Sherena Residence 2 construction progress
Sherena Residence 2 in Majan is 82% built at the Land Department inspection of April 2026. Developer Rose Homes Investment. Completion registered for August 2022.
82%
Built, at the Land Department site inspection of 22 April 2026
49 months past its registered completion date
- Completion date (Land Department)
- August 2022
- Finish at recent pace
- March 2027
- Construction started
- October 2018
- Registered with the Land Department
- October 2018
- Developer
- Rose Homes Investment
- Community
- Majan
- Units
- 120
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- 2 مجمع شيرينا السكني
- Land Department project number
- 2101
- Land Department site inspections
- 7
Schedule
Sherena Residence 2 was registered to complete in August 2022, 49 months ago, and is still under construction. Over the last year of inspections it has added about 1.7 points a month. Kept at that rate, the site would reach 100% around March 2027.
Site inspections
22 April 2026
82%+6.5 pts
26 December 2025
76%+24 pts
15 February 2024
51%+4.8 pts
17 August 2023
47%+8.0 pts
6 February 2023
39%+12 pts
2 March 2021
27%+4.4 pts
5 May 2019
22%
Context
Majan has 25 projects under construction, 24% built on average. Sherena Residence 2 is ahead of that average.
Rose Homes Investment has 2 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Sherena Residence 2?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Track the handoverQuestions
- When will Sherena Residence 2 be completed?
- The completion date registered with the Dubai Land Department is August 2022. At the pace of its recent inspections the site would reach 100% around March 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Sherena Residence 2 is built?
- 82%, measured at the Land Department site inspection on 22 April 2026. The Land Department engineers have inspected the site 7 times since May 2019.
- Is Sherena Residence 2 delayed?
- Yes. Its registered completion date of August 2022 has passed and the Land Department still lists it as under construction.
- Who is building Sherena Residence 2?
- The registered developer is Rose Homes Investment. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for Sherena Residence 2?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Al Warsan StarAlso by Rose Homes Investment. 7.5%, Due February 2027.
- Samana Barari ViewsNearby in Majan. 27%, Due March 2027.
- Samana Barari Views 2Nearby in Majan. 20%.
- Barari Parkview By Al MawaredNearby in Majan. 45%, Due December 2027.
- Wadi 645Nearby in Majan. 55%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.