Skip to content

Ocean Pearl By Sd construction progress

The registered completion date for Ocean Pearl By Sd in Palm Deira is December 2026. At the last site inspection, in September 2026, it was 25% built. The developer is Samana Star Real Estate Development.

25%

Built, at the site inspection of 17 September 2026

Running behind its date

Registered completion date
December 2026
Finish at recent pace
August 2029
Construction started
December 2024
First registered
August 2024
Community
Palm Deira
Units
100
Escrow bank
First Abu Dhabi Bank
Name in Arabic
أوشن برل باي اس دي
Project number
3167
Site inspections
6

Schedule

Between December 2025 and September 2026 the site added about 2.2 points a month. At that rate it would finish around August 2029, more than three months after its registered date of December 2026.

0%25%50%75%100%20252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

17 September 2026

25%+16 pts

  • Ocean Pearl By Sd construction site, inspection photo 1, 17 September 2026
  • Ocean Pearl By Sd construction site, inspection photo 2, 17 September 2026
  • Ocean Pearl By Sd construction site, inspection photo 3, 17 September 2026
  • Ocean Pearl By Sd construction site, inspection photo 4, 17 September 2026

3 April 2026

8.8%+4.0 pts

  • Ocean Pearl By Sd construction site, inspection photo 1, 3 April 2026
  • Ocean Pearl By Sd construction site, inspection photo 2, 3 April 2026
  • Ocean Pearl By Sd construction site, inspection photo 3, 3 April 2026
  • Ocean Pearl By Sd construction site, inspection photo 4, 3 April 2026

4 December 2025

4.8%+3.4 pts

  • Ocean Pearl By Sd construction site, inspection photo 1, 4 December 2025
  • Ocean Pearl By Sd construction site, inspection photo 2, 4 December 2025
  • Ocean Pearl By Sd construction site, inspection photo 3, 4 December 2025
  • Ocean Pearl By Sd construction site, inspection photo 4, 4 December 2025

25 August 2025

1.4%+0.2 pts

  • Ocean Pearl By Sd construction site, inspection photo 1, 25 August 2025
  • Ocean Pearl By Sd construction site, inspection photo 2, 25 August 2025
  • Ocean Pearl By Sd construction site, inspection photo 3, 25 August 2025

8 April 2025

1.2%+1.2 pts

  • Ocean Pearl By Sd construction site, inspection photo 1, 8 April 2025
  • Ocean Pearl By Sd construction site, inspection photo 2, 8 April 2025
  • Ocean Pearl By Sd construction site, inspection photo 3, 8 April 2025

3 July 2024

0%

  • Ocean Pearl By Sd construction site, inspection photo 1, 3 July 2024
  • Ocean Pearl By Sd construction site, inspection photo 2, 3 July 2024

All 24 site photos, by inspection date

Context

Palm Deira has 94 projects under construction, 24% built on average.

Samana Star Real Estate Development has 8 projects under construction in Dubai; 2 have passed their registered completion date.

Own a unit in Ocean Pearl By Sd?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Ocean Pearl By Sd handover date?
The registered completion date is December 2026. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Ocean Pearl By Sd?
Ocean Pearl By Sd was 25% built at the site inspection on 17 September 2026. The site has been inspected 6 times since July 2024. The Land Department took 24 site photos at its inspections.
Is Ocean Pearl By Sd delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
Who is building Ocean Pearl By Sd?
The registered developer is Samana Star Real Estate Development. It has 7 other projects under construction in Dubai.
Which bank holds the escrow account for Ocean Pearl By Sd?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.