Skip to content

Samana Parkville construction progress

The registered completion date for Samana Parkville in Dubai Land Residence Complex is September 2028. At the last site inspection, in October 2026, it was 14% built. The developer is Samana Signature Real Estate Developments.

14%

Built, at the site inspection of 21 October 2026

Running behind its date

Registered completion date
September 2028
Finish at recent pace
October 2032
Construction started
June 2025
First registered
June 2025
Units
428
Escrow bank
Dubai Islamic Bank
Name in Arabic
سامانا باركفيل
Project number
3791
Site inspections
5

Schedule

Between December 2025 and October 2026 the site added about 1.2 points a month. At that rate it would finish around October 2032, more than three months after its registered date of September 2028.

0%25%50%75%100%202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

21 October 2026

14%+8.8 pts

  • Samana Parkville construction site, inspection photo 1, 21 October 2026
  • Samana Parkville construction site, inspection photo 2, 21 October 2026
  • Samana Parkville construction site, inspection photo 3, 21 October 2026
  • Samana Parkville construction site, inspection photo 4, 21 October 2026

18 June 2026

5.1%+1.5 pts

  • Samana Parkville construction site, inspection photo 1, 18 June 2026
  • Samana Parkville construction site, inspection photo 2, 18 June 2026
  • Samana Parkville construction site, inspection photo 3, 18 June 2026

28 April 2026

3.6%+2.1 pts

  • Samana Parkville construction site, inspection photo 1, 28 April 2026
  • Samana Parkville construction site, inspection photo 2, 28 April 2026
  • Samana Parkville construction site, inspection photo 3, 28 April 2026
  • Samana Parkville construction site, inspection photo 4, 28 April 2026

11 December 2025

1.5%+1.5 pts

  • Samana Parkville construction site, inspection photo 1, 11 December 2025
  • Samana Parkville construction site, inspection photo 2, 11 December 2025
  • Samana Parkville construction site, inspection photo 3, 11 December 2025
  • Samana Parkville construction site, inspection photo 4, 11 December 2025

26 May 2025

0%

  • Samana Parkville construction site, inspection photo 1, 26 May 2025
  • Samana Parkville construction site, inspection photo 2, 26 May 2025

All 18 site photos, by inspection date

Context

Dubai Land Residence Complex has 63 projects under construction, 28% built on average.

Samana Signature Real Estate Developments has 12 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Samana Parkville?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Samana Parkville handover date?
The registered completion date is September 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around October 2032. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Samana Parkville?
Samana Parkville was 14% built at the site inspection on 21 October 2026. The site has been inspected 5 times since May 2025. The Land Department took 18 site photos at its inspections.
Is Samana Parkville delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2028.
Who is building Samana Parkville?
The registered developer is Samana Signature Real Estate Developments. It has 11 other projects under construction in Dubai.
Which bank holds the escrow account for Samana Parkville?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.