Manhattan 1 By Sd construction progress
Manhattan 1 By Sd in Jumeirah Village Circle is 30% built at the Land Department inspection of September 2026. Developer Samana Star Real Estate Development.
30%
Built, at the Land Department site inspection of 17 September 2026
- Finish at recent pace
- January 2030
- Construction started
- November 2023
- Registered with the Land Department
- January 2024
- Developer
- Samana Star Real Estate Development
- Community
- Jumeirah Village Circle
- Units
- 193
- Escrow bank
- Dubai Islamic Bank
- Name in Arabic
- مانهاتن 1 باي اس دي
- Land Department project number
- 2794
- Land Department site inspections
- 6
Schedule
Since December 2025 Manhattan 1 By Sd has added about 1.7 points a month. At that rate the site reaches 100% around January 2030. The Land Department has no completion date on record to compare it with.
Site inspections
17 September 2026
30%+10 pts
23 April 2026
20%+5.5 pts
11 December 2025
14%+7.1 pts
25 August 2025
7.2%+3.7 pts
18 February 2025
3.6%+3.6 pts
28 September 2023
0%
Context
Jumeirah Village Circle has 119 projects under construction, 40% built on average.
Samana Star Real Estate Development has 8 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Manhattan 1 By Sd?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Manhattan 1 By Sd be completed?
- The Land Department has no completion date on record for Manhattan 1 By Sd yet.
- How much of Manhattan 1 By Sd is built?
- 30%, measured at the Land Department site inspection on 17 September 2026. The Land Department engineers have inspected the site 6 times since September 2023.
- Who is building Manhattan 1 By Sd?
- The registered developer is Samana Star Real Estate Development. It has 7 other projects under construction in Dubai.
- Which bank holds the escrow account for Manhattan 1 By Sd?
- Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Manhattan 2 By SdAlso by Samana Star Real Estate Development. 21%, Due November 2026.
- California 2 By SdAlso by Samana Star Real Estate Development. 34%.
- Ocean Pearl By SdAlso by Samana Star Real Estate Development. 25%, Due December 2026.
- Rome By SdAlso by Samana Star Real Estate Development. 39%, Due December 2027.
- German Supreme Tower 2Nearby in Jumeirah Village Circle. 42%, Due January 2013, passed.
- Serenity Lakes 2Nearby in Jumeirah Village Circle. 50%, Due November 2025, passed.
- Dusit Princess RijasNearby in Jumeirah Village Circle. 64%, Due April 2027.
- Samana WavesNearby in Jumeirah Village Circle. 90%, Due April 2026, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.








.jpeg&w=3840&q=75)











.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)