California 2 By Sd construction progress
California 2 By Sd in Discovery Gardens was registered to complete in October 2026 and is still under construction. At the last site inspection, in September 2026, it was 34% built. The developer is Samana Star Real Estate Development.
34%
Built, at the site inspection of 17 September 2026
1 months past its registered completion date
- Registered completion date
- October 2026
- Finish at recent pace
- July 2028
- Construction started
- April 2024
- First registered
- April 2024
- Developer
- Samana Star Real Estate Development
- Community
- Discovery Gardens
- Units
- 155
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- Sd كاليفورنيا 2 بواسطة
- Project number
- 2883
- Site inspections
- 6
Schedule
California 2 By Sd was registered to complete in October 2026, 1 month ago, and is still under construction. Over the last year of inspections it has added about 3.1 points a month. Kept at that rate, the site would reach 100% around July 2028.
Site inspections
17 September 2026
34%+19 pts
28 April 2026
15%+7.5 pts
26 December 2025
7.1%+2.3 pts
26 August 2025
4.8%+0.7 pts
17 March 2025
4.1%+4.1 pts
20 February 2024
0%
Context
Discovery Gardens has 9 projects under construction, 48% built on average.
Samana Star Real Estate Development has 8 projects under construction in Dubai; 2 have passed their registered completion date.
Own a unit in California 2 By Sd?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the California 2 By Sd handover date?
- The registered completion date was October 2026, and the register still lists California 2 By Sd as under construction. At the pace of its recent inspections the site would reach 100% around July 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on California 2 By Sd?
- California 2 By Sd was 34% built at the site inspection on 17 September 2026. The site has been inspected 6 times since February 2024. The Land Department took 25 site photos at its inspections.
- Is California 2 By Sd delayed?
- Yes. Its registered completion date of October 2026 has passed and the project is still listed as under construction.
- Who is building California 2 By Sd?
- The registered developer is Samana Star Real Estate Development. It has 7 other projects under construction in Dubai.
- Which bank holds the escrow account for California 2 By Sd?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Manhattan 1 By SdAlso by Samana Star Real Estate Development. 30%.
- Manhattan 2 By SdAlso by Samana Star Real Estate Development. 21%, Due November 2026, passed.
- Ocean Pearl By SdAlso by Samana Star Real Estate Development. 25%, Due December 2026.
- Rome By SdAlso by Samana Star Real Estate Development. 39%, Due December 2027.
- California By SdNearby in Discovery Gardens. 24%.
- Serene Gardens By PrescottNearby in Discovery Gardens. 62%.
- Serene Gardens 2 By PrescottNearby in Discovery Gardens. 70%.
- Enqlave By AqasaNearby in Discovery Gardens. 70%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)


.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)