Lumiere Heights construction progress
The registered completion date for Lumiere Heights in Jaddaf Waterfront is June 2027. At the last site inspection, in August 2026, it was 2.1% built. The developer is A J G Jaddaf Real Estate Development.
2.1%
Built, at the site inspection of 6 August 2026
Running behind its date
- Registered completion date
- June 2027
- Finish at recent pace
- November 2064
- Construction started
- April 2025
- First registered
- March 2025
- Developer
- A J G Jaddaf Real Estate Development
- Community
- Jaddaf Waterfront
- Units
- 124
- Escrow bank
- Dubai Islamic Bank
- Name in Arabic
- لوميير هايتس
- Project number
- 3554
- Site inspections
- 6
Schedule
Between October 2025 and August 2026 the site added about 0.2 points a month. At that rate it would finish around November 2064, more than three months after its registered date of June 2027.
Site inspections
6 August 2026
2.1%+1.0 pts
21 April 2026
1.1%+1.1 pts
24 February 2026
0%
16 October 2025
0%
23 June 2025
0%
11 February 2025
0%
Context
Jaddaf Waterfront has 13 projects under construction, 32% built on average.
Own a unit in Lumiere Heights?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Lumiere Heights handover date?
- The registered completion date is June 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around November 2064. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Lumiere Heights?
- Lumiere Heights was 2.1% built at the site inspection on 6 August 2026. The site has been inspected 6 times since February 2025. The Land Department took 16 site photos at its inspections.
- Is Lumiere Heights delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2027.
- Who is building Lumiere Heights?
- The registered developer is A J G Jaddaf Real Estate Development.
- Which bank holds the escrow account for Lumiere Heights?
- Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Cascade VilleNearby in Jaddaf Waterfront. 22%, Due December 2027.
- Boutique 23Nearby in Jaddaf Waterfront. 65%.
- Art Bay EastNearby in Jaddaf Waterfront. 19%.
- Art Bay WestNearby in Jaddaf Waterfront. 15%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)





.jpeg&w=3840&q=75)