Samana Lake Views construction progress

Samana Lake Views in International Media Production Zone is 23% built at the Land Department inspection of September 2026. Developer Samana Signature Real Estate Developments.

23%

Built, at the Land Department site inspection of 28 September 2026

Finish at recent pace
December 2030
Construction started
June 2024
Registered with the Land Department
May 2024
Units
451
Escrow bank
Ajman Bank
Name in Arabic
سامانا ليك فيوز
Land Department project number
3071
Land Department site inspections
7

Schedule

Since November 2025 Samana Lake Views has added about 1.5 points a month. At that rate the site reaches 100% around December 2030. The Land Department has no completion date on record to compare it with.

0%25%50%75%100%20252026
Progress at each Land Department site inspection

Site inspections

28 September 2026

23%+9.3 pts

  • Samana Lake Views construction site, Land Department inspection photo 1, 28 September 2026
  • Samana Lake Views construction site, Land Department inspection photo 2, 28 September 2026
  • Samana Lake Views construction site, Land Department inspection photo 3, 28 September 2026
  • Samana Lake Views construction site, Land Department inspection photo 4, 28 September 2026

3 June 2026

14%+4.0 pts

  • Samana Lake Views construction site, Land Department inspection photo 1, 3 June 2026
  • Samana Lake Views construction site, Land Department inspection photo 2, 3 June 2026
  • Samana Lake Views construction site, Land Department inspection photo 3, 3 June 2026
  • Samana Lake Views construction site, Land Department inspection photo 4, 3 June 2026

3 February 2026

9.6%+3.1 pts

  • Samana Lake Views construction site, Land Department inspection photo 1, 3 February 2026
  • Samana Lake Views construction site, Land Department inspection photo 2, 3 February 2026
  • Samana Lake Views construction site, Land Department inspection photo 3, 3 February 2026
  • Samana Lake Views construction site, Land Department inspection photo 4, 3 February 2026

3 November 2025

6.5%+1.9 pts

  • Samana Lake Views construction site, Land Department inspection photo 1, 3 November 2025
  • Samana Lake Views construction site, Land Department inspection photo 2, 3 November 2025
  • Samana Lake Views construction site, Land Department inspection photo 3, 3 November 2025
  • Samana Lake Views construction site, Land Department inspection photo 4, 3 November 2025

2 July 2025

4.6%+2.9 pts

  • Samana Lake Views construction site, Land Department inspection photo 1, 2 July 2025
  • Samana Lake Views construction site, Land Department inspection photo 2, 2 July 2025
  • Samana Lake Views construction site, Land Department inspection photo 3, 2 July 2025
  • Samana Lake Views construction site, Land Department inspection photo 4, 2 July 2025

25 February 2025

1.6%+1.6 pts

  • Samana Lake Views construction site, Land Department inspection photo 1, 25 February 2025
  • Samana Lake Views construction site, Land Department inspection photo 2, 25 February 2025
  • Samana Lake Views construction site, Land Department inspection photo 3, 25 February 2025
  • Samana Lake Views construction site, Land Department inspection photo 4, 25 February 2025

6 May 2024

0%

  • Samana Lake Views construction site, Land Department inspection photo 1, 6 May 2024
  • Samana Lake Views construction site, Land Department inspection photo 2, 6 May 2024

All 35 site photos, by inspection date

Context

International Media Production Zone has 15 projects under construction, 22% built on average.

Samana Signature Real Estate Developments has 12 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Samana Lake Views?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Samana Lake Views be completed?
The Land Department has no completion date on record for Samana Lake Views yet.
How much of Samana Lake Views is built?
23%, measured at the Land Department site inspection on 28 September 2026. The Land Department engineers have inspected the site 7 times since May 2024.
Who is building Samana Lake Views?
The registered developer is Samana Signature Real Estate Developments. It has 11 other projects under construction in Dubai.
Which bank holds the escrow account for Samana Lake Views?
Ajman Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.