Sherena Residence 2 construction progress

Sherena Residence 2 in Majan was registered to complete in August 2022 and is still under construction. At the last site inspection, in April 2026, it was 82% built. The developer is Rose Homes Investment.

82%

Built, at the site inspection of 22 April 2026

51 months past its registered completion date

Registered completion date
August 2022
Finish at recent pace
March 2027
Construction started
October 2018
First registered
October 2018
Developer
Rose Homes Investment
Community
Majan
Units
120
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
2 مجمع شيرينا السكني
Project number
2101
Site inspections
7

Schedule

Sherena Residence 2 was registered to complete in August 2022, 51 months ago, and is still under construction. Over the last year of inspections it has added about 1.7 points a month. Kept at that rate, the site would reach 100% around March 2027.

0%25%50%75%100%2019202120232025
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

22 April 2026

82%+6.5 pts

  • Sherena Residence 2 construction site, inspection photo 1, 22 April 2026
  • Sherena Residence 2 construction site, inspection photo 2, 22 April 2026
  • Sherena Residence 2 construction site, inspection photo 3, 22 April 2026
  • Sherena Residence 2 construction site, inspection photo 4, 22 April 2026

26 December 2025

76%+24 pts

  • Sherena Residence 2 construction site, inspection photo 1, 26 December 2025
  • Sherena Residence 2 construction site, inspection photo 2, 26 December 2025
  • Sherena Residence 2 construction site, inspection photo 3, 26 December 2025
  • Sherena Residence 2 construction site, inspection photo 4, 26 December 2025

15 February 2024

51%+4.8 pts

  • Sherena Residence 2 construction site, inspection photo 1, 15 February 2024
  • Sherena Residence 2 construction site, inspection photo 2, 15 February 2024
  • Sherena Residence 2 construction site, inspection photo 3, 15 February 2024
  • Sherena Residence 2 construction site, inspection photo 4, 15 February 2024

17 August 2023

47%+8.0 pts

  • Sherena Residence 2 construction site, inspection photo 1, 17 August 2023
  • Sherena Residence 2 construction site, inspection photo 2, 17 August 2023
  • Sherena Residence 2 construction site, inspection photo 3, 17 August 2023
  • Sherena Residence 2 construction site, inspection photo 4, 17 August 2023

6 February 2023

39%+12 pts

  • Sherena Residence 2 construction site, inspection photo 1, 6 February 2023
  • Sherena Residence 2 construction site, inspection photo 2, 6 February 2023
  • Sherena Residence 2 construction site, inspection photo 3, 6 February 2023
  • Sherena Residence 2 construction site, inspection photo 4, 6 February 2023

2 March 2021

27%+4.4 pts

  • Sherena Residence 2 construction site, inspection photo 1, 2 March 2021
  • Sherena Residence 2 construction site, inspection photo 2, 2 March 2021
  • Sherena Residence 2 construction site, inspection photo 3, 2 March 2021
  • Sherena Residence 2 construction site, inspection photo 4, 2 March 2021

5 May 2019

22%

  • Sherena Residence 2 construction site, inspection photo 1, 5 May 2019
  • Sherena Residence 2 construction site, inspection photo 2, 5 May 2019
  • Sherena Residence 2 construction site, inspection photo 3, 5 May 2019
  • Sherena Residence 2 construction site, inspection photo 4, 5 May 2019

All 59 site photos, by inspection date

Context

Majan has 25 projects under construction, 28% built on average.

Rose Homes Investment has 2 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Sherena Residence 2?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Sherena Residence 2 handover date?
The registered completion date was August 2022, and the register still lists Sherena Residence 2 as under construction. At the pace of its recent inspections the site would reach 100% around March 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Sherena Residence 2?
Sherena Residence 2 was 82% built at the site inspection on 22 April 2026. The site has been inspected 7 times since May 2019. The Land Department took 59 site photos at its inspections.
Is Sherena Residence 2 delayed?
Yes. Its registered completion date of August 2022 has passed and the project is still listed as under construction.
Who is building Sherena Residence 2?
The registered developer is Rose Homes Investment. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Sherena Residence 2?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.