Aliva Green construction progress

Aliva Green in Jumeirah Village Circle is 52% built at the site inspection of November 2026. Developer Gulf Land Property Developers. Completion registered for November 2025.

52%

Built, at the site inspection of 3 November 2026

13 months past its registered completion date

Registered completion date
November 2025
Finish at recent pace
January 2032
Construction started
June 2014
First registered
August 2014
Developer
Gulf Land Property Developers
Units
268
Escrow bank
First Abu Dhabi Bank
Name in Arabic
أليفا جرين
Project number
1555
Site inspections
13

Schedule

Aliva Green was registered to complete in November 2025, 13 months ago, and is still under construction. Over the last year of inspections it has added about 0.8 points a month. Kept at that rate, the site would reach 100% around January 2032.

0%25%50%75%100%2015201820212024
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

3 November 2026

52%+1.7 pts

  • Aliva Green construction site, inspection photo 1, 3 November 2026
  • Aliva Green construction site, inspection photo 2, 3 November 2026
  • Aliva Green construction site, inspection photo 3, 3 November 2026
  • Aliva Green construction site, inspection photo 4, 3 November 2026

11 September 2026

50%+0.5 pts

  • Aliva Green construction site, inspection photo 1, 11 September 2026
  • Aliva Green construction site, inspection photo 2, 11 September 2026
  • Aliva Green construction site, inspection photo 3, 11 September 2026
  • Aliva Green construction site, inspection photo 4, 11 September 2026

2 July 2026

50%+2.7 pts

  • Aliva Green construction site, inspection photo 1, 2 July 2026
  • Aliva Green construction site, inspection photo 2, 2 July 2026
  • Aliva Green construction site, inspection photo 3, 2 July 2026
  • Aliva Green construction site, inspection photo 4, 2 July 2026

25 April 2026

47%

  • Aliva Green construction site, inspection photo 1, 25 April 2026
  • Aliva Green construction site, inspection photo 2, 25 April 2026
  • Aliva Green construction site, inspection photo 3, 25 April 2026
  • Aliva Green construction site, inspection photo 4, 25 April 2026

22 July 2024

47%+6.8 pts

  • Aliva Green construction site, inspection photo 1, 22 July 2024
  • Aliva Green construction site, inspection photo 2, 22 July 2024
  • Aliva Green construction site, inspection photo 3, 22 July 2024
  • Aliva Green construction site, inspection photo 4, 22 July 2024

8 May 2023

40%+1.0 pts

  • Aliva Green construction site, inspection photo 1, 8 May 2023
  • Aliva Green construction site, inspection photo 2, 8 May 2023
  • Aliva Green construction site, inspection photo 3, 8 May 2023
  • Aliva Green construction site, inspection photo 4, 8 May 2023

14 April 2022

39%

  • Aliva Green construction site, inspection photo 1, 14 April 2022
  • Aliva Green construction site, inspection photo 2, 14 April 2022
  • Aliva Green construction site, inspection photo 3, 14 April 2022
  • Aliva Green construction site, inspection photo 4, 14 April 2022

29 April 2019

39%+11 pts

  • Aliva Green construction site, inspection photo 1, 29 April 2019
  • Aliva Green construction site, inspection photo 2, 29 April 2019
  • Aliva Green construction site, inspection photo 3, 29 April 2019
  • Aliva Green construction site, inspection photo 4, 29 April 2019

26 February 2018

28%+12 pts

  • Aliva Green construction site, inspection photo 1, 26 February 2018
  • Aliva Green construction site, inspection photo 2, 26 February 2018
  • Aliva Green construction site, inspection photo 3, 26 February 2018
  • Aliva Green construction site, inspection photo 4, 26 February 2018

20 September 2017

17%+5.6 pts

  • Aliva Green construction site, inspection photo 1, 20 September 2017
  • Aliva Green construction site, inspection photo 2, 20 September 2017
  • Aliva Green construction site, inspection photo 3, 20 September 2017

All 75 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Gulf Land Property Developers has 2 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Aliva Green?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Aliva Green be completed?
The registered completion date is November 2025. At the pace of its recent inspections the site would reach 100% around January 2032. RERA asks developers to update their dates as projects move, so check the register before relying on it.
How much of Aliva Green is built?
52%, measured at the site inspection on 3 November 2026. The site has been inspected 13 times since July 2015.
Is Aliva Green delayed?
Yes. Its registered completion date of November 2025 has passed and the project is still listed as under construction.
Who is building Aliva Green?
The registered developer is Gulf Land Property Developers. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Aliva Green?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.