Samana Lake Views 2 construction progress
No completion date is registered for Samana Lake Views 2 in International Media Production Zone yet. At the last site inspection, in October 2026, it was 12% built. The developer is Samana Signature Real Estate Developments.
12%
Built, at the site inspection of 28 October 2026
- Finish at recent pace
- October 2037
- Construction started
- June 2024
- First registered
- May 2024
- Community
- International Media Production Zone
- Units
- 548
- Escrow bank
- Ajman Bank
- Name in Arabic
- سامانا ليك فيوز 2
- Project number
- 3087
- Site inspections
- 7
Schedule
Since November 2025 Samana Lake Views 2 has added about 0.7 points a month. At that rate the site reaches 100% around October 2037. No completion date is on record to compare it with.
Site inspections
28 October 2026
12%+3.1 pts
10 June 2026
8.9%+1.4 pts
5 February 2026
7.5%+3.3 pts
3 November 2025
4.1%+0.4 pts
2 July 2025
3.8%+3.5 pts
29 January 2025
0.3%+0.3 pts
8 May 2024
0%
Context
International Media Production Zone has 15 projects under construction, 23% built on average.
Samana Signature Real Estate Developments has 12 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Samana Lake Views 2?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Samana Lake Views 2 handover date?
- No completion date is on record for Samana Lake Views 2 yet. Handover follows completion, so there is no date to give.
- What is the latest construction update on Samana Lake Views 2?
- Samana Lake Views 2 was 12% built at the site inspection on 28 October 2026. The site has been inspected 7 times since May 2024. The Land Department took 29 site photos at its inspections.
- Who is building Samana Lake Views 2?
- The registered developer is Samana Signature Real Estate Developments. It has 11 other projects under construction in Dubai.
- Which bank holds the escrow account for Samana Lake Views 2?
- Ajman Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Samana SkyrosAlso by Samana Signature Real Estate Developments. 71%, Due April 2026, passed.
- Samana Lake ViewsAlso by Samana Signature Real Estate Developments. 23%.
- Samana Barari LagoonsAlso by Samana Signature Real Estate Developments. 17%, Due March 2028.
- Samana ParkvilleAlso by Samana Signature Real Estate Developments. 14%, Due September 2028.
- Samana PortofinoNearby in International Media Production Zone. 60%.
- Samana ResortsNearby in International Media Production Zone. 5.9%, Due May 2028.
- Imperial ResidenceNearby in International Media Production Zone. 43%, Due April 2026, passed.
- Golf Grove By RegentNearby in International Media Production Zone. 8.7%, Due January 2028.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.