German Supreme Tower 2 construction progress
German Supreme Tower 2 in Jumeirah Village Circle is 42% built at the Land Department inspection of August 2026. Developer Pyamod International. Completion registered for January 2013.
42%
Built, at the Land Department site inspection of 24 August 2026
165 months past its registered completion date
- Completion date (Land Department)
- January 2013
- Finish at recent pace
- August 2028
- Construction started
- March 2024
- Registered with the Land Department
- March 2024
- Developer
- Pyamod International
- Community
- Jumeirah Village Circle
- Units
- 165
- Escrow bank
- The National Bank of Fujairah
- Name in Arabic
- جيرمن سوبريم تاور 2
- Land Department project number
- 982
- Land Department site inspections
- 2
Schedule
German Supreme Tower 2 was registered to complete in January 2013, 165 months ago, and is still under construction. Over the last year of inspections it has added about 2.5 points a month. Kept at that rate, the site would reach 100% around August 2028.
Site inspections
24 August 2026
42%+8.3 pts
14 May 2026
33%
Context
Jumeirah Village Circle has 119 projects under construction, 40% built on average.
Own a unit in German Supreme Tower 2?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will German Supreme Tower 2 be completed?
- The completion date registered with the Dubai Land Department is January 2013. At the pace of its recent inspections the site would reach 100% around August 2028. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of German Supreme Tower 2 is built?
- 42%, measured at the Land Department site inspection on 24 August 2026. The Land Department engineers have inspected the site 2 times since May 2026.
- Is German Supreme Tower 2 delayed?
- Yes. Its registered completion date of January 2013 has passed and the Land Department still lists it as under construction.
- Who is building German Supreme Tower 2?
- The registered developer is Pyamod International.
- Which bank holds the escrow account for German Supreme Tower 2?
- The National Bank of Fujairah. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Serenity Lakes 2Nearby in Jumeirah Village Circle. 50%, Due November 2025, passed.
- Dusit Princess RijasNearby in Jumeirah Village Circle. 64%, Due April 2027.
- Samana WavesNearby in Jumeirah Village Circle. 90%, Due April 2026, passed.
- Luxury Family ResidenceNearby in Jumeirah Village Circle. 76%, Due December 2023, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.


.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)