Sierra By Iman construction progress
The registered completion date for Sierra By Iman in Motor City is June 2029. At the last site inspection, in August 2026, it was 3.7% built. The developer is Iman Developers.
3.7%
Built, at the site inspection of 10 August 2026
Running behind its date
- Registered completion date
- June 2029
- Finish at recent pace
- March 2051
- Construction started
- November 2025
- First registered
- October 2025
- Developer
- Iman Developers
- Community
- Motor City
- Units
- 598
- Escrow bank
- Dubai Islamic Bank
- Name in Arabic
- سيرا باي ايمان
- Project number
- 3835
- Site inspections
- 3
Schedule
Between August 2025 and August 2026 the site added about 0.3 points a month. At that rate it would finish around March 2051, more than three months after its registered date of June 2029.
Site inspections
10 August 2026
3.7%+3.5 pts
14 January 2026
0.2%+0.2 pts
26 August 2025
0%
Context
Motor City has 11 projects under construction, 20% built on average.
Iman Developers has 10 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Sierra By Iman?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Sierra By Iman handover date?
- The registered completion date is June 2029. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around March 2051. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Sierra By Iman?
- Sierra By Iman was 3.7% built at the site inspection on 10 August 2026. The site has been inspected 3 times since August 2025. The Land Department took 10 site photos at its inspections.
- Is Sierra By Iman delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2029.
- Who is building Sierra By Iman?
- The registered developer is Iman Developers. It has 9 other projects under construction in Dubai.
- Which bank holds the escrow account for Sierra By Iman?
- Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- 10 Oxford By ImanAlso by Iman Developers. 91%.
- Gardens 2Also by Iman Developers. 68%, Due December 2025, passed.
- One Park Central By ImanAlso by Iman Developers. 32%, Due June 2027.
- One Sky Park By ImanAlso by Iman Developers. 22%, Due March 2028.
- The Community Motor CityNearby in Motor City. 95%, Due October 2025, passed.
- Sobha OrbisNearby in Motor City. 22%, Due December 2028.
- TakayaNearby in Motor City. 16%, Due December 2027.
- Sobha SolisNearby in Motor City. 18%, Due December 2028.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.