La Boutique construction progress

The registered completion date for La Boutique in Jaddaf Waterfront is December 2026. At the last site inspection, in October 2026, it was 53% built. The developer is Continental Investments Lmd.

53%

Built, at the site inspection of 12 October 2026

Running behind its date

Registered completion date
December 2026
Finish at recent pace
November 2027
Construction started
July 2024
First registered
September 2024
Units
119
Escrow bank
Sharjah Islamic Bank
Name in Arabic
لا بوتيك
Project number
3120
Site inspections
6

Schedule

Between November 2025 and October 2026 the site added about 3.6 points a month. At that rate it would finish around November 2027, more than three months after its registered date of December 2026.

0%25%50%75%100%20252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

12 October 2026

53%+14 pts

  • La Boutique construction site, inspection photo 1, 12 October 2026
  • La Boutique construction site, inspection photo 2, 12 October 2026
  • La Boutique construction site, inspection photo 3, 12 October 2026
  • La Boutique construction site, inspection photo 4, 12 October 2026

18 June 2026

38%+16 pts

  • La Boutique construction site, inspection photo 1, 18 June 2026
  • La Boutique construction site, inspection photo 2, 18 June 2026
  • La Boutique construction site, inspection photo 3, 18 June 2026
  • La Boutique construction site, inspection photo 4, 18 June 2026

25 March 2026

22%+7.3 pts

  • La Boutique construction site, inspection photo 1, 25 March 2026
  • La Boutique construction site, inspection photo 2, 25 March 2026
  • La Boutique construction site, inspection photo 3, 25 March 2026
  • La Boutique construction site, inspection photo 4, 25 March 2026

25 November 2025

14%+10 pts

  • La Boutique construction site, inspection photo 1, 25 November 2025
  • La Boutique construction site, inspection photo 2, 25 November 2025
  • La Boutique construction site, inspection photo 3, 25 November 2025
  • La Boutique construction site, inspection photo 4, 25 November 2025

16 July 2025

4.3%+4.3 pts

  • La Boutique construction site, inspection photo 1, 16 July 2025
  • La Boutique construction site, inspection photo 2, 16 July 2025
  • La Boutique construction site, inspection photo 3, 16 July 2025
  • La Boutique construction site, inspection photo 4, 16 July 2025

19 June 2024

0%

  • La Boutique construction site, inspection photo 1, 19 June 2024
  • La Boutique construction site, inspection photo 2, 19 June 2024

All 40 site photos, by inspection date

Context

Jaddaf Waterfront has 13 projects under construction, 32% built on average.

Continental Investments Lmd has 4 projects under construction in Dubai, none past their registered completion dates.

Own a unit in La Boutique?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the La Boutique handover date?
The registered completion date is December 2026. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around November 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on La Boutique?
La Boutique was 53% built at the site inspection on 12 October 2026. The site has been inspected 6 times since June 2024. The Land Department took 40 site photos at its inspections.
Is La Boutique delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
Who is building La Boutique?
The registered developer is Continental Investments Lmd. It has 3 other projects under construction in Dubai.
Which bank holds the escrow account for La Boutique?
Sharjah Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.