Samana Barari Views construction progress
Samana Barari Views in Majan is 27% built at the Land Department inspection of May 2026. Developer Samana International Real Estate Development. Completion registered for March 2027.
27%
Built, at the Land Department site inspection of 19 May 2026
Running behind its date
- Completion date (Land Department)
- March 2027
- Finish at recent pace
- May 2030
- Construction started
- February 2024
- Registered with the Land Department
- December 2023
- Community
- Majan
- Units
- 669
- Escrow bank
- Dubai Islamic Bank
- Name in Arabic
- سمانا براري فيوز
- Land Department project number
- 2835
- Land Department site inspections
- 6
Schedule
Between July 2025 and May 2026 the site added about 1.5 points a month. At that rate it would finish around May 2030, more than three months after the March 2027 date registered with the Land Department.
Site inspections
19 May 2026
27%+2.9 pts
28 January 2026
24%+9.2 pts
30 October 2025
15%+4.1 pts
3 July 2025
11%+5.4 pts
14 November 2024
5.3%+5.3 pts
1 November 2023
0%
Context
Majan has 25 projects under construction, 24% built on average.
Samana International Real Estate Development has 14 projects under construction in Dubai; 2 have passed their registered completion date.
Own a unit in Samana Barari Views?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Samana Barari Views be completed?
- The completion date registered with the Dubai Land Department is March 2027. At the pace of its recent inspections the site would reach 100% around May 2030. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Samana Barari Views is built?
- 27%, measured at the Land Department site inspection on 19 May 2026. The Land Department engineers have inspected the site 6 times since November 2023.
- Is Samana Barari Views delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2027.
- Who is building Samana Barari Views?
- The registered developer is Samana International Real Estate Development. It has 13 other projects under construction in Dubai.
- Which bank holds the escrow account for Samana Barari Views?
- Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Samana MykonosAlso by Samana International Real Estate Development. 91%, Due April 2026, passed.
- Samana Mykonos SignatureAlso by Samana International Real Estate Development. 80%, Due April 2026, passed.
- Samana Ivy GardensAlso by Samana International Real Estate Development. 41%.
- Samana Golf ViewsAlso by Samana International Real Estate Development. 56%.
- Sherena Residence 2Nearby in Majan. 82%, Due August 2022, passed.
- Barari Parkview By Al MawaredNearby in Majan. 45%, Due December 2027.
- Wadi 645Nearby in Majan. 55%.
- Jade TowerNearby in Majan. 11%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.