Binghatti Crest construction progress

The register lists Binghatti Crest in Jumeirah Village Circle as complete, with a registered completion date of October 2023. Its last site inspection on record was in December 2023. The developer is Binghatti Developers.

100%

Built, at the site inspection of 21 December 2023

Construction complete

Registered completion date
October 2023
Construction started
September 2022
First registered
October 2022
Units
171
Escrow bank
Sharjah Islamic Bank
Name in Arabic
بن غاطي كريست
Project number
2473
Site inspections
4

Schedule

The register lists Binghatti Crest as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2023
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

21 December 2023

100%+4.9 pts

  • Binghatti Crest construction site, inspection photo 1, 21 December 2023
  • Binghatti Crest construction site, inspection photo 2, 21 December 2023
  • Binghatti Crest construction site, inspection photo 3, 21 December 2023
  • Binghatti Crest construction site, inspection photo 4, 21 December 2023

30 August 2023

95%+68 pts

  • Binghatti Crest construction site, inspection photo 1, 30 August 2023
  • Binghatti Crest construction site, inspection photo 2, 30 August 2023
  • Binghatti Crest construction site, inspection photo 3, 30 August 2023
  • Binghatti Crest construction site, inspection photo 4, 30 August 2023

31 January 2023

27%+23 pts

  • Binghatti Crest construction site, inspection photo 1, 31 January 2023
  • Binghatti Crest construction site, inspection photo 2, 31 January 2023
  • Binghatti Crest construction site, inspection photo 3, 31 January 2023
  • Binghatti Crest construction site, inspection photo 4, 31 January 2023

11 October 2022

4.0%

  • Binghatti Crest construction site, inspection photo 1, 11 October 2022
  • Binghatti Crest construction site, inspection photo 2, 11 October 2022
  • Binghatti Crest construction site, inspection photo 3, 11 October 2022
  • Binghatti Crest construction site, inspection photo 4, 11 October 2022

All 47 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Binghatti Developers has 38 projects under construction in Dubai; 14 have passed their registered completion date.

Own a unit in Binghatti Crest?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Binghatti Crest handover date?
Construction of Binghatti Crest is recorded as complete, with a registered completion date of October 2023. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Binghatti Crest?
Binghatti Crest was 100% built at the site inspection on 21 December 2023. The site has been inspected 4 times since October 2022. The Land Department took 47 site photos at its inspections.
Is Binghatti Crest delayed?
The register lists construction as complete.
Who is building Binghatti Crest?
The registered developer is Binghatti Developers. It has 38 other projects under construction in Dubai.
Which bank holds the escrow account for Binghatti Crest?
Sharjah Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.