The Oasis - Mirage construction progress

No completion date is registered for The Oasis - Mirage in Me'aisem Second yet. At the last site inspection, in June 2026, it was 47% built. The developer is Emaar Properties.

47%

Built, at the site inspection of 29 June 2026

Finish at recent pace
September 2027
Construction started
April 2024
First registered
April 2024
Units
204
Escrow bank
First Abu Dhabi Bank
Name in Arabic
ذا اويسيس - ميراج
Project number
3025
Site inspections
7

Schedule

Since July 2025 The Oasis - Mirage has added about 3.7 points a month. At that rate the site reaches 100% around September 2027. No completion date is on record to compare it with.

0%25%50%75%100%20252026
Progress at each site inspection

Site inspections

29 June 2026

47%+16 pts

  • The Oasis - Mirage construction site, inspection photo 1, 29 June 2026
  • The Oasis - Mirage construction site, inspection photo 2, 29 June 2026
  • The Oasis - Mirage construction site, inspection photo 3, 29 June 2026
  • The Oasis - Mirage construction site, inspection photo 4, 29 June 2026

7 May 2026

31%+11 pts

  • The Oasis - Mirage construction site, inspection photo 1, 7 May 2026
  • The Oasis - Mirage construction site, inspection photo 2, 7 May 2026
  • The Oasis - Mirage construction site, inspection photo 3, 7 May 2026
  • The Oasis - Mirage construction site, inspection photo 4, 7 May 2026

11 November 2025

19%+14 pts

  • The Oasis - Mirage construction site, inspection photo 1, 11 November 2025
  • The Oasis - Mirage construction site, inspection photo 2, 11 November 2025
  • The Oasis - Mirage construction site, inspection photo 3, 11 November 2025
  • The Oasis - Mirage construction site, inspection photo 4, 11 November 2025

22 July 2025

5.2%+2.8 pts

  • The Oasis - Mirage construction site, inspection photo 1, 22 July 2025
  • The Oasis - Mirage construction site, inspection photo 2, 22 July 2025
  • The Oasis - Mirage construction site, inspection photo 3, 22 July 2025
  • The Oasis - Mirage construction site, inspection photo 4, 22 July 2025

3 March 2025

2.3%+0.6 pts

  • The Oasis - Mirage construction site, inspection photo 1, 3 March 2025
  • The Oasis - Mirage construction site, inspection photo 2, 3 March 2025
  • The Oasis - Mirage construction site, inspection photo 3, 3 March 2025
  • The Oasis - Mirage construction site, inspection photo 4, 3 March 2025

16 October 2024

1.7%+1.2 pts

  • The Oasis - Mirage construction site, inspection photo 1, 16 October 2024
  • The Oasis - Mirage construction site, inspection photo 2, 16 October 2024

1 April 2024

0.5%

  • The Oasis - Mirage construction site, inspection photo 1, 1 April 2024
  • The Oasis - Mirage construction site, inspection photo 2, 1 April 2024

All 39 site photos, by inspection date

Context

Me'aisem Second has 7 projects under construction, 45% built on average.

Emaar Properties has 7 projects under construction in Dubai, none past their registered completion dates.

Own a unit in The Oasis - Mirage?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the The Oasis - Mirage handover date?
No completion date is on record for The Oasis - Mirage yet. Handover follows completion, so there is no date to give.
What is the latest construction update on The Oasis - Mirage?
The Oasis - Mirage was 47% built at the site inspection on 29 June 2026. The site has been inspected 7 times since April 2024. The Land Department took 39 site photos at its inspections.
Who is building The Oasis - Mirage?
The registered developer is Emaar Properties. It has 6 other projects under construction in Dubai.
Which bank holds the escrow account for The Oasis - Mirage?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.