The Oasis - Address Villas - Tierra construction progress

The Oasis - Address Villas - Tierra in Me'aisem Second is 6.8% built at the Land Department inspection of July 2026. Developer Emaar Development. Completion registered for June 2029.

6.8%

Built, at the Land Department site inspection of 21 July 2026

Running behind its date

Completion date (Land Department)
June 2029
Finish at recent pace
July 2038
Construction started
May 2025
Registered with the Land Department
March 2025
Units
487
Escrow bank
Emirates Islamic Bank
Name in Arabic
ذا اويسيس - ادرس فيلا - تييرا
Land Department project number
3580
Land Department site inspections
4

Schedule

Between October 2025 and July 2026 the site added about 0.6 points a month. At that rate it would finish around July 2038, more than three months after the June 2029 date registered with the Land Department.

0%25%50%75%100%2026202720282029
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

21 July 2026

6.8%+2.9 pts

  • The Oasis - Address Villas - Tierra construction site, Land Department inspection photo 1, 21 July 2026
  • The Oasis - Address Villas - Tierra construction site, Land Department inspection photo 2, 21 July 2026
  • The Oasis - Address Villas - Tierra construction site, Land Department inspection photo 3, 21 July 2026
  • The Oasis - Address Villas - Tierra construction site, Land Department inspection photo 4, 21 July 2026

16 March 2026

3.9%+2.9 pts

  • The Oasis - Address Villas - Tierra construction site, Land Department inspection photo 1, 16 March 2026
  • The Oasis - Address Villas - Tierra construction site, Land Department inspection photo 2, 16 March 2026
  • The Oasis - Address Villas - Tierra construction site, Land Department inspection photo 3, 16 March 2026
  • The Oasis - Address Villas - Tierra construction site, Land Department inspection photo 4, 16 March 2026

22 October 2025

1.0%+1.0 pts

  • The Oasis - Address Villas - Tierra construction site, Land Department inspection photo 1, 22 October 2025
  • The Oasis - Address Villas - Tierra construction site, Land Department inspection photo 2, 22 October 2025

25 February 2025

0%

  • The Oasis - Address Villas - Tierra construction site, Land Department inspection photo 1, 25 February 2025
  • The Oasis - Address Villas - Tierra construction site, Land Department inspection photo 2, 25 February 2025

All 18 site photos, by inspection date

Context

Me'aisem Second has 7 projects under construction, 45% built on average.

Emaar Development has 52 projects under construction in Dubai, none past their registered completion dates.

Own a unit in The Oasis - Address Villas - Tierra?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will The Oasis - Address Villas - Tierra be completed?
The completion date registered with the Dubai Land Department is June 2029. At the pace of its recent inspections the site would reach 100% around July 2038. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of The Oasis - Address Villas - Tierra is built?
6.8%, measured at the Land Department site inspection on 21 July 2026. The Land Department engineers have inspected the site 4 times since February 2025.
Is The Oasis - Address Villas - Tierra delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2029.
Who is building The Oasis - Address Villas - Tierra?
The registered developer is Emaar Development. It has 51 other projects under construction in Dubai.
Which bank holds the escrow account for The Oasis - Address Villas - Tierra?
Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.