Samana Barari Lagoons construction photos
28 photos from 7 site inspections, newest first. The percentage is how much of Samana Barari Lagoons was built on the day of each visit.
20 October 202617% built
2 June 202612% built
3 February 20269.9% built
27 October 20255.9% built
3 July 20254.0% built
10 March 20251.8% built
21 November 20240% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.