Manhattan 2 By Sd construction progress

Manhattan 2 By Sd in Jumeirah Village Circle is 21% built at the Land Department inspection of September 2026. Developer Samana Star Real Estate Development. Completion registered for November 2026.

21%

Built, at the Land Department site inspection of 17 September 2026

Running behind its date

Completion date (Land Department)
November 2026
Finish at recent pace
February 2031
Construction started
April 2024
Registered with the Land Department
February 2024
Units
193
Escrow bank
Dubai Islamic Bank
Name in Arabic
مانهاتن 2 باي اس دي
Land Department project number
2802
Land Department site inspections
7

Schedule

Between November 2025 and September 2026 the site added about 1.5 points a month. At that rate it would finish around February 2031, more than three months after the November 2026 date registered with the Land Department.

0%25%50%75%100%202420252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

17 September 2026

21%+3.6 pts

  • Manhattan 2 By Sd construction site, Land Department inspection photo 1, 17 September 2026
  • Manhattan 2 By Sd construction site, Land Department inspection photo 2, 17 September 2026
  • Manhattan 2 By Sd construction site, Land Department inspection photo 3, 17 September 2026
  • Manhattan 2 By Sd construction site, Land Department inspection photo 4, 17 September 2026

19 June 2026

18%+7.6 pts

  • Manhattan 2 By Sd construction site, Land Department inspection photo 1, 19 June 2026
  • Manhattan 2 By Sd construction site, Land Department inspection photo 2, 19 June 2026
  • Manhattan 2 By Sd construction site, Land Department inspection photo 3, 19 June 2026
  • Manhattan 2 By Sd construction site, Land Department inspection photo 4, 19 June 2026

5 February 2026

10%+3.4 pts

  • Manhattan 2 By Sd construction site, Land Department inspection photo 1, 5 February 2026
  • Manhattan 2 By Sd construction site, Land Department inspection photo 2, 5 February 2026
  • Manhattan 2 By Sd construction site, Land Department inspection photo 3, 5 February 2026

21 November 2025

6.7%+2.4 pts

  • Manhattan 2 By Sd construction site, Land Department inspection photo 1, 21 November 2025
  • Manhattan 2 By Sd construction site, Land Department inspection photo 2, 21 November 2025
  • Manhattan 2 By Sd construction site, Land Department inspection photo 3, 21 November 2025
  • Manhattan 2 By Sd construction site, Land Department inspection photo 4, 21 November 2025

11 July 2025

4.3%+1.9 pts

  • Manhattan 2 By Sd construction site, Land Department inspection photo 1, 11 July 2025
  • Manhattan 2 By Sd construction site, Land Department inspection photo 2, 11 July 2025
  • Manhattan 2 By Sd construction site, Land Department inspection photo 3, 11 July 2025
  • Manhattan 2 By Sd construction site, Land Department inspection photo 4, 11 July 2025

18 February 2025

2.4%+2.4 pts

  • Manhattan 2 By Sd construction site, Land Department inspection photo 1, 18 February 2025
  • Manhattan 2 By Sd construction site, Land Department inspection photo 2, 18 February 2025
  • Manhattan 2 By Sd construction site, Land Department inspection photo 3, 18 February 2025
  • Manhattan 2 By Sd construction site, Land Department inspection photo 4, 18 February 2025

9 October 2023

0%

  • Manhattan 2 By Sd construction site, Land Department inspection photo 1, 9 October 2023
  • Manhattan 2 By Sd construction site, Land Department inspection photo 2, 9 October 2023

All 29 site photos, by inspection date

Context

Jumeirah Village Circle has 119 projects under construction, 40% built on average.

Samana Star Real Estate Development has 8 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Manhattan 2 By Sd?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Manhattan 2 By Sd be completed?
The completion date registered with the Dubai Land Department is November 2026. At the pace of its recent inspections the site would reach 100% around February 2031. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Manhattan 2 By Sd is built?
21%, measured at the Land Department site inspection on 17 September 2026. The Land Department engineers have inspected the site 7 times since October 2023.
Is Manhattan 2 By Sd delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of November 2026.
Who is building Manhattan 2 By Sd?
The registered developer is Samana Star Real Estate Development. It has 7 other projects under construction in Dubai.
Which bank holds the escrow account for Manhattan 2 By Sd?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.