The Oasis - Palmiera 2 construction progress
No completion date is registered for The Oasis - Palmiera 2 in Me'aisem Second yet. At the last site inspection, in August 2026, it was 77% built. The developer is Emaar Properties.
77%
Built, at the site inspection of 3 August 2026
- Finish at recent pace
- February 2027
- Construction started
- June 2024
- First registered
- April 2024
- Developer
- Emaar Properties
- Community
- Me'aisem Second
- Units
- 56
- Escrow bank
- Emirates Islamic Bank
- Name in Arabic
- ذا اويسيس - بالمييرا 2
- Project number
- 3031
- Site inspections
- 8
Schedule
Since September 2025 The Oasis - Palmiera 2 has added about 3.8 points a month. At that rate the site reaches 100% around February 2027. No completion date is on record to compare it with.
Site inspections
3 August 2026
77%+14 pts
21 April 2026
63%+10 pts
25 December 2025
53%+15 pts
25 September 2025
38%+10 pts
16 June 2025
28%+17 pts
24 March 2025
11%+9.5 pts
29 October 2024
1.8%+1.2 pts
1 April 2024
0.6%
Context
Me'aisem Second has 7 projects under construction, 45% built on average.
Emaar Properties has 7 projects under construction in Dubai, none past their registered completion dates.
Own a unit in The Oasis - Palmiera 2?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the The Oasis - Palmiera 2 handover date?
- No completion date is on record for The Oasis - Palmiera 2 yet. Handover follows completion, so there is no date to give.
- What is the latest construction update on The Oasis - Palmiera 2?
- The Oasis - Palmiera 2 was 77% built at the site inspection on 3 August 2026. The site has been inspected 8 times since April 2024. The Land Department took 53 site photos at its inspections.
- Who is building The Oasis - Palmiera 2?
- The registered developer is Emaar Properties. It has 6 other projects under construction in Dubai.
- Which bank holds the escrow account for The Oasis - Palmiera 2?
- Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Marina ShoresAlso by Emaar Properties. 87%, Due December 2026.
- The Oasis - PalmieraAlso by Emaar Properties. 82%.
- The Oasis - MirageAlso by Emaar Properties. 47%.
- The Oasis - Palmiera 3Also by Emaar Properties. 73%, Due October 2028.
- The Oasis - Address Villas - TierraNearby in Me'aisem Second. 6.8%, Due June 2029.
- The Oasis - Palace Villas - OstraNearby in Me'aisem Second. 6.5%, Due September 2029.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.


.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)












.jpeg&w=3840&q=75)

