German Supreme Tower 2 construction progress

German Supreme Tower 2 in Jumeirah Village Circle is 42% built at the Land Department inspection of August 2026. Developer Pyamod International. Completion registered for January 2013.

42%

Built, at the Land Department site inspection of 24 August 2026

165 months past its registered completion date

Completion date (Land Department)
January 2013
Finish at recent pace
August 2028
Construction started
March 2024
Registered with the Land Department
March 2024
Developer
Pyamod International
Units
165
Escrow bank
The National Bank of Fujairah
Name in Arabic
جيرمن سوبريم تاور 2
Land Department project number
982
Land Department site inspections
2

Schedule

German Supreme Tower 2 was registered to complete in January 2013, 165 months ago, and is still under construction. Over the last year of inspections it has added about 2.5 points a month. Kept at that rate, the site would reach 100% around August 2028.

0%25%50%75%100%20252026
Progress at each Land Department site inspection

Site inspections

24 August 2026

42%+8.3 pts

  • German Supreme Tower 2 construction site, Land Department inspection photo 1, 24 August 2026
  • German Supreme Tower 2 construction site, Land Department inspection photo 2, 24 August 2026
  • German Supreme Tower 2 construction site, Land Department inspection photo 3, 24 August 2026
  • German Supreme Tower 2 construction site, Land Department inspection photo 4, 24 August 2026

14 May 2026

33%

  • German Supreme Tower 2 construction site, Land Department inspection photo 1, 14 May 2026
  • German Supreme Tower 2 construction site, Land Department inspection photo 2, 14 May 2026
  • German Supreme Tower 2 construction site, Land Department inspection photo 3, 14 May 2026
  • German Supreme Tower 2 construction site, Land Department inspection photo 4, 14 May 2026

All 18 site photos, by inspection date

Context

Jumeirah Village Circle has 119 projects under construction, 40% built on average.

Own a unit in German Supreme Tower 2?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will German Supreme Tower 2 be completed?
The completion date registered with the Dubai Land Department is January 2013. At the pace of its recent inspections the site would reach 100% around August 2028. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of German Supreme Tower 2 is built?
42%, measured at the Land Department site inspection on 24 August 2026. The Land Department engineers have inspected the site 2 times since May 2026.
Is German Supreme Tower 2 delayed?
Yes. Its registered completion date of January 2013 has passed and the Land Department still lists it as under construction.
Who is building German Supreme Tower 2?
The registered developer is Pyamod International.
Which bank holds the escrow account for German Supreme Tower 2?
The National Bank of Fujairah. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.