Ananda Residences construction progress

Ananda Residences in Motor City is 3.2% built at the Land Department inspection of October 2026. Developer Tiger Properties. Completion registered for May 2028.

3.2%

Built, at the Land Department site inspection of 7 October 2026

Running behind its date

Completion date (Land Department)
May 2028
Finish at recent pace
March 2052
Construction started
February 2025
Registered with the Land Department
September 2025
Community
Motor City
Units
1,027
Escrow bank
First Abu Dhabi Bank
Name in Arabic
اناندا ريزدنسيس
Land Department project number
3535
Land Department site inspections
5

Schedule

Between December 2025 and October 2026 the site added about 0.3 points a month. At that rate it would finish around March 2052, more than three months after the May 2028 date registered with the Land Department.

0%25%50%75%100%202620272028
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

7 October 2026

3.2%+0.7 pts

  • Ananda Residences construction site, Land Department inspection photo 1, 7 October 2026
  • Ananda Residences construction site, Land Department inspection photo 2, 7 October 2026
  • Ananda Residences construction site, Land Department inspection photo 3, 7 October 2026
  • Ananda Residences construction site, Land Department inspection photo 4, 7 October 2026

5 August 2026

2.5%+0.4 pts

  • Ananda Residences construction site, Land Department inspection photo 1, 5 August 2026
  • Ananda Residences construction site, Land Department inspection photo 2, 5 August 2026
  • Ananda Residences construction site, Land Department inspection photo 3, 5 August 2026
  • Ananda Residences construction site, Land Department inspection photo 4, 5 August 2026

20 April 2026

2.1%+1.8 pts

  • Ananda Residences construction site, Land Department inspection photo 1, 20 April 2026
  • Ananda Residences construction site, Land Department inspection photo 2, 20 April 2026
  • Ananda Residences construction site, Land Department inspection photo 3, 20 April 2026

31 December 2025

0.3%+0.3 pts

  • Ananda Residences construction site, Land Department inspection photo 1, 31 December 2025
  • Ananda Residences construction site, Land Department inspection photo 2, 31 December 2025
  • Ananda Residences construction site, Land Department inspection photo 3, 31 December 2025
  • Ananda Residences construction site, Land Department inspection photo 4, 31 December 2025

10 February 2025

0%

  • Ananda Residences construction site, Land Department inspection photo 1, 10 February 2025
  • Ananda Residences construction site, Land Department inspection photo 2, 10 February 2025

All 19 site photos, by inspection date

Context

Motor City has 11 projects under construction, 18% built on average.

Tiger Properties has 9 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Ananda Residences?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Ananda Residences be completed?
The completion date registered with the Dubai Land Department is May 2028. At the pace of its recent inspections the site would reach 100% around March 2052. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Ananda Residences is built?
3.2%, measured at the Land Department site inspection on 7 October 2026. The Land Department engineers have inspected the site 5 times since February 2025.
Is Ananda Residences delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of May 2028.
Who is building Ananda Residences?
The registered developer is Tiger Properties. It has 8 other projects under construction in Dubai.
Which bank holds the escrow account for Ananda Residences?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.