Binghatti Corner construction progress

The register lists Binghatti Corner in Jumeirah Village Circle as complete, with a registered completion date of March 2024. Its last site inspection on record was in August 2024. The developer is Binghatti Developers.

100%

Built, at the site inspection of 5 August 2024

Construction complete

Registered completion date
March 2024
Construction started
October 2022
First registered
December 2022
Units
727
Escrow bank
Sharjah Islamic Bank
Name in Arabic
بن غاطي كورنر
Project number
2478
Site inspections
3

Schedule

The register lists Binghatti Corner as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20232024
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

5 August 2024

100%+72 pts

  • Binghatti Corner construction site, inspection photo 1, 5 August 2024
  • Binghatti Corner construction site, inspection photo 2, 5 August 2024
  • Binghatti Corner construction site, inspection photo 3, 5 August 2024
  • Binghatti Corner construction site, inspection photo 4, 5 August 2024

7 June 2023

28%+28 pts

  • Binghatti Corner construction site, inspection photo 1, 7 June 2023
  • Binghatti Corner construction site, inspection photo 2, 7 June 2023
  • Binghatti Corner construction site, inspection photo 3, 7 June 2023
  • Binghatti Corner construction site, inspection photo 4, 7 June 2023

21 November 2022

0%

  • Binghatti Corner construction site, inspection photo 1, 21 November 2022

All 23 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Binghatti Developers has 38 projects under construction in Dubai; 14 have passed their registered completion date.

Own a unit in Binghatti Corner?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Binghatti Corner handover date?
Construction of Binghatti Corner is recorded as complete, with a registered completion date of March 2024. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Binghatti Corner?
Binghatti Corner was 100% built at the site inspection on 5 August 2024. The site has been inspected 3 times since November 2022. The Land Department took 23 site photos at its inspections.
Is Binghatti Corner delayed?
The register lists construction as complete.
Who is building Binghatti Corner?
The registered developer is Binghatti Developers. It has 38 other projects under construction in Dubai.
Which bank holds the escrow account for Binghatti Corner?
Sharjah Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.