Binghatti Royale construction progress

The register lists Binghatti Royale in Jumeirah Village Circle as complete. Its last site inspection on record was in October 2025. The developer is Binghatti Developers.

100%

Built, at the site inspection of 14 October 2025

Construction complete

Construction started
January 2024
First registered
March 2024
Units
370
Escrow bank
Dubai Islamic Bank
Name in Arabic
بن غاطي رويال
Project number
2961
Site inspections
3

Schedule

The register lists Binghatti Royale as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2025
Progress at each site inspection

Site inspections

14 October 2025

100%+68 pts

  • Binghatti Royale construction site, inspection photo 1, 14 October 2025
  • Binghatti Royale construction site, inspection photo 2, 14 October 2025
  • Binghatti Royale construction site, inspection photo 3, 14 October 2025
  • Binghatti Royale construction site, inspection photo 4, 14 October 2025

6 November 2024

32%+32 pts

  • Binghatti Royale construction site, inspection photo 1, 6 November 2024
  • Binghatti Royale construction site, inspection photo 2, 6 November 2024
  • Binghatti Royale construction site, inspection photo 3, 6 November 2024
  • Binghatti Royale construction site, inspection photo 4, 6 November 2024

8 February 2024

0%

  • Binghatti Royale construction site, inspection photo 1, 8 February 2024
  • Binghatti Royale construction site, inspection photo 2, 8 February 2024
  • Binghatti Royale construction site, inspection photo 3, 8 February 2024

All 23 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Binghatti Developers has 38 projects under construction in Dubai; 14 have passed their registered completion date.

Own a unit in Binghatti Royale?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Binghatti Royale handover date?
Construction of Binghatti Royale is recorded as complete. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Binghatti Royale?
Binghatti Royale was 100% built at the site inspection on 14 October 2025. The site has been inspected 3 times since February 2024. The Land Department took 23 site photos at its inspections.
Is Binghatti Royale delayed?
The register lists construction as complete.
Who is building Binghatti Royale?
The registered developer is Binghatti Developers. It has 38 other projects under construction in Dubai.
Which bank holds the escrow account for Binghatti Royale?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.