Binghatti Rose construction progress

The register lists Binghatti Rose in Jumeirah Village Circle as complete, with a registered completion date of April 2022. Its last site inspection on record was in July 2022. The developer is Binghatti Developers.

100%

Built, at the site inspection of 28 July 2022

Construction complete

Registered completion date
April 2022
Construction started
April 2021
First registered
December 2021
Units
171
Escrow bank
Sharjah Islamic Bank
Name in Arabic
بن غاطي روز
Project number
2326
Site inspections
3

Schedule

The register lists Binghatti Rose as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2022
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

28 July 2022

100%+45 pts

  • Binghatti Rose construction site, inspection photo 1, 28 July 2022
  • Binghatti Rose construction site, inspection photo 2, 28 July 2022
  • Binghatti Rose construction site, inspection photo 3, 28 July 2022
  • Binghatti Rose construction site, inspection photo 4, 28 July 2022

23 February 2022

55%+25 pts

  • Binghatti Rose construction site, inspection photo 1, 23 February 2022
  • Binghatti Rose construction site, inspection photo 2, 23 February 2022
  • Binghatti Rose construction site, inspection photo 3, 23 February 2022
  • Binghatti Rose construction site, inspection photo 4, 23 February 2022

5 December 2021

30%

  • Binghatti Rose construction site, inspection photo 1, 5 December 2021
  • Binghatti Rose construction site, inspection photo 2, 5 December 2021
  • Binghatti Rose construction site, inspection photo 3, 5 December 2021
  • Binghatti Rose construction site, inspection photo 4, 5 December 2021

All 38 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Binghatti Developers has 38 projects under construction in Dubai; 14 have passed their registered completion date.

Own a unit in Binghatti Rose?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Binghatti Rose handover date?
Construction of Binghatti Rose is recorded as complete, with a registered completion date of April 2022. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Binghatti Rose?
Binghatti Rose was 100% built at the site inspection on 28 July 2022. The site has been inspected 3 times since December 2021. The Land Department took 38 site photos at its inspections.
Is Binghatti Rose delayed?
The register lists construction as complete.
Who is building Binghatti Rose?
The registered developer is Binghatti Developers. It has 38 other projects under construction in Dubai.
Which bank holds the escrow account for Binghatti Rose?
Sharjah Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.