Skip to content

Amazonia construction progress

Amazonia in Jaddaf Waterfront is 0% built at the Land Department inspection of June 2026. Developer Palladium Prime Real Estate Development. Completion registered for October 2027.

0%

Built, at the Land Department site inspection of 29 June 2026

Running behind its date

Completion date (Land Department)
October 2027
Finish at recent pace
May 7364
Construction started
October 2025
Registered with the Land Department
October 2025
Developer
Palladium Prime Real Estate Development
Units
76
Escrow bank
Abu Dhabi Islamic Bank
Name in Arabic
امازونيا
Land Department project number
3595
Land Department site inspections
2

Schedule

Between June 2025 and June 2026 the site added about 0.0 points a month. At that rate it would finish around May 7364, more than three months after the October 2027 date registered with the Land Department.

0%25%50%75%100%20262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

29 June 2026

0%+0.0 pts

  • Amazonia construction site, Land Department inspection photo 1, 29 June 2026
  • Amazonia construction site, Land Department inspection photo 2, 29 June 2026
  • Amazonia construction site, Land Department inspection photo 3, 29 June 2026

4 June 2025

0%

  • Amazonia construction site, Land Department inspection photo 1, 4 June 2025
  • Amazonia construction site, Land Department inspection photo 2, 4 June 2025

All 5 site photos, by inspection date

Context

Jaddaf Waterfront has 13 projects under construction, 27% built on average. Amazonia is behind that average.

Palladium Prime Real Estate Development has 2 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Amazonia?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will Amazonia be completed?
The completion date registered with the Dubai Land Department is October 2027. At the pace of its recent inspections the site would reach 100% around May 7364. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Amazonia is built?
0%, measured at the Land Department site inspection on 29 June 2026. The Land Department engineers have inspected the site 2 times since June 2025.
Is Amazonia delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of October 2027.
Who is building Amazonia?
The registered developer is Palladium Prime Real Estate Development. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Amazonia?
Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.