The Oasis - Address Villas - Tierra construction photos

18 photos taken by Dubai Land Department engineers at 4 site inspections, newest first. The percentage is how much of The Oasis - Address Villas - Tierra was built on the day of each visit.

21 July 20266.8% built

16 March 20263.9% built

22 October 20251.0% built

25 February 20250% built

Back to The Oasis - Address Villas - Tierra construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.