The Oasis - Palmiera 2 construction progress
The Oasis - Palmiera 2 in Me'aisem Second is 77% built at the Land Department inspection of August 2026. Developer Emaar Properties.
77%
Built, at the Land Department site inspection of 3 August 2026
- Finish at recent pace
- February 2027
- Construction started
- June 2024
- Registered with the Land Department
- April 2024
- Developer
- Emaar Properties
- Community
- Me'aisem Second
- Units
- 56
- Escrow bank
- Emirates Islamic Bank
- Name in Arabic
- ذا اويسيس - بالمييرا 2
- Land Department project number
- 3031
- Land Department site inspections
- 8
Schedule
Since September 2025 The Oasis - Palmiera 2 has added about 3.8 points a month. At that rate the site reaches 100% around February 2027. The Land Department has no completion date on record to compare it with.
Site inspections
3 August 2026
77%+14 pts
21 April 2026
63%+10 pts
25 December 2025
53%+15 pts
25 September 2025
38%+10 pts
16 June 2025
28%+17 pts
24 March 2025
11%+9.5 pts
29 October 2024
1.8%+1.2 pts
1 April 2024
0.6%
Context
Me'aisem Second has 7 projects under construction, 45% built on average. The Oasis - Palmiera 2 is ahead of that average.
Emaar Properties has 7 projects under construction in Dubai, none past their registered completion dates.
Own a unit in The Oasis - Palmiera 2?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Track the handoverQuestions
- When will The Oasis - Palmiera 2 be completed?
- The Land Department has no completion date on record for The Oasis - Palmiera 2 yet. It appears once the developer registers the construction timeline.
- How much of The Oasis - Palmiera 2 is built?
- 77%, measured at the Land Department site inspection on 3 August 2026. The Land Department engineers have inspected the site 8 times since April 2024.
- Who is building The Oasis - Palmiera 2?
- The registered developer is Emaar Properties. It has 6 other projects under construction in Dubai.
- Which bank holds the escrow account for The Oasis - Palmiera 2?
- Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Marina ShoresAlso by Emaar Properties. 87%, Due December 2026.
- The Oasis - PalmieraAlso by Emaar Properties. 82%.
- The Oasis - MirageAlso by Emaar Properties. 47%.
- The Oasis - Palmiera 3Also by Emaar Properties. 73%, Due October 2028.
- The Oasis - Address Villas - TierraNearby in Me'aisem Second. 6.8%, Due June 2029.
- The Oasis - Palace Villas - OstraNearby in Me'aisem Second. 6.5%, Due September 2029.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.

.jpg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)














.jpeg&w=3840&q=75)