Montage construction progress

The registered completion date for Montage in Jaddaf Waterfront is August 2027. At the last site inspection, in October 2026, it was 40% built. The developer is Key Mavens Montage Real Estate Development.

40%

Built, at the site inspection of 15 October 2026

Running behind its date

Registered completion date
August 2027
Finish at recent pace
August 2028
Construction started
September 2024
First registered
January 2025
Developer
Key Mavens Montage Real Estate Development
Units
257
Escrow bank
Al Masraf
Name in Arabic
مونتاج
Project number
3212
Site inspections
9

Schedule

Between November 2025 and October 2026 the site added about 2.7 points a month. At that rate it would finish around August 2028, more than three months after its registered date of August 2027.

0%25%50%75%100%202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

15 October 2026

40%+9.4 pts

  • Montage construction site, inspection photo 1, 15 October 2026
  • Montage construction site, inspection photo 2, 15 October 2026
  • Montage construction site, inspection photo 3, 15 October 2026
  • Montage construction site, inspection photo 4, 15 October 2026

6 August 2026

31%+6.2 pts

  • Montage construction site, inspection photo 1, 6 August 2026
  • Montage construction site, inspection photo 2, 6 August 2026
  • Montage construction site, inspection photo 3, 6 August 2026
  • Montage construction site, inspection photo 4, 6 August 2026

3 June 2026

24%+7.9 pts

  • Montage construction site, inspection photo 1, 3 June 2026
  • Montage construction site, inspection photo 2, 3 June 2026
  • Montage construction site, inspection photo 3, 3 June 2026
  • Montage construction site, inspection photo 4, 3 June 2026

16 February 2026

16%+4.2 pts

  • Montage construction site, inspection photo 1, 16 February 2026
  • Montage construction site, inspection photo 2, 16 February 2026
  • Montage construction site, inspection photo 3, 16 February 2026
  • Montage construction site, inspection photo 4, 16 February 2026

22 December 2025

12%+3.3 pts

  • Montage construction site, inspection photo 1, 22 December 2025
  • Montage construction site, inspection photo 2, 22 December 2025
  • Montage construction site, inspection photo 3, 22 December 2025

4 November 2025

8.8%+6.3 pts

  • Montage construction site, inspection photo 1, 4 November 2025
  • Montage construction site, inspection photo 2, 4 November 2025
  • Montage construction site, inspection photo 3, 4 November 2025

29 April 2025

2.5%+2.5 pts

  • Montage construction site, inspection photo 1, 29 April 2025
  • Montage construction site, inspection photo 2, 29 April 2025
  • Montage construction site, inspection photo 3, 29 April 2025
  • Montage construction site, inspection photo 4, 29 April 2025

25 December 2024

0%

  • Montage construction site, inspection photo 1, 25 December 2024
  • Montage construction site, inspection photo 2, 25 December 2024

15 August 2024

0%

  • Montage construction site, inspection photo 1, 15 August 2024
  • Montage construction site, inspection photo 2, 15 August 2024

All 52 site photos, by inspection date

Context

Jaddaf Waterfront has 13 projects under construction, 32% built on average.

Own a unit in Montage?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Montage handover date?
The registered completion date is August 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Montage?
Montage was 40% built at the site inspection on 15 October 2026. The site has been inspected 9 times since August 2024. The Land Department took 52 site photos at its inspections.
Is Montage delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of August 2027.
Who is building Montage?
The registered developer is Key Mavens Montage Real Estate Development.
Which bank holds the escrow account for Montage?
Al Masraf. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.