Sobha Solis construction progress
The registered completion date for Sobha Solis in Motor City is December 2028. At the last site inspection, in October 2026, it was 18% built. The developer is Sobha.
18%
Built, at the site inspection of 22 October 2026
Running behind its date
- Registered completion date
- December 2028
- Finish at recent pace
- October 2033
- Construction started
- October 2024
- First registered
- January 2025
- Developer
- Sobha
- Community
- Motor City
- Units
- 2,351
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- شوبا سوليس
- Project number
- 3334
- Site inspections
- 5
Schedule
Between January 2026 and October 2026 the site added about 1.0 points a month. At that rate it would finish around October 2033, more than three months after its registered date of December 2028.
Site inspections
22 October 2026
18%+4.7 pts
5 May 2026
13%+3.9 pts
29 January 2026
9.4%+5.7 pts
29 September 2025
3.7%+3.7 pts
22 October 2024
0%
Context
Motor City has 11 projects under construction, 20% built on average.
Sobha has 27 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Sobha Solis?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Sobha Solis handover date?
- The registered completion date is December 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around October 2033. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Sobha Solis?
- Sobha Solis was 18% built at the site inspection on 22 October 2026. The site has been inspected 5 times since October 2024. The Land Department took 29 site photos at its inspections.
- Is Sobha Solis delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2028.
- Who is building Sobha Solis?
- The registered developer is Sobha. It has 26 other projects under construction in Dubai.
- Which bank holds the escrow account for Sobha Solis?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Sobha Seahaven Tower AAlso by Sobha. 45%, Due April 2028.
- Verde By SobhaAlso by Sobha. 85%, Due June 2027.
- Sobha Creek Vista HeightsAlso by Sobha. 92%.
- Sobha Seahaven Tower B & CAlso by Sobha. 40%, Due October 2028.
- The Community Motor CityNearby in Motor City. 95%, Due October 2025, passed.
- TakayaNearby in Motor City. 16%, Due December 2027.
- Capital OneNearby in Motor City. 20%, Due February 2027.
- 15 CascadeNearby in Motor City. 5.5%, Due September 2028.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)






.jpeg&w=3840&q=75)





.jpeg&w=3840&q=75)