Samana Waves construction progress
Samana Waves in Jumeirah Village Circle was registered to complete in April 2026 and is still under construction. At the last site inspection, in October 2026, it was 91% built. The developer is Samana Si Holding Limited Dubai Branch.
91%
Built, at the site inspection of 16 October 2026
7 months past its registered completion date
- Registered completion date
- April 2026
- Finish at recent pace
- April 2027
- Construction started
- July 2022
- First registered
- February 2022
- Community
- Jumeirah Village Circle
- Units
- 197
- Escrow bank
- Mashreq Bank
- Name in Arabic
- سمانا ويفز
- Project number
- 2345
- Site inspections
- 10
Schedule
Samana Waves was registered to complete in April 2026, 7 months ago, and is still under construction. Over the last year of inspections it has added about 1.6 points a month. Kept at that rate, the site would reach 100% around April 2027.
Site inspections
16 October 2026
91%+0.5 pts
19 June 2026
90%+13 pts
5 February 2026
77%+3.7 pts
20 November 2025
73%+19 pts
14 July 2025
54%+14 pts
31 January 2025
40%+13 pts
13 November 2024
27%+17 pts
14 May 2024
10%+6.6 pts
15 March 2023
3.6%+3.6 pts
5 December 2022
0%
Context
Jumeirah Village Circle has 118 projects under construction, 42% built on average.
Samana Si Holding Limited Dubai Branch has 4 projects under construction in Dubai; 3 have passed their registered completion date.
Own a unit in Samana Waves?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Samana Waves handover date?
- The registered completion date was April 2026, and the register still lists Samana Waves as under construction. At the pace of its recent inspections the site would reach 100% around April 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Samana Waves?
- Samana Waves was 91% built at the site inspection on 16 October 2026. The site has been inspected 10 times since December 2022. The Land Department took 75 site photos at its inspections.
- Is Samana Waves delayed?
- Yes. Its registered completion date of April 2026 has passed and the project is still listed as under construction.
- Who is building Samana Waves?
- The registered developer is Samana Si Holding Limited Dubai Branch. It has 3 other projects under construction in Dubai.
- Which bank holds the escrow account for Samana Waves?
- Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Miami By SdAlso by Samana Si Holding Limited Dubai Branch. 71%, Due July 2026, passed.
- Samana Waves 2Also by Samana Si Holding Limited Dubai Branch. 52%, Due March 2026, passed.
- California By SdAlso by Samana Si Holding Limited Dubai Branch. 24%.
- German Supreme Tower 2Nearby in Jumeirah Village Circle. 45%, Due January 2029.
- Aliva GreenNearby in Jumeirah Village Circle. 52%, Due November 2025, passed.
- Dusit Princess RijasNearby in Jumeirah Village Circle. 64%, Due April 2027.
- Luxury Family ResidenceNearby in Jumeirah Village Circle. 76%, Due December 2023, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.








.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)

.jpg&w=3840&q=75)
.jpg&w=3840&q=75)




.jpg&w=3840&q=75)