Celeste construction progress

The registered completion date for Celeste in Jaddaf Waterfront is February 2027. At the last site inspection, in November 2026, it was 3.4% built. The developer is Hre Real Estate Development.

3.4%

Built, at the site inspection of 9 November 2026

Running behind its date

Registered completion date
February 2027
Finish at recent pace
July 2058
Construction started
February 2025
First registered
February 2025
Units
50
Escrow bank
Sharjah Islamic Bank
Name in Arabic
سيليست
Project number
3527
Site inspections
4

Schedule

Between March 2026 and November 2026 the site added about 0.3 points a month. At that rate it would finish around July 2058, more than three months after its registered date of February 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

9 November 2026

3.4%+0.4 pts

  • Celeste construction site, inspection photo 1, 9 November 2026
  • Celeste construction site, inspection photo 2, 9 November 2026
  • Celeste construction site, inspection photo 3, 9 November 2026
  • Celeste construction site, inspection photo 4, 9 November 2026

30 July 2026

3.0%+1.5 pts

  • Celeste construction site, inspection photo 1, 30 July 2026
  • Celeste construction site, inspection photo 2, 30 July 2026

24 March 2026

1.5%+1.5 pts

  • Celeste construction site, inspection photo 1, 24 March 2026
  • Celeste construction site, inspection photo 2, 24 March 2026
  • Celeste construction site, inspection photo 3, 24 March 2026

4 February 2025

0%

  • Celeste construction site, inspection photo 1, 4 February 2025
  • Celeste construction site, inspection photo 2, 4 February 2025

All 14 site photos, by inspection date

Context

Jaddaf Waterfront has 13 projects under construction, 32% built on average.

Hre Real Estate Development has 5 projects under construction in Dubai; 2 have passed their registered completion date.

Own a unit in Celeste?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Celeste handover date?
The registered completion date is February 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around July 2058. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Celeste?
Celeste was 3.4% built at the site inspection on 9 November 2026. The site has been inspected 4 times since February 2025. The Land Department took 14 site photos at its inspections.
Is Celeste delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of February 2027.
Who is building Celeste?
The registered developer is Hre Real Estate Development. It has 4 other projects under construction in Dubai.
Which bank holds the escrow account for Celeste?
Sharjah Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.