La Boutique construction progress
The registered completion date for La Boutique in Jaddaf Waterfront is December 2026. At the last site inspection, in October 2026, it was 53% built. The developer is Continental Investments Lmd.
53%
Built, at the site inspection of 12 October 2026
Running behind its date
- Registered completion date
- December 2026
- Finish at recent pace
- November 2027
- Construction started
- July 2024
- First registered
- September 2024
- Developer
- Continental Investments Lmd
- Community
- Jaddaf Waterfront
- Units
- 119
- Escrow bank
- Sharjah Islamic Bank
- Name in Arabic
- لا بوتيك
- Project number
- 3120
- Site inspections
- 6
Schedule
Between November 2025 and October 2026 the site added about 3.6 points a month. At that rate it would finish around November 2027, more than three months after its registered date of December 2026.
Site inspections
12 October 2026
53%+14 pts
18 June 2026
38%+16 pts
25 March 2026
22%+7.3 pts
25 November 2025
14%+10 pts
16 July 2025
4.3%+4.3 pts
19 June 2024
0%
Context
Jaddaf Waterfront has 13 projects under construction, 32% built on average.
Continental Investments Lmd has 4 projects under construction in Dubai, none past their registered completion dates.
Own a unit in La Boutique?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the La Boutique handover date?
- The registered completion date is December 2026. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around November 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on La Boutique?
- La Boutique was 53% built at the site inspection on 12 October 2026. The site has been inspected 6 times since June 2024. The Land Department took 40 site photos at its inspections.
- Is La Boutique delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
- Who is building La Boutique?
- The registered developer is Continental Investments Lmd. It has 3 other projects under construction in Dubai.
- Which bank holds the escrow account for La Boutique?
- Sharjah Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Boutique 23Also by Continental Investments Lmd. 65%.
- The PierAlso by Continental Investments Lmd. 48%, Due December 2026.
- Taiyo ResidencesAlso by Continental Investments Lmd. 12%, Due December 2027.
- Cascade VilleNearby in Jaddaf Waterfront. 22%, Due December 2027.
- Art Bay EastNearby in Jaddaf Waterfront. 19%.
- Art Bay WestNearby in Jaddaf Waterfront. 15%.
- Creek ViewsNearby in Jaddaf Waterfront. 44%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.




.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)