Sherena Residence 2 construction progress

Sherena Residence 2 in Majan is 82% built at the Land Department inspection of April 2026. Developer Rose Homes Investment. Completion registered for August 2022.

82%

Built, at the Land Department site inspection of 22 April 2026

49 months past its registered completion date

Completion date (Land Department)
August 2022
Finish at recent pace
March 2027
Construction started
October 2018
Registered with the Land Department
October 2018
Developer
Rose Homes Investment
Community
Majan
Units
120
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
2 مجمع شيرينا السكني
Land Department project number
2101
Land Department site inspections
7

Schedule

Sherena Residence 2 was registered to complete in August 2022, 49 months ago, and is still under construction. Over the last year of inspections it has added about 1.7 points a month. Kept at that rate, the site would reach 100% around March 2027.

0%25%50%75%100%2019202120232025
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

22 April 2026

82%+6.5 pts

  • Sherena Residence 2 construction site, Land Department inspection photo 1, 22 April 2026
  • Sherena Residence 2 construction site, Land Department inspection photo 2, 22 April 2026
  • Sherena Residence 2 construction site, Land Department inspection photo 3, 22 April 2026
  • Sherena Residence 2 construction site, Land Department inspection photo 4, 22 April 2026

26 December 2025

76%+24 pts

  • Sherena Residence 2 construction site, Land Department inspection photo 1, 26 December 2025
  • Sherena Residence 2 construction site, Land Department inspection photo 2, 26 December 2025
  • Sherena Residence 2 construction site, Land Department inspection photo 3, 26 December 2025
  • Sherena Residence 2 construction site, Land Department inspection photo 4, 26 December 2025

15 February 2024

51%+4.8 pts

  • Sherena Residence 2 construction site, Land Department inspection photo 1, 15 February 2024
  • Sherena Residence 2 construction site, Land Department inspection photo 2, 15 February 2024
  • Sherena Residence 2 construction site, Land Department inspection photo 3, 15 February 2024
  • Sherena Residence 2 construction site, Land Department inspection photo 4, 15 February 2024

17 August 2023

47%+8.0 pts

  • Sherena Residence 2 construction site, Land Department inspection photo 1, 17 August 2023
  • Sherena Residence 2 construction site, Land Department inspection photo 2, 17 August 2023
  • Sherena Residence 2 construction site, Land Department inspection photo 3, 17 August 2023
  • Sherena Residence 2 construction site, Land Department inspection photo 4, 17 August 2023

6 February 2023

39%+12 pts

  • Sherena Residence 2 construction site, Land Department inspection photo 1, 6 February 2023
  • Sherena Residence 2 construction site, Land Department inspection photo 2, 6 February 2023
  • Sherena Residence 2 construction site, Land Department inspection photo 3, 6 February 2023
  • Sherena Residence 2 construction site, Land Department inspection photo 4, 6 February 2023

2 March 2021

27%+4.4 pts

  • Sherena Residence 2 construction site, Land Department inspection photo 1, 2 March 2021
  • Sherena Residence 2 construction site, Land Department inspection photo 2, 2 March 2021
  • Sherena Residence 2 construction site, Land Department inspection photo 3, 2 March 2021
  • Sherena Residence 2 construction site, Land Department inspection photo 4, 2 March 2021

5 May 2019

22%

  • Sherena Residence 2 construction site, Land Department inspection photo 1, 5 May 2019
  • Sherena Residence 2 construction site, Land Department inspection photo 2, 5 May 2019
  • Sherena Residence 2 construction site, Land Department inspection photo 3, 5 May 2019
  • Sherena Residence 2 construction site, Land Department inspection photo 4, 5 May 2019

All 59 site photos, by inspection date

Context

Majan has 25 projects under construction, 24% built on average. Sherena Residence 2 is ahead of that average.

Rose Homes Investment has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Sherena Residence 2?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will Sherena Residence 2 be completed?
The completion date registered with the Dubai Land Department is August 2022. At the pace of its recent inspections the site would reach 100% around March 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Sherena Residence 2 is built?
82%, measured at the Land Department site inspection on 22 April 2026. The Land Department engineers have inspected the site 7 times since May 2019.
Is Sherena Residence 2 delayed?
Yes. Its registered completion date of August 2022 has passed and the Land Department still lists it as under construction.
Who is building Sherena Residence 2?
The registered developer is Rose Homes Investment. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Sherena Residence 2?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.