Dusit Princess Rijas construction progress
Dusit Princess Rijas in Jumeirah Village Circle is 64% built at the Land Department inspection of August 2026. Developer Aces Property Development. Completion registered for April 2027.
64%
Built, at the Land Department site inspection of 6 August 2026
Running behind its date
- Completion date (Land Department)
- April 2027
- Finish at recent pace
- August 2028
- Construction started
- April 2017
- Registered with the Land Department
- July 2017
- Developer
- Aces Property Development
- Community
- Jumeirah Village Circle
- Units
- 256
- Escrow bank
- United Bank Limited
- Name in Arabic
- دوست برنسس رجاز
- Land Department project number
- 1901
- Land Department site inspections
- 11
Schedule
Between August 2025 and August 2026 the site added about 1.5 points a month. At that rate it would finish around August 2028, more than three months after the April 2027 date registered with the Land Department.
Site inspections
6 August 2026
64%+7.0 pts
10 April 2026
57%+9.9 pts
20 August 2025
47%+6.0 pts
17 January 2025
41%+10 pts
25 September 2024
31%+9.6 pts
14 March 2024
21%+11 pts
17 August 2023
11%+5.3 pts
13 March 2023
5.3%+0.6 pts
10 November 2022
4.7%+0.3 pts
30 June 2022
4.4%+4.3 pts
Context
Jumeirah Village Circle has 119 projects under construction, 40% built on average.
Own a unit in Dusit Princess Rijas?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Dusit Princess Rijas be completed?
- The completion date registered with the Dubai Land Department is April 2027. At the pace of its recent inspections the site would reach 100% around August 2028. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Dusit Princess Rijas is built?
- 64%, measured at the Land Department site inspection on 6 August 2026. The Land Department engineers have inspected the site 11 times since January 2022.
- Is Dusit Princess Rijas delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of April 2027.
- Who is building Dusit Princess Rijas?
- The registered developer is Aces Property Development.
- Which bank holds the escrow account for Dusit Princess Rijas?
- United Bank Limited. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- German Supreme Tower 2Nearby in Jumeirah Village Circle. 42%, Due January 2013, passed.
- Serenity Lakes 2Nearby in Jumeirah Village Circle. 50%, Due November 2025, passed.
- Samana WavesNearby in Jumeirah Village Circle. 90%, Due April 2026, passed.
- Luxury Family ResidenceNearby in Jumeirah Village Circle. 76%, Due December 2023, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)
















.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)

.jpg&w=3840&q=75)
.jpg&w=3840&q=75)

.jpg&w=3840&q=75)

.jpg&w=3840&q=75)
.jpg&w=3840&q=75)