Aliva Green construction progress
Aliva Green in Jumeirah Village Circle is 52% built at the site inspection of November 2026. Developer Gulf Land Property Developers. Completion registered for November 2025.
52%
Built, at the site inspection of 3 November 2026
13 months past its registered completion date
- Registered completion date
- November 2025
- Finish at recent pace
- January 2032
- Construction started
- June 2014
- First registered
- August 2014
- Developer
- Gulf Land Property Developers
- Community
- Jumeirah Village Circle
- Units
- 268
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- أليفا جرين
- Project number
- 1555
- Site inspections
- 13
Schedule
Aliva Green was registered to complete in November 2025, 13 months ago, and is still under construction. Over the last year of inspections it has added about 0.8 points a month. Kept at that rate, the site would reach 100% around January 2032.
Site inspections
3 November 2026
52%+1.7 pts
11 September 2026
50%+0.5 pts
2 July 2026
50%+2.7 pts
25 April 2026
47%
22 July 2024
47%+6.8 pts
8 May 2023
40%+1.0 pts
14 April 2022
39%
29 April 2019
39%+11 pts
26 February 2018
28%+12 pts
20 September 2017
17%+5.6 pts
Context
Jumeirah Village Circle has 118 projects under construction, 42% built on average.
Gulf Land Property Developers has 2 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Aliva Green?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Aliva Green be completed?
- The registered completion date is November 2025. At the pace of its recent inspections the site would reach 100% around January 2032. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- How much of Aliva Green is built?
- 52%, measured at the site inspection on 3 November 2026. The site has been inspected 13 times since July 2015.
- Is Aliva Green delayed?
- Yes. Its registered completion date of November 2025 has passed and the project is still listed as under construction.
- Who is building Aliva Green?
- The registered developer is Gulf Land Property Developers. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for Aliva Green?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Tonino Lamborghini ResidencesAlso by Gulf Land Property Developers. 60%, Due December 2026.
- German Supreme Tower 2Nearby in Jumeirah Village Circle. 45%, Due January 2029.
- Dusit Princess RijasNearby in Jumeirah Village Circle. 64%, Due April 2027.
- Samana WavesNearby in Jumeirah Village Circle. 91%, Due April 2026, passed.
- Luxury Family ResidenceNearby in Jumeirah Village Circle. 76%, Due December 2023, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.
















.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)