La Boutique construction progress

La Boutique in Jaddaf Waterfront is 38% built at the Land Department inspection of June 2026. Developer Continental Investments Lmd. Completion registered for December 2026.

38%

Built, at the Land Department site inspection of 18 June 2026

Running behind its date

Completion date (Land Department)
December 2026
Finish at recent pace
February 2028
Construction started
July 2024
Registered with the Land Department
September 2024
Units
119
Escrow bank
Sharjah Islamic Bank
Name in Arabic
لا بوتيك
Land Department project number
3120
Land Department site inspections
5

Schedule

Between July 2025 and June 2026 the site added about 3.1 points a month. At that rate it would finish around February 2028, more than three months after the December 2026 date registered with the Land Department.

0%25%50%75%100%20252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

18 June 2026

38%+16 pts

  • La Boutique construction site, Land Department inspection photo 1, 18 June 2026
  • La Boutique construction site, Land Department inspection photo 2, 18 June 2026
  • La Boutique construction site, Land Department inspection photo 3, 18 June 2026
  • La Boutique construction site, Land Department inspection photo 4, 18 June 2026

25 March 2026

22%+7.3 pts

  • La Boutique construction site, Land Department inspection photo 1, 25 March 2026
  • La Boutique construction site, Land Department inspection photo 2, 25 March 2026
  • La Boutique construction site, Land Department inspection photo 3, 25 March 2026
  • La Boutique construction site, Land Department inspection photo 4, 25 March 2026

25 November 2025

14%+10 pts

  • La Boutique construction site, Land Department inspection photo 1, 25 November 2025
  • La Boutique construction site, Land Department inspection photo 2, 25 November 2025
  • La Boutique construction site, Land Department inspection photo 3, 25 November 2025
  • La Boutique construction site, Land Department inspection photo 4, 25 November 2025

16 July 2025

4.3%+4.3 pts

  • La Boutique construction site, Land Department inspection photo 1, 16 July 2025
  • La Boutique construction site, Land Department inspection photo 2, 16 July 2025
  • La Boutique construction site, Land Department inspection photo 3, 16 July 2025
  • La Boutique construction site, Land Department inspection photo 4, 16 July 2025

19 June 2024

0%

  • La Boutique construction site, Land Department inspection photo 1, 19 June 2024
  • La Boutique construction site, Land Department inspection photo 2, 19 June 2024

All 30 site photos, by inspection date

Context

Jaddaf Waterfront has 13 projects under construction, 27% built on average. La Boutique is ahead of that average.

Continental Investments Lmd has 4 projects under construction in Dubai, none past their registered completion dates.

Own a unit in La Boutique?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will La Boutique be completed?
The completion date registered with the Dubai Land Department is December 2026. At the pace of its recent inspections the site would reach 100% around February 2028. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of La Boutique is built?
38%, measured at the Land Department site inspection on 18 June 2026. The Land Department engineers have inspected the site 5 times since June 2024.
Is La Boutique delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
Who is building La Boutique?
The registered developer is Continental Investments Lmd. It has 3 other projects under construction in Dubai.
Which bank holds the escrow account for La Boutique?
Sharjah Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.