Samana Barari Views construction progress

The registered completion date for Samana Barari Views in Majan is March 2027. At the last site inspection, in October 2026, it was 32% built. The developer is Samana International Real Estate Development.

32%

Built, at the site inspection of 28 October 2026

Running behind its date

Registered completion date
March 2027
Finish at recent pace
August 2030
Construction started
February 2024
First registered
December 2023
Community
Majan
Units
669
Escrow bank
Dubai Islamic Bank
Name in Arabic
سمانا براري فيوز
Project number
2835
Site inspections
7

Schedule

Between October 2025 and October 2026 the site added about 1.5 points a month. At that rate it would finish around August 2030, more than three months after its registered date of March 2027.

0%25%50%75%100%2024202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

28 October 2026

32%+5.6 pts

  • Samana Barari Views construction site, inspection photo 1, 28 October 2026
  • Samana Barari Views construction site, inspection photo 2, 28 October 2026
  • Samana Barari Views construction site, inspection photo 3, 28 October 2026
  • Samana Barari Views construction site, inspection photo 4, 28 October 2026

19 May 2026

27%+2.9 pts

  • Samana Barari Views construction site, inspection photo 1, 19 May 2026
  • Samana Barari Views construction site, inspection photo 2, 19 May 2026
  • Samana Barari Views construction site, inspection photo 3, 19 May 2026
  • Samana Barari Views construction site, inspection photo 4, 19 May 2026

28 January 2026

24%+9.2 pts

  • Samana Barari Views construction site, inspection photo 1, 28 January 2026
  • Samana Barari Views construction site, inspection photo 2, 28 January 2026
  • Samana Barari Views construction site, inspection photo 3, 28 January 2026
  • Samana Barari Views construction site, inspection photo 4, 28 January 2026

30 October 2025

15%+4.1 pts

  • Samana Barari Views construction site, inspection photo 1, 30 October 2025
  • Samana Barari Views construction site, inspection photo 2, 30 October 2025
  • Samana Barari Views construction site, inspection photo 3, 30 October 2025
  • Samana Barari Views construction site, inspection photo 4, 30 October 2025

3 July 2025

11%+5.4 pts

  • Samana Barari Views construction site, inspection photo 1, 3 July 2025
  • Samana Barari Views construction site, inspection photo 2, 3 July 2025
  • Samana Barari Views construction site, inspection photo 3, 3 July 2025
  • Samana Barari Views construction site, inspection photo 4, 3 July 2025

14 November 2024

5.3%+5.3 pts

  • Samana Barari Views construction site, inspection photo 1, 14 November 2024
  • Samana Barari Views construction site, inspection photo 2, 14 November 2024
  • Samana Barari Views construction site, inspection photo 3, 14 November 2024
  • Samana Barari Views construction site, inspection photo 4, 14 November 2024

1 November 2023

0%

  • Samana Barari Views construction site, inspection photo 1, 1 November 2023
  • Samana Barari Views construction site, inspection photo 2, 1 November 2023

All 36 site photos, by inspection date

Context

Majan has 25 projects under construction, 28% built on average.

Samana International Real Estate Development has 14 projects under construction in Dubai; 2 have passed their registered completion date.

Own a unit in Samana Barari Views?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Samana Barari Views handover date?
The registered completion date is March 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2030. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Samana Barari Views?
Samana Barari Views was 32% built at the site inspection on 28 October 2026. The site has been inspected 7 times since November 2023. The Land Department took 36 site photos at its inspections.
Is Samana Barari Views delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2027.
Who is building Samana Barari Views?
The registered developer is Samana International Real Estate Development. It has 13 other projects under construction in Dubai.
Which bank holds the escrow account for Samana Barari Views?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.