Takaya construction progress
Takaya in Motor City is 16% built at the Land Department inspection of August 2026. Developer Takaya Real Estate Development. Completion registered for December 2027.
16%
Built, at the Land Department site inspection of 5 August 2026
Running behind its date
- Completion date (Land Department)
- December 2027
- Finish at recent pace
- October 2031
- Construction started
- July 2024
- Registered with the Land Department
- October 2024
- Developer
- Takaya Real Estate Development
- Community
- Motor City
- Units
- 822
- Escrow bank
- Dubai Islamic Bank
- Name in Arabic
- تاكايا
- Land Department project number
- 3112
- Land Department site inspections
- 5
Schedule
Between October 2025 and August 2026 the site added about 1.3 points a month. At that rate it would finish around October 2031, more than three months after the December 2027 date registered with the Land Department.
Site inspections
5 August 2026
16%+12 pts
3 March 2026
3.7%+1.3 pts
10 October 2025
2.4%+1.3 pts
1 May 2025
1.1%+1.1 pts
3 June 2024
0%
Context
Motor City has 11 projects under construction, 18% built on average. Takaya is behind that average.
Own a unit in Takaya?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Track the handoverQuestions
- When will Takaya be completed?
- The completion date registered with the Dubai Land Department is December 2027. At the pace of its recent inspections the site would reach 100% around October 2031. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Takaya is built?
- 16%, measured at the Land Department site inspection on 5 August 2026. The Land Department engineers have inspected the site 5 times since June 2024.
- Is Takaya delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2027.
- Who is building Takaya?
- The registered developer is Takaya Real Estate Development.
- Which bank holds the escrow account for Takaya?
- Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- The Community Motor CityNearby in Motor City. 95%.
- Sobha OrbisNearby in Motor City. 18%, Due December 2028.
- Sobha SolisNearby in Motor City. 13%, Due December 2028.
- Capital OneNearby in Motor City. 11%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.