Samana Barari Views construction progress
The registered completion date for Samana Barari Views in Majan is March 2027. At the last site inspection, in October 2026, it was 32% built. The developer is Samana International Real Estate Development.
32%
Built, at the site inspection of 28 October 2026
Running behind its date
- Registered completion date
- March 2027
- Finish at recent pace
- August 2030
- Construction started
- February 2024
- First registered
- December 2023
- Community
- Majan
- Units
- 669
- Escrow bank
- Dubai Islamic Bank
- Name in Arabic
- سمانا براري فيوز
- Project number
- 2835
- Site inspections
- 7
Schedule
Between October 2025 and October 2026 the site added about 1.5 points a month. At that rate it would finish around August 2030, more than three months after its registered date of March 2027.
Site inspections
28 October 2026
32%+5.6 pts
19 May 2026
27%+2.9 pts
28 January 2026
24%+9.2 pts
30 October 2025
15%+4.1 pts
3 July 2025
11%+5.4 pts
14 November 2024
5.3%+5.3 pts
1 November 2023
0%
Context
Majan has 25 projects under construction, 28% built on average.
Samana International Real Estate Development has 14 projects under construction in Dubai; 2 have passed their registered completion date.
Own a unit in Samana Barari Views?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Samana Barari Views handover date?
- The registered completion date is March 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2030. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Samana Barari Views?
- Samana Barari Views was 32% built at the site inspection on 28 October 2026. The site has been inspected 7 times since November 2023. The Land Department took 36 site photos at its inspections.
- Is Samana Barari Views delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2027.
- Who is building Samana Barari Views?
- The registered developer is Samana International Real Estate Development. It has 13 other projects under construction in Dubai.
- Which bank holds the escrow account for Samana Barari Views?
- Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Samana MykonosAlso by Samana International Real Estate Development. 91%, Due April 2026, passed.
- Samana Mykonos SignatureAlso by Samana International Real Estate Development. 86%, Due April 2026, passed.
- Samana Ivy GardensAlso by Samana International Real Estate Development. 41%.
- Samana Golf ViewsAlso by Samana International Real Estate Development. 56%.
- Sherena Residence 2Nearby in Majan. 82%, Due August 2022, passed.
- Barari Parkview By Al MawaredNearby in Majan. 45%, Due December 2027.
- Wadi 645Nearby in Majan. 55%.
- Jade TowerNearby in Majan. 11%, Due March 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.










.jpeg&w=3840&q=75)






