Montage construction progress
The registered completion date for Montage in Jaddaf Waterfront is August 2027. At the last site inspection, in October 2026, it was 40% built. The developer is Key Mavens Montage Real Estate Development.
40%
Built, at the site inspection of 15 October 2026
Running behind its date
- Registered completion date
- August 2027
- Finish at recent pace
- August 2028
- Construction started
- September 2024
- First registered
- January 2025
- Developer
- Key Mavens Montage Real Estate Development
- Community
- Jaddaf Waterfront
- Units
- 257
- Escrow bank
- Al Masraf
- Name in Arabic
- مونتاج
- Project number
- 3212
- Site inspections
- 9
Schedule
Between November 2025 and October 2026 the site added about 2.7 points a month. At that rate it would finish around August 2028, more than three months after its registered date of August 2027.
Site inspections
15 October 2026
40%+9.4 pts
6 August 2026
31%+6.2 pts
3 June 2026
24%+7.9 pts
16 February 2026
16%+4.2 pts
22 December 2025
12%+3.3 pts
4 November 2025
8.8%+6.3 pts
29 April 2025
2.5%+2.5 pts
25 December 2024
0%
15 August 2024
0%
Context
Jaddaf Waterfront has 13 projects under construction, 32% built on average.
Own a unit in Montage?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Montage handover date?
- The registered completion date is August 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Montage?
- Montage was 40% built at the site inspection on 15 October 2026. The site has been inspected 9 times since August 2024. The Land Department took 52 site photos at its inspections.
- Is Montage delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of August 2027.
- Who is building Montage?
- The registered developer is Key Mavens Montage Real Estate Development.
- Which bank holds the escrow account for Montage?
- Al Masraf. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Cascade VilleNearby in Jaddaf Waterfront. 22%, Due December 2027.
- Boutique 23Nearby in Jaddaf Waterfront. 65%.
- Art Bay EastNearby in Jaddaf Waterfront. 19%.
- Art Bay WestNearby in Jaddaf Waterfront. 15%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.