Binghatti Jasmine construction progress

The register lists Binghatti Jasmine in Jumeirah Village Circle as complete, with a registered completion date of January 2023. Its last site inspection on record was in November 2022. The developer is Binghatti Developers.

100%

Built, at the site inspection of 17 November 2022

Construction complete

Registered completion date
January 2023
Construction started
January 2022
First registered
April 2022
Units
92
Escrow bank
Sharjah Islamic Bank
Name in Arabic
بن غاطي جازمين
Project number
2386
Site inspections
3

Schedule

The register lists Binghatti Jasmine as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2023
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

17 November 2022

100%+45 pts

  • Binghatti Jasmine construction site, inspection photo 1, 17 November 2022
  • Binghatti Jasmine construction site, inspection photo 2, 17 November 2022
  • Binghatti Jasmine construction site, inspection photo 3, 17 November 2022
  • Binghatti Jasmine construction site, inspection photo 4, 17 November 2022

5 July 2022

55%+33 pts

  • Binghatti Jasmine construction site, inspection photo 1, 5 July 2022
  • Binghatti Jasmine construction site, inspection photo 2, 5 July 2022
  • Binghatti Jasmine construction site, inspection photo 3, 5 July 2022
  • Binghatti Jasmine construction site, inspection photo 4, 5 July 2022

17 May 2022

22%

  • Binghatti Jasmine construction site, inspection photo 1, 17 May 2022
  • Binghatti Jasmine construction site, inspection photo 2, 17 May 2022
  • Binghatti Jasmine construction site, inspection photo 3, 17 May 2022
  • Binghatti Jasmine construction site, inspection photo 4, 17 May 2022

All 32 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Binghatti Developers has 38 projects under construction in Dubai; 14 have passed their registered completion date.

Own a unit in Binghatti Jasmine?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Binghatti Jasmine handover date?
Construction of Binghatti Jasmine is recorded as complete, with a registered completion date of January 2023. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Binghatti Jasmine?
Binghatti Jasmine was 100% built at the site inspection on 17 November 2022. The site has been inspected 3 times since May 2022. The Land Department took 32 site photos at its inspections.
Is Binghatti Jasmine delayed?
The register lists construction as complete.
Who is building Binghatti Jasmine?
The registered developer is Binghatti Developers. It has 38 other projects under construction in Dubai.
Which bank holds the escrow account for Binghatti Jasmine?
Sharjah Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.