Celeste construction progress
The registered completion date for Celeste in Jaddaf Waterfront is February 2027. At the last site inspection, in November 2026, it was 3.4% built. The developer is Hre Real Estate Development.
3.4%
Built, at the site inspection of 9 November 2026
Running behind its date
- Registered completion date
- February 2027
- Finish at recent pace
- July 2058
- Construction started
- February 2025
- First registered
- February 2025
- Developer
- Hre Real Estate Development
- Community
- Jaddaf Waterfront
- Units
- 50
- Escrow bank
- Sharjah Islamic Bank
- Name in Arabic
- سيليست
- Project number
- 3527
- Site inspections
- 4
Schedule
Between March 2026 and November 2026 the site added about 0.3 points a month. At that rate it would finish around July 2058, more than three months after its registered date of February 2027.
Site inspections
9 November 2026
3.4%+0.4 pts
30 July 2026
3.0%+1.5 pts
24 March 2026
1.5%+1.5 pts
4 February 2025
0%
Context
Jaddaf Waterfront has 13 projects under construction, 32% built on average.
Hre Real Estate Development has 5 projects under construction in Dubai; 2 have passed their registered completion date.
Own a unit in Celeste?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Celeste handover date?
- The registered completion date is February 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around July 2058. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Celeste?
- Celeste was 3.4% built at the site inspection on 9 November 2026. The site has been inspected 4 times since February 2025. The Land Department took 14 site photos at its inspections.
- Is Celeste delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of February 2027.
- Who is building Celeste?
- The registered developer is Hre Real Estate Development. It has 4 other projects under construction in Dubai.
- Which bank holds the escrow account for Celeste?
- Sharjah Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Skyhills II By HreAlso by Hre Real Estate Development. 96%, Due June 2026, passed.
- Skyhills III By HreAlso by Hre Real Estate Development. 76%, Due June 2026, passed.
- Skyhills Astra By HreAlso by Hre Real Estate Development. 51%, Due June 2028.
- Sakura Gardens By HreAlso by Hre Real Estate Development. 3.6%, Due June 2029.
- Cascade VilleNearby in Jaddaf Waterfront. 22%, Due December 2027.
- Boutique 23Nearby in Jaddaf Waterfront. 65%.
- Art Bay EastNearby in Jaddaf Waterfront. 19%.
- Art Bay WestNearby in Jaddaf Waterfront. 15%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)


.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)