Dusk By Binghatti construction progress

The register lists Dusk By Binghatti in Jumeirah Village Circle as complete, with a registered completion date of December 2024. Its last site inspection on record was in April 2025. The developer is Binghatti Developers.

100%

Built, at the site inspection of 24 April 2025

Construction complete

Registered completion date
December 2024
Construction started
January 2024
First registered
August 2024
Units
107
Escrow bank
Abu Dhabi Islamic Bank
Name in Arabic
داسك من بن غاطي
Project number
3024
Site inspections
2

Schedule

The register lists Dusk By Binghatti as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2025
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

24 April 2025

100%+54 pts

  • Dusk By Binghatti construction site, inspection photo 1, 24 April 2025
  • Dusk By Binghatti construction site, inspection photo 2, 24 April 2025
  • Dusk By Binghatti construction site, inspection photo 3, 24 April 2025
  • Dusk By Binghatti construction site, inspection photo 4, 24 April 2025

15 May 2024

46%

  • Dusk By Binghatti construction site, inspection photo 1, 15 May 2024
  • Dusk By Binghatti construction site, inspection photo 2, 15 May 2024
  • Dusk By Binghatti construction site, inspection photo 3, 15 May 2024
  • Dusk By Binghatti construction site, inspection photo 4, 15 May 2024

All 17 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Binghatti Developers has 38 projects under construction in Dubai; 14 have passed their registered completion date.

Own a unit in Dusk By Binghatti?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Dusk By Binghatti handover date?
Construction of Dusk By Binghatti is recorded as complete, with a registered completion date of December 2024. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Dusk By Binghatti?
Dusk By Binghatti was 100% built at the site inspection on 24 April 2025. The site has been inspected 2 times since May 2024. The Land Department took 17 site photos at its inspections.
Is Dusk By Binghatti delayed?
The register lists construction as complete.
Who is building Dusk By Binghatti?
The registered developer is Binghatti Developers. It has 38 other projects under construction in Dubai.
Which bank holds the escrow account for Dusk By Binghatti?
Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.