Amazonia construction progress
Amazonia in Jaddaf Waterfront is 0% built at the Land Department inspection of June 2026. Developer Palladium Prime Real Estate Development. Completion registered for October 2027.
0%
Built, at the Land Department site inspection of 29 June 2026
Running behind its date
- Completion date (Land Department)
- October 2027
- Finish at recent pace
- May 7364
- Construction started
- October 2025
- Registered with the Land Department
- October 2025
- Developer
- Palladium Prime Real Estate Development
- Community
- Jaddaf Waterfront
- Units
- 76
- Escrow bank
- Abu Dhabi Islamic Bank
- Name in Arabic
- امازونيا
- Land Department project number
- 3595
- Land Department site inspections
- 2
Schedule
Between June 2025 and June 2026 the site added about 0.0 points a month. At that rate it would finish around May 7364, more than three months after the October 2027 date registered with the Land Department.
Site inspections
29 June 2026
0%+0.0 pts
4 June 2025
0%
Context
Jaddaf Waterfront has 13 projects under construction, 27% built on average. Amazonia is behind that average.
Palladium Prime Real Estate Development has 2 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Amazonia?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Track the handoverQuestions
- When will Amazonia be completed?
- The completion date registered with the Dubai Land Department is October 2027. At the pace of its recent inspections the site would reach 100% around May 7364. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Amazonia is built?
- 0%, measured at the Land Department site inspection on 29 June 2026. The Land Department engineers have inspected the site 2 times since June 2025.
- Is Amazonia delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of October 2027.
- Who is building Amazonia?
- The registered developer is Palladium Prime Real Estate Development. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for Amazonia?
- Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- The GrandalaAlso by Palladium Prime Real Estate Development. 86%, Due January 2026, passed.
- Cascade VilleNearby in Jaddaf Waterfront. 22%.
- Boutique 23Nearby in Jaddaf Waterfront. 49%.
- Art Bay EastNearby in Jaddaf Waterfront. 10%.
- Art Bay WestNearby in Jaddaf Waterfront. 9.1%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.