Manhattan 1 By Sd construction progress

No completion date is registered for Manhattan 1 By Sd in Jumeirah Village Circle yet. At the last site inspection, in September 2026, it was 30% built. The developer is Samana Star Real Estate Development.

30%

Built, at the site inspection of 17 September 2026

Finish at recent pace
January 2030
Construction started
November 2023
First registered
January 2024
Units
193
Escrow bank
Dubai Islamic Bank
Name in Arabic
مانهاتن 1 باي اس دي
Project number
2794
Site inspections
6

Schedule

Since December 2025 Manhattan 1 By Sd has added about 1.7 points a month. At that rate the site reaches 100% around January 2030. No completion date is on record to compare it with.

0%25%50%75%100%202420252026
Progress at each site inspection

Site inspections

17 September 2026

30%+10 pts

  • Manhattan 1 By Sd construction site, inspection photo 1, 17 September 2026
  • Manhattan 1 By Sd construction site, inspection photo 2, 17 September 2026
  • Manhattan 1 By Sd construction site, inspection photo 3, 17 September 2026
  • Manhattan 1 By Sd construction site, inspection photo 4, 17 September 2026

23 April 2026

20%+5.5 pts

  • Manhattan 1 By Sd construction site, inspection photo 1, 23 April 2026
  • Manhattan 1 By Sd construction site, inspection photo 2, 23 April 2026
  • Manhattan 1 By Sd construction site, inspection photo 3, 23 April 2026
  • Manhattan 1 By Sd construction site, inspection photo 4, 23 April 2026

11 December 2025

14%+7.1 pts

  • Manhattan 1 By Sd construction site, inspection photo 1, 11 December 2025
  • Manhattan 1 By Sd construction site, inspection photo 2, 11 December 2025
  • Manhattan 1 By Sd construction site, inspection photo 3, 11 December 2025
  • Manhattan 1 By Sd construction site, inspection photo 4, 11 December 2025

25 August 2025

7.2%+3.7 pts

  • Manhattan 1 By Sd construction site, inspection photo 1, 25 August 2025
  • Manhattan 1 By Sd construction site, inspection photo 2, 25 August 2025
  • Manhattan 1 By Sd construction site, inspection photo 3, 25 August 2025
  • Manhattan 1 By Sd construction site, inspection photo 4, 25 August 2025

18 February 2025

3.6%+3.6 pts

  • Manhattan 1 By Sd construction site, inspection photo 1, 18 February 2025
  • Manhattan 1 By Sd construction site, inspection photo 2, 18 February 2025
  • Manhattan 1 By Sd construction site, inspection photo 3, 18 February 2025
  • Manhattan 1 By Sd construction site, inspection photo 4, 18 February 2025

28 September 2023

0%

  • Manhattan 1 By Sd construction site, inspection photo 1, 28 September 2023
  • Manhattan 1 By Sd construction site, inspection photo 2, 28 September 2023
  • Manhattan 1 By Sd construction site, inspection photo 3, 28 September 2023

All 38 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Samana Star Real Estate Development has 8 projects under construction in Dubai; 2 have passed their registered completion date.

Own a unit in Manhattan 1 By Sd?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Manhattan 1 By Sd handover date?
No completion date is on record for Manhattan 1 By Sd yet. Handover follows completion, so there is no date to give.
What is the latest construction update on Manhattan 1 By Sd?
Manhattan 1 By Sd was 30% built at the site inspection on 17 September 2026. The site has been inspected 6 times since September 2023. The Land Department took 38 site photos at its inspections.
Who is building Manhattan 1 By Sd?
The registered developer is Samana Star Real Estate Development. It has 7 other projects under construction in Dubai.
Which bank holds the escrow account for Manhattan 1 By Sd?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.