The Oasis - Palmiera construction progress
The Oasis - Palmiera in Me'aisem Second is 82% built at the Land Department inspection of July 2026. Developer Emaar Properties.
82%
Built, at the Land Department site inspection of 20 July 2026
- Finish at recent pace
- November 2026
- Construction started
- August 2023
- Registered with the Land Department
- July 2023
- Developer
- Emaar Properties
- Community
- Me'aisem Second
- Units
- 265
- Escrow bank
- Emirates NBD
- Name in Arabic
- ذا اويسيس - بالمييرا
- Land Department project number
- 2732
- Land Department site inspections
- 8
Schedule
Since October 2025 The Oasis - Palmiera has added about 4.2 points a month. At that rate the site reaches 100% around November 2026. The Land Department has no completion date on record to compare it with.
Site inspections
20 July 2026
82%+9.2 pts
27 March 2026
73%+12 pts
25 November 2025
61%+19 pts
1 October 2025
42%+8.2 pts
3 June 2025
34%+11 pts
24 February 2025
22%+16 pts
15 October 2024
6.5%+6.5 pts
25 July 2023
0%
Context
Me'aisem Second has 7 projects under construction, 45% built on average.
Emaar Properties has 7 projects under construction in Dubai, none past their registered completion dates.
Own a unit in The Oasis - Palmiera?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will The Oasis - Palmiera be completed?
- The Land Department has no completion date on record for The Oasis - Palmiera yet.
- How much of The Oasis - Palmiera is built?
- 82%, measured at the Land Department site inspection on 20 July 2026. The Land Department engineers have inspected the site 8 times since July 2023.
- Who is building The Oasis - Palmiera?
- The registered developer is Emaar Properties. It has 6 other projects under construction in Dubai.
- Which bank holds the escrow account for The Oasis - Palmiera?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Marina ShoresAlso by Emaar Properties. 87%, Due December 2026.
- The Oasis - MirageAlso by Emaar Properties. 47%.
- The Oasis - Palmiera 2Also by Emaar Properties. 77%.
- The Oasis - Palmiera 3Also by Emaar Properties. 73%, Due October 2028.
- The Oasis - Address Villas - TierraNearby in Me'aisem Second. 6.8%, Due June 2029.
- The Oasis - Palace Villas - OstraNearby in Me'aisem Second. 6.5%, Due September 2029.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.










.jpeg&w=3840&q=75)





.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)