Samana Parkville construction progress

Samana Parkville in Dubai Land Residence Complex is 5.1% built at the Land Department inspection of June 2026. Developer Samana Signature Real Estate Developments. Completion registered for September 2028.

5.1%

Built, at the Land Department site inspection of 18 June 2026

Running behind its date

Completion date (Land Department)
September 2028
Finish at recent pace
February 2040
Construction started
June 2025
Registered with the Land Department
June 2025
Units
428
Escrow bank
Dubai Islamic Bank
Name in Arabic
سامانا باركفيل
Land Department project number
3791
Land Department site inspections
4

Schedule

Between December 2025 and June 2026 the site added about 0.6 points a month. At that rate it would finish around February 2040, more than three months after the September 2028 date registered with the Land Department.

0%25%50%75%100%202620272028
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

18 June 2026

5.1%+1.5 pts

  • Samana Parkville construction site, Land Department inspection photo 1, 18 June 2026
  • Samana Parkville construction site, Land Department inspection photo 2, 18 June 2026
  • Samana Parkville construction site, Land Department inspection photo 3, 18 June 2026

28 April 2026

3.6%+2.1 pts

  • Samana Parkville construction site, Land Department inspection photo 1, 28 April 2026
  • Samana Parkville construction site, Land Department inspection photo 2, 28 April 2026
  • Samana Parkville construction site, Land Department inspection photo 3, 28 April 2026
  • Samana Parkville construction site, Land Department inspection photo 4, 28 April 2026

11 December 2025

1.5%+1.5 pts

  • Samana Parkville construction site, Land Department inspection photo 1, 11 December 2025
  • Samana Parkville construction site, Land Department inspection photo 2, 11 December 2025
  • Samana Parkville construction site, Land Department inspection photo 3, 11 December 2025
  • Samana Parkville construction site, Land Department inspection photo 4, 11 December 2025

26 May 2025

0%

  • Samana Parkville construction site, Land Department inspection photo 1, 26 May 2025
  • Samana Parkville construction site, Land Department inspection photo 2, 26 May 2025

All 13 site photos, by inspection date

Context

Dubai Land Residence Complex has 65 projects under construction, 24% built on average. Samana Parkville is behind that average.

Samana Signature Real Estate Developments has 12 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Samana Parkville?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will Samana Parkville be completed?
The completion date registered with the Dubai Land Department is September 2028. At the pace of its recent inspections the site would reach 100% around February 2040. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Samana Parkville is built?
5.1%, measured at the Land Department site inspection on 18 June 2026. The Land Department engineers have inspected the site 4 times since May 2025.
Is Samana Parkville delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2028.
Who is building Samana Parkville?
The registered developer is Samana Signature Real Estate Developments. It has 11 other projects under construction in Dubai.
Which bank holds the escrow account for Samana Parkville?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.