Skip to content

Montage construction progress

Montage in Jaddaf Waterfront is 31% built at the Land Department inspection of August 2026. Developer Key Mavens Montage Real Estate Development. Completion registered for August 2027.

31%

Built, at the Land Department site inspection of 6 August 2026

Running behind its date

Completion date (Land Department)
August 2027
Finish at recent pace
December 2028
Construction started
September 2024
Registered with the Land Department
January 2025
Developer
Key Mavens Montage Real Estate Development
Units
257
Escrow bank
Al Masraf
Name in Arabic
مونتاج
Land Department project number
3212
Land Department site inspections
8

Schedule

Between November 2025 and August 2026 the site added about 2.4 points a month. At that rate it would finish around December 2028, more than three months after the August 2027 date registered with the Land Department.

0%25%50%75%100%202520262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

6 August 2026

31%+6.2 pts

  • Montage construction site, Land Department inspection photo 1, 6 August 2026
  • Montage construction site, Land Department inspection photo 2, 6 August 2026
  • Montage construction site, Land Department inspection photo 3, 6 August 2026
  • Montage construction site, Land Department inspection photo 4, 6 August 2026

3 June 2026

24%+7.9 pts

  • Montage construction site, Land Department inspection photo 1, 3 June 2026
  • Montage construction site, Land Department inspection photo 2, 3 June 2026
  • Montage construction site, Land Department inspection photo 3, 3 June 2026
  • Montage construction site, Land Department inspection photo 4, 3 June 2026

16 February 2026

16%+4.2 pts

  • Montage construction site, Land Department inspection photo 1, 16 February 2026
  • Montage construction site, Land Department inspection photo 2, 16 February 2026
  • Montage construction site, Land Department inspection photo 3, 16 February 2026
  • Montage construction site, Land Department inspection photo 4, 16 February 2026

22 December 2025

12%+3.3 pts

  • Montage construction site, Land Department inspection photo 1, 22 December 2025
  • Montage construction site, Land Department inspection photo 2, 22 December 2025
  • Montage construction site, Land Department inspection photo 3, 22 December 2025

4 November 2025

8.8%+6.3 pts

  • Montage construction site, Land Department inspection photo 1, 4 November 2025
  • Montage construction site, Land Department inspection photo 2, 4 November 2025
  • Montage construction site, Land Department inspection photo 3, 4 November 2025

29 April 2025

2.5%+2.5 pts

  • Montage construction site, Land Department inspection photo 1, 29 April 2025
  • Montage construction site, Land Department inspection photo 2, 29 April 2025
  • Montage construction site, Land Department inspection photo 3, 29 April 2025
  • Montage construction site, Land Department inspection photo 4, 29 April 2025

25 December 2024

0%

  • Montage construction site, Land Department inspection photo 1, 25 December 2024
  • Montage construction site, Land Department inspection photo 2, 25 December 2024

15 August 2024

0%

  • Montage construction site, Land Department inspection photo 1, 15 August 2024
  • Montage construction site, Land Department inspection photo 2, 15 August 2024

All 37 site photos, by inspection date

Context

Jaddaf Waterfront has 13 projects under construction, 27% built on average.

Own a unit in Montage?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Montage be completed?
The completion date registered with the Dubai Land Department is August 2027. At the pace of its recent inspections the site would reach 100% around December 2028. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Montage is built?
31%, measured at the Land Department site inspection on 6 August 2026. The Land Department engineers have inspected the site 8 times since August 2024.
Is Montage delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of August 2027.
Who is building Montage?
The registered developer is Key Mavens Montage Real Estate Development.
Which bank holds the escrow account for Montage?
Al Masraf. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.