Ananda Residences construction progress
Ananda Residences in Motor City is 3.2% built at the Land Department inspection of October 2026. Developer Tiger Properties. Completion registered for May 2028.
3.2%
Built, at the Land Department site inspection of 7 October 2026
Running behind its date
- Completion date (Land Department)
- May 2028
- Finish at recent pace
- March 2052
- Construction started
- February 2025
- Registered with the Land Department
- September 2025
- Developer
- Tiger Properties
- Community
- Motor City
- Units
- 1,027
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- اناندا ريزدنسيس
- Land Department project number
- 3535
- Land Department site inspections
- 5
Schedule
Between December 2025 and October 2026 the site added about 0.3 points a month. At that rate it would finish around March 2052, more than three months after the May 2028 date registered with the Land Department.
Site inspections
7 October 2026
3.2%+0.7 pts
5 August 2026
2.5%+0.4 pts
20 April 2026
2.1%+1.8 pts
31 December 2025
0.3%+0.3 pts
10 February 2025
0%
Context
Motor City has 11 projects under construction, 18% built on average.
Tiger Properties has 9 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Ananda Residences?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Ananda Residences be completed?
- The completion date registered with the Dubai Land Department is May 2028. At the pace of its recent inspections the site would reach 100% around March 2052. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Ananda Residences is built?
- 3.2%, measured at the Land Department site inspection on 7 October 2026. The Land Department engineers have inspected the site 5 times since February 2025.
- Is Ananda Residences delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of May 2028.
- Who is building Ananda Residences?
- The registered developer is Tiger Properties. It has 8 other projects under construction in Dubai.
- Which bank holds the escrow account for Ananda Residences?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Tiger Sky TowerAlso by Tiger Properties. 10%.
- Altai TowerAlso by Tiger Properties. 98%, Due January 2026, passed.
- Volga TowerAlso by Tiger Properties. 51%.
- Red SquareAlso by Tiger Properties. 27%.
- The Community Motor CityNearby in Motor City. 95%.
- Sobha OrbisNearby in Motor City. 18%, Due December 2028.
- TakayaNearby in Motor City. 16%, Due December 2027.
- Sobha SolisNearby in Motor City. 13%, Due December 2028.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.










.jpeg&w=3840&q=75)