Samana Parkville construction progress
The registered completion date for Samana Parkville in Dubai Land Residence Complex is September 2028. At the last site inspection, in October 2026, it was 14% built. The developer is Samana Signature Real Estate Developments.
14%
Built, at the site inspection of 21 October 2026
Running behind its date
- Registered completion date
- September 2028
- Finish at recent pace
- October 2032
- Construction started
- June 2025
- First registered
- June 2025
- Community
- Dubai Land Residence Complex
- Units
- 428
- Escrow bank
- Dubai Islamic Bank
- Name in Arabic
- سامانا باركفيل
- Project number
- 3791
- Site inspections
- 5
Schedule
Between December 2025 and October 2026 the site added about 1.2 points a month. At that rate it would finish around October 2032, more than three months after its registered date of September 2028.
Site inspections
21 October 2026
14%+8.8 pts
18 June 2026
5.1%+1.5 pts
28 April 2026
3.6%+2.1 pts
11 December 2025
1.5%+1.5 pts
26 May 2025
0%
Context
Dubai Land Residence Complex has 63 projects under construction, 28% built on average.
Samana Signature Real Estate Developments has 12 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Samana Parkville?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Samana Parkville handover date?
- The registered completion date is September 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around October 2032. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Samana Parkville?
- Samana Parkville was 14% built at the site inspection on 21 October 2026. The site has been inspected 5 times since May 2025. The Land Department took 18 site photos at its inspections.
- Is Samana Parkville delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2028.
- Who is building Samana Parkville?
- The registered developer is Samana Signature Real Estate Developments. It has 11 other projects under construction in Dubai.
- Which bank holds the escrow account for Samana Parkville?
- Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Samana SkyrosAlso by Samana Signature Real Estate Developments. 71%, Due April 2026, passed.
- Samana Lake ViewsAlso by Samana Signature Real Estate Developments. 23%.
- Samana Lake Views 2Also by Samana Signature Real Estate Developments. 12%.
- Samana Barari LagoonsAlso by Samana Signature Real Estate Developments. 17%, Due March 2028.
- Ag CentralNearby in Dubai Land Residence Complex. 59%, Due October 2026, passed.
- Ag SquareNearby in Dubai Land Residence Complex. 69%, Due September 2026, passed.
- Time 2Nearby in Dubai Land Residence Complex. 87%, Due June 2026, passed.
- Ag 7evenNearby in Dubai Land Residence Complex. 94%, Due March 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.