Samana Waves construction progress
Samana Waves in Jumeirah Village Circle is 90% built at the Land Department inspection of June 2026. Developer Samana Si Holding Limited Dubai Branch. Completion registered for April 2026.
90%
Built, at the Land Department site inspection of 19 June 2026
6 months past its registered completion date
- Completion date (Land Department)
- April 2026
- Finish at recent pace
- September 2026
- Construction started
- July 2022
- Registered with the Land Department
- February 2022
- Community
- Jumeirah Village Circle
- Units
- 197
- Escrow bank
- Mashreq Bank
- Name in Arabic
- سمانا ويفز
- Land Department project number
- 2345
- Land Department site inspections
- 9
Schedule
Samana Waves was registered to complete in April 2026, 6 months ago, and is still under construction. Over the last year of inspections it has added about 3.2 points a month. Kept at that rate, the site would reach 100% around September 2026.
Site inspections
19 June 2026
90%+13 pts
5 February 2026
77%+3.7 pts
20 November 2025
73%+19 pts
14 July 2025
54%+14 pts
31 January 2025
40%+13 pts
13 November 2024
27%+17 pts
14 May 2024
10%+6.6 pts
15 March 2023
3.6%+3.6 pts
5 December 2022
0%
Context
Jumeirah Village Circle has 119 projects under construction, 40% built on average. Samana Waves is ahead of that average.
Samana Si Holding Limited Dubai Branch has 4 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Samana Waves?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Track the handoverQuestions
- When will Samana Waves be completed?
- The completion date registered with the Dubai Land Department is April 2026. At the pace of its recent inspections the site would reach 100% around September 2026. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Samana Waves is built?
- 90%, measured at the Land Department site inspection on 19 June 2026. The Land Department engineers have inspected the site 9 times since December 2022.
- Is Samana Waves delayed?
- Yes. Its registered completion date of April 2026 has passed and the Land Department still lists it as under construction.
- Who is building Samana Waves?
- The registered developer is Samana Si Holding Limited Dubai Branch. It has 3 other projects under construction in Dubai.
- Which bank holds the escrow account for Samana Waves?
- Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Miami By SdAlso by Samana Si Holding Limited Dubai Branch. 71%, Due July 2026, passed.
- Samana Waves 2Also by Samana Si Holding Limited Dubai Branch. 52%.
- California By SdAlso by Samana Si Holding Limited Dubai Branch. 24%.
- German Supreme Tower 2Nearby in Jumeirah Village Circle. 42%, Due January 2013, passed.
- Serenity Lakes 2Nearby in Jumeirah Village Circle. 50%, Due November 2025, passed.
- Dusit Princess RijasNearby in Jumeirah Village Circle. 64%, Due April 2027.
- Luxury Family ResidenceNearby in Jumeirah Village Circle. 76%, Due December 2023, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.




.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)




.jpg&w=3840&q=75)