Dusit Princess Rijas construction progress

Dusit Princess Rijas in Jumeirah Village Circle is 64% built at the Land Department inspection of August 2026. Developer Aces Property Development. Completion registered for April 2027.

64%

Built, at the Land Department site inspection of 6 August 2026

Running behind its date

Completion date (Land Department)
April 2027
Finish at recent pace
August 2028
Construction started
April 2017
Registered with the Land Department
July 2017
Developer
Aces Property Development
Units
256
Escrow bank
United Bank Limited
Name in Arabic
دوست برنسس رجاز
Land Department project number
1901
Land Department site inspections
11

Schedule

Between August 2025 and August 2026 the site added about 1.5 points a month. At that rate it would finish around August 2028, more than three months after the April 2027 date registered with the Land Department.

0%25%50%75%100%20182020202220242026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

6 August 2026

64%+7.0 pts

  • Dusit Princess Rijas construction site, Land Department inspection photo 1, 6 August 2026
  • Dusit Princess Rijas construction site, Land Department inspection photo 2, 6 August 2026
  • Dusit Princess Rijas construction site, Land Department inspection photo 3, 6 August 2026
  • Dusit Princess Rijas construction site, Land Department inspection photo 4, 6 August 2026

10 April 2026

57%+9.9 pts

  • Dusit Princess Rijas construction site, Land Department inspection photo 1, 10 April 2026
  • Dusit Princess Rijas construction site, Land Department inspection photo 2, 10 April 2026
  • Dusit Princess Rijas construction site, Land Department inspection photo 3, 10 April 2026
  • Dusit Princess Rijas construction site, Land Department inspection photo 4, 10 April 2026

20 August 2025

47%+6.0 pts

  • Dusit Princess Rijas construction site, Land Department inspection photo 1, 20 August 2025
  • Dusit Princess Rijas construction site, Land Department inspection photo 2, 20 August 2025
  • Dusit Princess Rijas construction site, Land Department inspection photo 3, 20 August 2025
  • Dusit Princess Rijas construction site, Land Department inspection photo 4, 20 August 2025

17 January 2025

41%+10 pts

  • Dusit Princess Rijas construction site, Land Department inspection photo 1, 17 January 2025
  • Dusit Princess Rijas construction site, Land Department inspection photo 2, 17 January 2025
  • Dusit Princess Rijas construction site, Land Department inspection photo 3, 17 January 2025
  • Dusit Princess Rijas construction site, Land Department inspection photo 4, 17 January 2025

25 September 2024

31%+9.6 pts

  • Dusit Princess Rijas construction site, Land Department inspection photo 1, 25 September 2024
  • Dusit Princess Rijas construction site, Land Department inspection photo 2, 25 September 2024
  • Dusit Princess Rijas construction site, Land Department inspection photo 3, 25 September 2024
  • Dusit Princess Rijas construction site, Land Department inspection photo 4, 25 September 2024

14 March 2024

21%+11 pts

  • Dusit Princess Rijas construction site, Land Department inspection photo 1, 14 March 2024
  • Dusit Princess Rijas construction site, Land Department inspection photo 2, 14 March 2024
  • Dusit Princess Rijas construction site, Land Department inspection photo 3, 14 March 2024
  • Dusit Princess Rijas construction site, Land Department inspection photo 4, 14 March 2024

17 August 2023

11%+5.3 pts

  • Dusit Princess Rijas construction site, Land Department inspection photo 1, 17 August 2023
  • Dusit Princess Rijas construction site, Land Department inspection photo 2, 17 August 2023
  • Dusit Princess Rijas construction site, Land Department inspection photo 3, 17 August 2023
  • Dusit Princess Rijas construction site, Land Department inspection photo 4, 17 August 2023

13 March 2023

5.3%+0.6 pts

  • Dusit Princess Rijas construction site, Land Department inspection photo 1, 13 March 2023
  • Dusit Princess Rijas construction site, Land Department inspection photo 2, 13 March 2023
  • Dusit Princess Rijas construction site, Land Department inspection photo 3, 13 March 2023
  • Dusit Princess Rijas construction site, Land Department inspection photo 4, 13 March 2023

10 November 2022

4.7%+0.3 pts

  • Dusit Princess Rijas construction site, Land Department inspection photo 1, 10 November 2022
  • Dusit Princess Rijas construction site, Land Department inspection photo 2, 10 November 2022
  • Dusit Princess Rijas construction site, Land Department inspection photo 3, 10 November 2022

30 June 2022

4.4%+4.3 pts

  • Dusit Princess Rijas construction site, Land Department inspection photo 1, 30 June 2022
  • Dusit Princess Rijas construction site, Land Department inspection photo 2, 30 June 2022
  • Dusit Princess Rijas construction site, Land Department inspection photo 3, 30 June 2022
  • Dusit Princess Rijas construction site, Land Department inspection photo 4, 30 June 2022

All 75 site photos, by inspection date

Context

Jumeirah Village Circle has 119 projects under construction, 40% built on average.

Own a unit in Dusit Princess Rijas?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Dusit Princess Rijas be completed?
The completion date registered with the Dubai Land Department is April 2027. At the pace of its recent inspections the site would reach 100% around August 2028. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Dusit Princess Rijas is built?
64%, measured at the Land Department site inspection on 6 August 2026. The Land Department engineers have inspected the site 11 times since January 2022.
Is Dusit Princess Rijas delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of April 2027.
Who is building Dusit Princess Rijas?
The registered developer is Aces Property Development.
Which bank holds the escrow account for Dusit Princess Rijas?
United Bank Limited. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.