Lumiere Heights construction progress

The registered completion date for Lumiere Heights in Jaddaf Waterfront is June 2027. At the last site inspection, in August 2026, it was 2.1% built. The developer is A J G Jaddaf Real Estate Development.

2.1%

Built, at the site inspection of 6 August 2026

Running behind its date

Registered completion date
June 2027
Finish at recent pace
November 2064
Construction started
April 2025
First registered
March 2025
Developer
A J G Jaddaf Real Estate Development
Units
124
Escrow bank
Dubai Islamic Bank
Name in Arabic
لوميير هايتس
Project number
3554
Site inspections
6

Schedule

Between October 2025 and August 2026 the site added about 0.2 points a month. At that rate it would finish around November 2064, more than three months after its registered date of June 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

6 August 2026

2.1%+1.0 pts

  • Lumiere Heights construction site, inspection photo 1, 6 August 2026
  • Lumiere Heights construction site, inspection photo 2, 6 August 2026
  • Lumiere Heights construction site, inspection photo 3, 6 August 2026
  • Lumiere Heights construction site, inspection photo 4, 6 August 2026

21 April 2026

1.1%+1.1 pts

  • Lumiere Heights construction site, inspection photo 1, 21 April 2026
  • Lumiere Heights construction site, inspection photo 2, 21 April 2026
  • Lumiere Heights construction site, inspection photo 3, 21 April 2026

24 February 2026

0%

  • Lumiere Heights construction site, inspection photo 1, 24 February 2026
  • Lumiere Heights construction site, inspection photo 2, 24 February 2026

16 October 2025

0%

  • Lumiere Heights construction site, inspection photo 1, 16 October 2025
  • Lumiere Heights construction site, inspection photo 2, 16 October 2025

23 June 2025

0%

  • Lumiere Heights construction site, inspection photo 1, 23 June 2025
  • Lumiere Heights construction site, inspection photo 2, 23 June 2025

11 February 2025

0%

  • Lumiere Heights construction site, inspection photo 1, 11 February 2025
  • Lumiere Heights construction site, inspection photo 2, 11 February 2025

All 16 site photos, by inspection date

Context

Jaddaf Waterfront has 13 projects under construction, 32% built on average.

Own a unit in Lumiere Heights?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Lumiere Heights handover date?
The registered completion date is June 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around November 2064. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Lumiere Heights?
Lumiere Heights was 2.1% built at the site inspection on 6 August 2026. The site has been inspected 6 times since February 2025. The Land Department took 16 site photos at its inspections.
Is Lumiere Heights delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2027.
Who is building Lumiere Heights?
The registered developer is A J G Jaddaf Real Estate Development.
Which bank holds the escrow account for Lumiere Heights?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.