100% around July 2026. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on The Community Motor City?
The Community Motor City was 95% built at the site inspection on 12 May 2026. The site has been inspected 6 times since December 2022. The Land Department took 41 site photos at its inspections.
Is The Community Motor City delayed?
Yes. Its registered completion date of October 2025 has passed and the project is still listed as under construction.
Who is building The Community Motor City?
The registered developer is Aqua Properties. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for The Community Motor City?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.