Manhattan 1 By Sd construction photos
38 photos from 6 site inspections, newest first. The percentage is how much of Manhattan 1 By Sd was built on the day of each visit.
17 September 202630% built
23 April 202620% built
11 December 202514% built
25 August 20257.2% built
18 February 20253.6% built
28 September 20230% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.