Off-plan projects in Jaddaf Waterfront
13 projects in Jaddaf Waterfront are under construction. On average they are 32% built. 2 have passed their registered completion date. The next one due is Val By Kasco, in December 2026.
- Val By KascoKasco Real Estate Development82%Due December 2026
- Boutique 23Continental Investments Lmd65%No date set
- Binghatti TwilightBinghatti Developers55%Due April 2026, passed
- La BoutiqueContinental Investments Lmd53%Due December 2026
- Creek ViewsIraz Real Estate Development44%No date set
- MontageKey Mavens Montage Real Estate Development40%Due August 2027
- Cascade VilleCig Properties Realestate Development22%Due December 2027
- Art Bay EastEllington Dutco Real Estate19%No date set
- Binghatti MoonlightBinghatti Developers19%Due June 2026, passed
- Art Bay WestEllington Dutco Real Estate15%No date set
- CelesteHre Real Estate Development3.4%Due February 2027
- Lumiere HeightsA J G Jaddaf Real Estate Development2.1%Due June 2027
- AmazoniaPalladium Prime Real Estate Development1.4%Due October 2027
Questions
How many off-plan projects are under construction in Jaddaf Waterfront?
13 projects are under construction in Jaddaf Waterfront, 32% built on average at the latest site inspections.
Which Jaddaf Waterfront projects are due to finish next?
By registered completion date: Val By Kasco (December 2026, 82% built), La Boutique (December 2026, 53% built) and Celeste (February 2027, 3.4% built). RERA asks developers to update these dates as projects move, so check the register before relying on one.
How many Jaddaf Waterfront projects are past their completion date?
2 of 13, among them Binghatti Twilight and Binghatti Moonlight. A project counts as late once its registered completion date has passed before it reaches 100%.
Which developers are building in Jaddaf Waterfront?
The developers with the most projects here are Binghatti Developers (2), Continental Investments Lmd (2) and Ellington Dutco Real Estate (2), out of 10 building in Jaddaf Waterfront.
Reading these figures
Each percentage is the share of construction recorded at the latest site inspection. The completion date is the one the developer registered, and RERA asks developers to update it when it reviews a project. Open a project to see its latest inspections, the site photos and whether it is keeping pace with that date.
What happens at handover and how to snag a new home cover the steps after 100%.
Source: the Dubai Land Department’s Mashrooi register, read daily. Projects listed as cancelled or finished are not shown.