Samana Barari Views 2 construction progress

No completion date is registered for Samana Barari Views 2 in Majan yet. At the last site inspection, in October 2026, it was 26% built. The developer is Samana International Real Estate Development.

26%

Built, at the site inspection of 28 October 2026

Finish at recent pace
March 2031
Construction started
February 2024
First registered
December 2023
Community
Majan
Units
669
Escrow bank
Dubai Islamic Bank
Name in Arabic
سامانا براري فيوز 2
Project number
2841
Site inspections
7

Schedule

Since November 2025 Samana Barari Views 2 has added about 1.4 points a month. At that rate the site reaches 100% around March 2031. No completion date is on record to compare it with.

0%25%50%75%100%202420252026
Progress at each site inspection

Site inspections

28 October 2026

26%+6.2 pts

  • Samana Barari Views 2 construction site, inspection photo 1, 28 October 2026
  • Samana Barari Views 2 construction site, inspection photo 2, 28 October 2026
  • Samana Barari Views 2 construction site, inspection photo 3, 28 October 2026
  • Samana Barari Views 2 construction site, inspection photo 4, 28 October 2026

16 June 2026

20%+6.2 pts

  • Samana Barari Views 2 construction site, inspection photo 1, 16 June 2026
  • Samana Barari Views 2 construction site, inspection photo 2, 16 June 2026
  • Samana Barari Views 2 construction site, inspection photo 3, 16 June 2026
  • Samana Barari Views 2 construction site, inspection photo 4, 16 June 2026

3 February 2026

13%+4.4 pts

  • Samana Barari Views 2 construction site, inspection photo 1, 3 February 2026
  • Samana Barari Views 2 construction site, inspection photo 2, 3 February 2026
  • Samana Barari Views 2 construction site, inspection photo 3, 3 February 2026
  • Samana Barari Views 2 construction site, inspection photo 4, 3 February 2026

3 November 2025

9.1%+1.8 pts

  • Samana Barari Views 2 construction site, inspection photo 1, 3 November 2025
  • Samana Barari Views 2 construction site, inspection photo 2, 3 November 2025
  • Samana Barari Views 2 construction site, inspection photo 3, 3 November 2025
  • Samana Barari Views 2 construction site, inspection photo 4, 3 November 2025

3 July 2025

7.2%+4.3 pts

  • Samana Barari Views 2 construction site, inspection photo 1, 3 July 2025
  • Samana Barari Views 2 construction site, inspection photo 2, 3 July 2025
  • Samana Barari Views 2 construction site, inspection photo 3, 3 July 2025
  • Samana Barari Views 2 construction site, inspection photo 4, 3 July 2025

14 November 2024

3.0%+3.0 pts

  • Samana Barari Views 2 construction site, inspection photo 1, 14 November 2024
  • Samana Barari Views 2 construction site, inspection photo 2, 14 November 2024
  • Samana Barari Views 2 construction site, inspection photo 3, 14 November 2024
  • Samana Barari Views 2 construction site, inspection photo 4, 14 November 2024

30 November 2023

0%

  • Samana Barari Views 2 construction site, inspection photo 1, 30 November 2023
  • Samana Barari Views 2 construction site, inspection photo 2, 30 November 2023

All 34 site photos, by inspection date

Context

Majan has 25 projects under construction, 28% built on average.

Samana International Real Estate Development has 14 projects under construction in Dubai; 2 have passed their registered completion date.

Own a unit in Samana Barari Views 2?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Samana Barari Views 2 handover date?
No completion date is on record for Samana Barari Views 2 yet. Handover follows completion, so there is no date to give.
What is the latest construction update on Samana Barari Views 2?
Samana Barari Views 2 was 26% built at the site inspection on 28 October 2026. The site has been inspected 7 times since November 2023. The Land Department took 34 site photos at its inspections.
Who is building Samana Barari Views 2?
The registered developer is Samana International Real Estate Development. It has 13 other projects under construction in Dubai.
Which bank holds the escrow account for Samana Barari Views 2?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.