Sobha Solis construction progress

The registered completion date for Sobha Solis in Motor City is December 2028. At the last site inspection, in October 2026, it was 18% built. The developer is Sobha.

18%

Built, at the site inspection of 22 October 2026

Running behind its date

Registered completion date
December 2028
Finish at recent pace
October 2033
Construction started
October 2024
First registered
January 2025
Developer
Sobha
Community
Motor City
Units
2,351
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
شوبا سوليس
Project number
3334
Site inspections
5

Schedule

Between January 2026 and October 2026 the site added about 1.0 points a month. At that rate it would finish around October 2033, more than three months after its registered date of December 2028.

0%25%50%75%100%2025202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

22 October 2026

18%+4.7 pts

  • Sobha Solis construction site, inspection photo 1, 22 October 2026
  • Sobha Solis construction site, inspection photo 2, 22 October 2026
  • Sobha Solis construction site, inspection photo 3, 22 October 2026
  • Sobha Solis construction site, inspection photo 4, 22 October 2026

5 May 2026

13%+3.9 pts

  • Sobha Solis construction site, inspection photo 1, 5 May 2026
  • Sobha Solis construction site, inspection photo 2, 5 May 2026
  • Sobha Solis construction site, inspection photo 3, 5 May 2026
  • Sobha Solis construction site, inspection photo 4, 5 May 2026

29 January 2026

9.4%+5.7 pts

  • Sobha Solis construction site, inspection photo 1, 29 January 2026
  • Sobha Solis construction site, inspection photo 2, 29 January 2026
  • Sobha Solis construction site, inspection photo 3, 29 January 2026
  • Sobha Solis construction site, inspection photo 4, 29 January 2026

29 September 2025

3.7%+3.7 pts

  • Sobha Solis construction site, inspection photo 1, 29 September 2025
  • Sobha Solis construction site, inspection photo 2, 29 September 2025
  • Sobha Solis construction site, inspection photo 3, 29 September 2025
  • Sobha Solis construction site, inspection photo 4, 29 September 2025

22 October 2024

0%

  • Sobha Solis construction site, inspection photo 1, 22 October 2024
  • Sobha Solis construction site, inspection photo 2, 22 October 2024

All 29 site photos, by inspection date

Context

Motor City has 11 projects under construction, 20% built on average.

Sobha has 27 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Sobha Solis?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Sobha Solis handover date?
The registered completion date is December 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around October 2033. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Sobha Solis?
Sobha Solis was 18% built at the site inspection on 22 October 2026. The site has been inspected 5 times since October 2024. The Land Department took 29 site photos at its inspections.
Is Sobha Solis delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2028.
Who is building Sobha Solis?
The registered developer is Sobha. It has 26 other projects under construction in Dubai.
Which bank holds the escrow account for Sobha Solis?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.