Val By Kasco construction progress

Val By Kasco in Jaddaf Waterfront is 73% built at the Land Department inspection of August 2026. Developer Kasco Real Estate Development. Completion registered for December 2026.

73%

Built, at the Land Department site inspection of 19 August 2026

On pace for its date

Completion date (Land Department)
December 2026
Finish at recent pace
February 2027
Construction started
August 2024
Registered with the Land Department
November 2024
Units
134
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
فال باي كاسكو
Land Department project number
3142
Land Department site inspections
7

Schedule

Since October 2025 Val By Kasco has added about 4.8 points a month. That puts 100% around February 2027, within three months of its registered completion date of December 2026.

0%25%50%75%100%20252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

19 August 2026

73%+15 pts

  • Val By Kasco construction site, Land Department inspection photo 1, 19 August 2026
  • Val By Kasco construction site, Land Department inspection photo 2, 19 August 2026
  • Val By Kasco construction site, Land Department inspection photo 3, 19 August 2026
  • Val By Kasco construction site, Land Department inspection photo 4, 19 August 2026

6 May 2026

57%+16 pts

  • Val By Kasco construction site, Land Department inspection photo 1, 6 May 2026
  • Val By Kasco construction site, Land Department inspection photo 2, 6 May 2026
  • Val By Kasco construction site, Land Department inspection photo 3, 6 May 2026
  • Val By Kasco construction site, Land Department inspection photo 4, 6 May 2026

30 January 2026

41%+15 pts

  • Val By Kasco construction site, Land Department inspection photo 1, 30 January 2026
  • Val By Kasco construction site, Land Department inspection photo 2, 30 January 2026
  • Val By Kasco construction site, Land Department inspection photo 3, 30 January 2026
  • Val By Kasco construction site, Land Department inspection photo 4, 30 January 2026

31 October 2025

26%+13 pts

  • Val By Kasco construction site, Land Department inspection photo 1, 31 October 2025
  • Val By Kasco construction site, Land Department inspection photo 2, 31 October 2025
  • Val By Kasco construction site, Land Department inspection photo 3, 31 October 2025
  • Val By Kasco construction site, Land Department inspection photo 4, 31 October 2025

2 June 2025

13%+5.8 pts

  • Val By Kasco construction site, Land Department inspection photo 1, 2 June 2025
  • Val By Kasco construction site, Land Department inspection photo 2, 2 June 2025
  • Val By Kasco construction site, Land Department inspection photo 3, 2 June 2025
  • Val By Kasco construction site, Land Department inspection photo 4, 2 June 2025

14 February 2025

7.2%+7.2 pts

  • Val By Kasco construction site, Land Department inspection photo 1, 14 February 2025
  • Val By Kasco construction site, Land Department inspection photo 2, 14 February 2025
  • Val By Kasco construction site, Land Department inspection photo 3, 14 February 2025
  • Val By Kasco construction site, Land Department inspection photo 4, 14 February 2025

19 June 2024

0%

  • Val By Kasco construction site, Land Department inspection photo 1, 19 June 2024
  • Val By Kasco construction site, Land Department inspection photo 2, 19 June 2024

All 43 site photos, by inspection date

Context

Jaddaf Waterfront has 13 projects under construction, 27% built on average.

Kasco Real Estate Development has 3 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Val By Kasco?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Val By Kasco be completed?
The completion date registered with the Dubai Land Department is December 2026. At the pace of its recent inspections the site would reach 100% around February 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Val By Kasco is built?
73%, measured at the Land Department site inspection on 19 August 2026. The Land Department engineers have inspected the site 7 times since June 2024.
Is Val By Kasco delayed?
Not on current figures. At the rate of the last year it finishes within three months of its registered date of December 2026.
Who is building Val By Kasco?
The registered developer is Kasco Real Estate Development. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for Val By Kasco?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.