Creek Views construction progress
Creek Views in Jaddaf Waterfront is 39% built at the Land Department inspection of September 2026. Developer Iraz Real Estate Development.
39%
Built, at the Land Department site inspection of 16 September 2026
- Finish at recent pace
- November 2028
- Construction started
- May 2024
- Registered with the Land Department
- May 2024
- Developer
- Iraz Real Estate Development
- Community
- Jaddaf Waterfront
- Units
- 108
- Escrow bank
- Emirates Islamic Bank
- Name in Arabic
- كريك فيوز
- Land Department project number
- 3026
- Land Department site inspections
- 7
Schedule
Since December 2025 Creek Views has added about 2.3 points a month. At that rate the site reaches 100% around November 2028. The Land Department has no completion date on record to compare it with.
Site inspections
16 September 2026
39%+8.8 pts
31 July 2026
30%+8.3 pts
21 April 2026
22%+5.0 pts
3 December 2025
17%+5.8 pts
3 July 2025
11%+4.9 pts
9 October 2024
6.0%+6.0 pts
25 April 2024
0%
Context
Jaddaf Waterfront has 13 projects under construction, 27% built on average.
Own a unit in Creek Views?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Creek Views be completed?
- The Land Department has no completion date on record for Creek Views yet.
- How much of Creek Views is built?
- 39%, measured at the Land Department site inspection on 16 September 2026. The Land Department engineers have inspected the site 7 times since April 2024.
- Who is building Creek Views?
- The registered developer is Iraz Real Estate Development.
- Which bank holds the escrow account for Creek Views?
- Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Cascade VilleNearby in Jaddaf Waterfront. 22%.
- Boutique 23Nearby in Jaddaf Waterfront. 49%.
- Art Bay EastNearby in Jaddaf Waterfront. 10%.
- Art Bay WestNearby in Jaddaf Waterfront. 9.1%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.










.jpeg&w=3840&q=75)