German Supreme Tower 2 construction progress

The registered completion date for German Supreme Tower 2 in Jumeirah Village Circle is January 2029. At the last site inspection, in October 2026, it was 45% built. The developer is Pyamod International.

45%

Built, at the site inspection of 28 October 2026

On pace for its date

Registered completion date
January 2029
Finish at recent pace
December 2028
Construction started
March 2024
First registered
March 2024
Developer
Pyamod International
Units
165
Escrow bank
The National Bank of Fujairah
Name in Arabic
جيرمن سوبريم تاور 2
Project number
982
Site inspections
3

Schedule

Since May 2026 German Supreme Tower 2 has added about 2.1 points a month. That puts 100% around December 2028, within three months of its registered completion date of January 2029.

0%25%50%75%100%20252026202720282029
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

28 October 2026

45%+3.5 pts

  • German Supreme Tower 2 construction site, inspection photo 1, 28 October 2026
  • German Supreme Tower 2 construction site, inspection photo 2, 28 October 2026
  • German Supreme Tower 2 construction site, inspection photo 3, 28 October 2026
  • German Supreme Tower 2 construction site, inspection photo 4, 28 October 2026

24 August 2026

42%+8.3 pts

  • German Supreme Tower 2 construction site, inspection photo 1, 24 August 2026
  • German Supreme Tower 2 construction site, inspection photo 2, 24 August 2026
  • German Supreme Tower 2 construction site, inspection photo 3, 24 August 2026
  • German Supreme Tower 2 construction site, inspection photo 4, 24 August 2026

14 May 2026

33%

  • German Supreme Tower 2 construction site, inspection photo 1, 14 May 2026
  • German Supreme Tower 2 construction site, inspection photo 2, 14 May 2026
  • German Supreme Tower 2 construction site, inspection photo 3, 14 May 2026
  • German Supreme Tower 2 construction site, inspection photo 4, 14 May 2026

All 29 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Own a unit in German Supreme Tower 2?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the German Supreme Tower 2 handover date?
The registered completion date is January 2029. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around December 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on German Supreme Tower 2?
German Supreme Tower 2 was 45% built at the site inspection on 28 October 2026. The site has been inspected 3 times since May 2026. The Land Department took 29 site photos at its inspections.
Is German Supreme Tower 2 delayed?
Not on current figures. At the rate of the last year it finishes within three months of its registered date of January 2029.
Who is building German Supreme Tower 2?
The registered developer is Pyamod International.
Which bank holds the escrow account for German Supreme Tower 2?
The National Bank of Fujairah. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.