Barari Parkview By Al Mawared construction progress

The registered completion date for Barari Parkview By Al Mawared in Majan is December 2027. At the last site inspection, in August 2026, it was 45% built. The developer is Almawared Properties.

45%

Built, at the site inspection of 13 August 2026

Running behind its date

Registered completion date
December 2027
Finish at recent pace
May 2034
Construction started
August 2023
First registered
October 2024
Developer
Almawared Properties
Community
Majan
Units
199
Escrow bank
Emirates Islamic Bank
Name in Arabic
براري بارك فيو من الموارد
Project number
2971
Site inspections
7

Schedule

Between April 2026 and August 2026 the site added about 0.6 points a month. At that rate it would finish around May 2034, more than three months after its registered date of December 2027.

0%25%50%75%100%2024202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

13 August 2026

45%+2.4 pts

  • Barari Parkview By Al Mawared construction site, inspection photo 1, 13 August 2026
  • Barari Parkview By Al Mawared construction site, inspection photo 2, 13 August 2026
  • Barari Parkview By Al Mawared construction site, inspection photo 3, 13 August 2026
  • Barari Parkview By Al Mawared construction site, inspection photo 4, 13 August 2026

13 April 2026

42%+10 pts

  • Barari Parkview By Al Mawared construction site, inspection photo 1, 13 April 2026
  • Barari Parkview By Al Mawared construction site, inspection photo 2, 13 April 2026
  • Barari Parkview By Al Mawared construction site, inspection photo 3, 13 April 2026
  • Barari Parkview By Al Mawared construction site, inspection photo 4, 13 April 2026

18 July 2025

32%+1.2 pts

  • Barari Parkview By Al Mawared construction site, inspection photo 1, 18 July 2025
  • Barari Parkview By Al Mawared construction site, inspection photo 2, 18 July 2025
  • Barari Parkview By Al Mawared construction site, inspection photo 3, 18 July 2025
  • Barari Parkview By Al Mawared construction site, inspection photo 4, 18 July 2025

13 June 2025

31%+5.8 pts

  • Barari Parkview By Al Mawared construction site, inspection photo 1, 13 June 2025
  • Barari Parkview By Al Mawared construction site, inspection photo 2, 13 June 2025
  • Barari Parkview By Al Mawared construction site, inspection photo 3, 13 June 2025
  • Barari Parkview By Al Mawared construction site, inspection photo 4, 13 June 2025

14 February 2025

25%+6.5 pts

  • Barari Parkview By Al Mawared construction site, inspection photo 1, 14 February 2025
  • Barari Parkview By Al Mawared construction site, inspection photo 2, 14 February 2025
  • Barari Parkview By Al Mawared construction site, inspection photo 3, 14 February 2025
  • Barari Parkview By Al Mawared construction site, inspection photo 4, 14 February 2025

22 August 2024

18%+6.1 pts

  • Barari Parkview By Al Mawared construction site, inspection photo 1, 22 August 2024
  • Barari Parkview By Al Mawared construction site, inspection photo 2, 22 August 2024
  • Barari Parkview By Al Mawared construction site, inspection photo 3, 22 August 2024

22 March 2024

12%

  • Barari Parkview By Al Mawared construction site, inspection photo 1, 22 March 2024
  • Barari Parkview By Al Mawared construction site, inspection photo 2, 22 March 2024
  • Barari Parkview By Al Mawared construction site, inspection photo 3, 22 March 2024

All 40 site photos, by inspection date

Context

Majan has 25 projects under construction, 28% built on average.

Own a unit in Barari Parkview By Al Mawared?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Barari Parkview By Al Mawared handover date?
The registered completion date is December 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around May 2034. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Barari Parkview By Al Mawared?
Barari Parkview By Al Mawared was 45% built at the site inspection on 13 August 2026. The site has been inspected 7 times since March 2024. The Land Department took 40 site photos at its inspections.
Is Barari Parkview By Al Mawared delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2027.
Who is building Barari Parkview By Al Mawared?
The registered developer is Almawared Properties.
Which bank holds the escrow account for Barari Parkview By Al Mawared?
Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.