The Oasis - Palmiera 3 construction progress
The Oasis - Palmiera 3 in Me'aisem Second is 73% built at the Land Department inspection of June 2026. Developer Emaar Properties. Completion registered for October 2028.
73%
Built, at the Land Department site inspection of 9 June 2026
On pace for its date
- Completion date (Land Department)
- October 2028
- Finish at recent pace
- January 2027
- Construction started
- August 2024
- Registered with the Land Department
- August 2024
- Developer
- Emaar Properties
- Community
- Me'aisem Second
- Units
- 59
- Escrow bank
- Dubai Islamic Bank
- Name in Arabic
- ذا أويسيس - بالميرا 3
- Land Department project number
- 3221
- Land Department site inspections
- 6
Schedule
Since October 2025 The Oasis - Palmiera 3 has added about 3.8 points a month. That puts 100% around January 2027, within three months of its registered completion date of October 2028.
Site inspections
9 June 2026
73%+10 pts
4 February 2026
62%+21 pts
1 October 2025
41%+15 pts
28 May 2025
26%+20 pts
28 November 2024
6.6%+5.2 pts
5 August 2024
1.4%
Context
Me'aisem Second has 7 projects under construction, 45% built on average.
Emaar Properties has 7 projects under construction in Dubai, none past their registered completion dates.
Own a unit in The Oasis - Palmiera 3?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will The Oasis - Palmiera 3 be completed?
- The completion date registered with the Dubai Land Department is October 2028. At the pace of its recent inspections the site would reach 100% around January 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of The Oasis - Palmiera 3 is built?
- 73%, measured at the Land Department site inspection on 9 June 2026. The Land Department engineers have inspected the site 6 times since August 2024.
- Is The Oasis - Palmiera 3 delayed?
- Not on current figures. At the rate of the last year it finishes within three months of its registered date of October 2028.
- Who is building The Oasis - Palmiera 3?
- The registered developer is Emaar Properties. It has 6 other projects under construction in Dubai.
- Which bank holds the escrow account for The Oasis - Palmiera 3?
- Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Marina ShoresAlso by Emaar Properties. 87%, Due December 2026.
- The Oasis - PalmieraAlso by Emaar Properties. 82%.
- The Oasis - MirageAlso by Emaar Properties. 47%.
- The Oasis - Palmiera 2Also by Emaar Properties. 77%.
- The Oasis - Address Villas - TierraNearby in Me'aisem Second. 6.8%, Due June 2029.
- The Oasis - Palace Villas - OstraNearby in Me'aisem Second. 6.5%, Due September 2029.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)





.jpeg&w=3840&q=75)