Skip to content

Samana Barari Lagoons construction progress

The registered completion date for Samana Barari Lagoons in Majan is March 2028. At the last site inspection, in October 2026, it was 17% built. The developer is Samana Signature Real Estate Developments.

17%

Built, at the site inspection of 20 October 2026

Running behind its date

Registered completion date
March 2028
Finish at recent pace
July 2034
Construction started
April 2025
First registered
December 2024
Community
Majan
Units
601
Escrow bank
The National Bank of Fujairah
Name in Arabic
سامانا براري لاجونز
Project number
3422
Site inspections
7

Schedule

Between October 2025 and October 2026 the site added about 0.9 points a month. At that rate it would finish around July 2034, more than three months after its registered date of March 2028.

0%25%50%75%100%2025202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

20 October 2026

17%+4.7 pts

  • Samana Barari Lagoons construction site, inspection photo 1, 20 October 2026
  • Samana Barari Lagoons construction site, inspection photo 2, 20 October 2026
  • Samana Barari Lagoons construction site, inspection photo 3, 20 October 2026
  • Samana Barari Lagoons construction site, inspection photo 4, 20 October 2026

2 June 2026

12%+2.0 pts

  • Samana Barari Lagoons construction site, inspection photo 1, 2 June 2026
  • Samana Barari Lagoons construction site, inspection photo 2, 2 June 2026
  • Samana Barari Lagoons construction site, inspection photo 3, 2 June 2026
  • Samana Barari Lagoons construction site, inspection photo 4, 2 June 2026

3 February 2026

9.9%+4.0 pts

  • Samana Barari Lagoons construction site, inspection photo 1, 3 February 2026
  • Samana Barari Lagoons construction site, inspection photo 2, 3 February 2026
  • Samana Barari Lagoons construction site, inspection photo 3, 3 February 2026
  • Samana Barari Lagoons construction site, inspection photo 4, 3 February 2026

27 October 2025

5.9%+1.9 pts

  • Samana Barari Lagoons construction site, inspection photo 1, 27 October 2025
  • Samana Barari Lagoons construction site, inspection photo 2, 27 October 2025
  • Samana Barari Lagoons construction site, inspection photo 3, 27 October 2025
  • Samana Barari Lagoons construction site, inspection photo 4, 27 October 2025

3 July 2025

4.0%+2.3 pts

  • Samana Barari Lagoons construction site, inspection photo 1, 3 July 2025
  • Samana Barari Lagoons construction site, inspection photo 2, 3 July 2025
  • Samana Barari Lagoons construction site, inspection photo 3, 3 July 2025
  • Samana Barari Lagoons construction site, inspection photo 4, 3 July 2025

10 March 2025

1.8%+1.8 pts

  • Samana Barari Lagoons construction site, inspection photo 1, 10 March 2025
  • Samana Barari Lagoons construction site, inspection photo 2, 10 March 2025
  • Samana Barari Lagoons construction site, inspection photo 3, 10 March 2025

21 November 2024

0%

  • Samana Barari Lagoons construction site, inspection photo 1, 21 November 2024
  • Samana Barari Lagoons construction site, inspection photo 2, 21 November 2024

All 28 site photos, by inspection date

Context

Majan has 25 projects under construction, 28% built on average.

Samana Signature Real Estate Developments has 12 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Samana Barari Lagoons?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Samana Barari Lagoons handover date?
The registered completion date is March 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around July 2034. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Samana Barari Lagoons?
Samana Barari Lagoons was 17% built at the site inspection on 20 October 2026. The site has been inspected 7 times since November 2024. The Land Department took 28 site photos at its inspections.
Is Samana Barari Lagoons delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2028.
Who is building Samana Barari Lagoons?
The registered developer is Samana Signature Real Estate Developments. It has 11 other projects under construction in Dubai.
Which bank holds the escrow account for Samana Barari Lagoons?
The National Bank of Fujairah. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.