Celeste construction progress

Celeste in Jaddaf Waterfront is 3.0% built at the Land Department inspection of July 2026. Developer Hre Real Estate Development. Completion registered for February 2027.

3.0%

Built, at the Land Department site inspection of 30 July 2026

Running behind its date

Completion date (Land Department)
February 2027
Finish at recent pace
July 2049
Construction started
February 2025
Registered with the Land Department
February 2025
Units
50
Escrow bank
Sharjah Islamic Bank
Name in Arabic
سيليست
Land Department project number
3527
Land Department site inspections
3

Schedule

Between March 2026 and July 2026 the site added about 0.4 points a month. At that rate it would finish around July 2049, more than three months after the February 2027 date registered with the Land Department.

0%25%50%75%100%20262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

30 July 2026

3.0%+1.5 pts

  • Celeste construction site, Land Department inspection photo 1, 30 July 2026
  • Celeste construction site, Land Department inspection photo 2, 30 July 2026

24 March 2026

1.5%+1.5 pts

  • Celeste construction site, Land Department inspection photo 1, 24 March 2026
  • Celeste construction site, Land Department inspection photo 2, 24 March 2026
  • Celeste construction site, Land Department inspection photo 3, 24 March 2026

4 February 2025

0%

  • Celeste construction site, Land Department inspection photo 1, 4 February 2025
  • Celeste construction site, Land Department inspection photo 2, 4 February 2025

All 7 site photos, by inspection date

Context

Jaddaf Waterfront has 13 projects under construction, 27% built on average.

Hre Real Estate Development has 5 projects under construction in Dubai; 2 have passed their registered completion date.

Own a unit in Celeste?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Celeste be completed?
The completion date registered with the Dubai Land Department is February 2027. At the pace of its recent inspections the site would reach 100% around July 2049. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Celeste is built?
3.0%, measured at the Land Department site inspection on 30 July 2026. The Land Department engineers have inspected the site 3 times since February 2025.
Is Celeste delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of February 2027.
Who is building Celeste?
The registered developer is Hre Real Estate Development. It has 4 other projects under construction in Dubai.
Which bank holds the escrow account for Celeste?
Sharjah Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.