Ocean Pearl By Sd construction progress
The registered completion date for Ocean Pearl By Sd in Palm Deira is December 2026. At the last site inspection, in September 2026, it was 25% built. The developer is Samana Star Real Estate Development.
25%
Built, at the site inspection of 17 September 2026
Running behind its date
- Registered completion date
- December 2026
- Finish at recent pace
- August 2029
- Construction started
- December 2024
- First registered
- August 2024
- Developer
- Samana Star Real Estate Development
- Community
- Palm Deira
- Units
- 100
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- أوشن برل باي اس دي
- Project number
- 3167
- Site inspections
- 6
Schedule
Between December 2025 and September 2026 the site added about 2.2 points a month. At that rate it would finish around August 2029, more than three months after its registered date of December 2026.
Site inspections
17 September 2026
25%+16 pts
3 April 2026
8.8%+4.0 pts
4 December 2025
4.8%+3.4 pts
25 August 2025
1.4%+0.2 pts
8 April 2025
1.2%+1.2 pts
3 July 2024
0%
Context
Palm Deira has 94 projects under construction, 24% built on average.
Samana Star Real Estate Development has 8 projects under construction in Dubai; 2 have passed their registered completion date.
Own a unit in Ocean Pearl By Sd?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Ocean Pearl By Sd handover date?
- The registered completion date is December 2026. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Ocean Pearl By Sd?
- Ocean Pearl By Sd was 25% built at the site inspection on 17 September 2026. The site has been inspected 6 times since July 2024. The Land Department took 24 site photos at its inspections.
- Is Ocean Pearl By Sd delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
- Who is building Ocean Pearl By Sd?
- The registered developer is Samana Star Real Estate Development. It has 7 other projects under construction in Dubai.
- Which bank holds the escrow account for Ocean Pearl By Sd?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Manhattan 1 By SdAlso by Samana Star Real Estate Development. 30%.
- Manhattan 2 By SdAlso by Samana Star Real Estate Development. 21%, Due November 2026, passed.
- California 2 By SdAlso by Samana Star Real Estate Development. 34%, Due October 2026, passed.
- Rome By SdAlso by Samana Star Real Estate Development. 39%, Due December 2027.
- Bay Residences Dubai IslandsNearby in Palm Deira. 48%, Due October 2026, passed.
- Beach Residences Dubai IslandsNearby in Palm Deira. 29%.
- Bay Villas - Dubai IslandsNearby in Palm Deira. 23%, Due May 2027.
- Edgewater ResidencesNearby in Palm Deira. 48%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.