Samana Lake Views construction progress
Samana Lake Views in International Media Production Zone is 23% built at the Land Department inspection of September 2026. Developer Samana Signature Real Estate Developments.
23%
Built, at the Land Department site inspection of 28 September 2026
- Finish at recent pace
- December 2030
- Construction started
- June 2024
- Registered with the Land Department
- May 2024
- Community
- International Media Production Zone
- Units
- 451
- Escrow bank
- Ajman Bank
- Name in Arabic
- سامانا ليك فيوز
- Land Department project number
- 3071
- Land Department site inspections
- 7
Schedule
Since November 2025 Samana Lake Views has added about 1.5 points a month. At that rate the site reaches 100% around December 2030. The Land Department has no completion date on record to compare it with.
Site inspections
28 September 2026
23%+9.3 pts
3 June 2026
14%+4.0 pts
3 February 2026
9.6%+3.1 pts
3 November 2025
6.5%+1.9 pts
2 July 2025
4.6%+2.9 pts
25 February 2025
1.6%+1.6 pts
6 May 2024
0%
Context
International Media Production Zone has 15 projects under construction, 22% built on average.
Samana Signature Real Estate Developments has 12 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Samana Lake Views?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Samana Lake Views be completed?
- The Land Department has no completion date on record for Samana Lake Views yet.
- How much of Samana Lake Views is built?
- 23%, measured at the Land Department site inspection on 28 September 2026. The Land Department engineers have inspected the site 7 times since May 2024.
- Who is building Samana Lake Views?
- The registered developer is Samana Signature Real Estate Developments. It has 11 other projects under construction in Dubai.
- Which bank holds the escrow account for Samana Lake Views?
- Ajman Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Samana SkyrosAlso by Samana Signature Real Estate Developments. 71%, Due April 2026, passed.
- Samana Lake Views 2Also by Samana Signature Real Estate Developments. 8.9%.
- Samana Barari LagoonsAlso by Samana Signature Real Estate Developments. 12%.
- Samana ParkvilleAlso by Samana Signature Real Estate Developments. 5.1%, Due September 2028.
- Samana PortofinoNearby in International Media Production Zone. 60%.
- Samana ResortsNearby in International Media Production Zone. 5.8%.
- Imperial ResidenceNearby in International Media Production Zone. 43%, Due April 2026, passed.
- Golf Grove By RegentNearby in International Media Production Zone. 8.7%, Due January 2028.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.