Ananda Residences construction progress

The registered completion date for Ananda Residences in Motor City is May 2028. At the last site inspection, in October 2026, it was 3.2% built. The developer is Tiger Properties.

3.2%

Built, at the site inspection of 7 October 2026

Running behind its date

Registered completion date
May 2028
Finish at recent pace
March 2052
Construction started
February 2025
First registered
September 2025
Community
Motor City
Units
1,027
Escrow bank
First Abu Dhabi Bank
Name in Arabic
اناندا ريزدنسيس
Project number
3535
Site inspections
5

Schedule

Between December 2025 and October 2026 the site added about 0.3 points a month. At that rate it would finish around March 2052, more than three months after its registered date of May 2028.

0%25%50%75%100%202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

7 October 2026

3.2%+0.7 pts

  • Ananda Residences construction site, inspection photo 1, 7 October 2026
  • Ananda Residences construction site, inspection photo 2, 7 October 2026
  • Ananda Residences construction site, inspection photo 3, 7 October 2026
  • Ananda Residences construction site, inspection photo 4, 7 October 2026

5 August 2026

2.5%+0.4 pts

  • Ananda Residences construction site, inspection photo 1, 5 August 2026
  • Ananda Residences construction site, inspection photo 2, 5 August 2026
  • Ananda Residences construction site, inspection photo 3, 5 August 2026
  • Ananda Residences construction site, inspection photo 4, 5 August 2026

20 April 2026

2.1%+1.8 pts

  • Ananda Residences construction site, inspection photo 1, 20 April 2026
  • Ananda Residences construction site, inspection photo 2, 20 April 2026
  • Ananda Residences construction site, inspection photo 3, 20 April 2026

31 December 2025

0.3%+0.3 pts

  • Ananda Residences construction site, inspection photo 1, 31 December 2025
  • Ananda Residences construction site, inspection photo 2, 31 December 2025
  • Ananda Residences construction site, inspection photo 3, 31 December 2025
  • Ananda Residences construction site, inspection photo 4, 31 December 2025

10 February 2025

0%

  • Ananda Residences construction site, inspection photo 1, 10 February 2025
  • Ananda Residences construction site, inspection photo 2, 10 February 2025

All 19 site photos, by inspection date

Context

Motor City has 11 projects under construction, 20% built on average.

Tiger Properties has 8 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Ananda Residences?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Ananda Residences handover date?
The registered completion date is May 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around March 2052. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Ananda Residences?
Ananda Residences was 3.2% built at the site inspection on 7 October 2026. The site has been inspected 5 times since February 2025. The Land Department took 19 site photos at its inspections.
Is Ananda Residences delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of May 2028.
Who is building Ananda Residences?
The registered developer is Tiger Properties. It has 7 other projects under construction in Dubai.
Which bank holds the escrow account for Ananda Residences?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.