Verano By Prescott construction progress
The registered completion date for Verano By Prescott in Dubai Studio City is December 2026. At the last site inspection, in September 2026, it was 41% built. The developer is Prescott Real Estate Development.
41%
Built, at the site inspection of 29 September 2026
Running behind its date
- Registered completion date
- December 2026
- Finish at recent pace
- May 2028
- Construction started
- March 2025
- First registered
- December 2024
- Developer
- Prescott Real Estate Development
- Community
- Dubai Studio City
- Units
- 269
- Escrow bank
- United Bank Limited
- Name in Arabic
- فيرانو من بريسكوت
- Project number
- 3339
- Site inspections
- 7
Schedule
Between October 2025 and September 2026 the site added about 3.0 points a month. At that rate it would finish around May 2028, more than three months after its registered date of December 2026.
Site inspections
29 September 2026
41%+8.5 pts
2 July 2026
33%+12 pts
19 March 2026
20%+5.3 pts
18 December 2025
15%+8.6 pts
16 October 2025
6.5%+4.8 pts
27 May 2025
1.7%+1.7 pts
25 October 2024
0%
Context
Dubai Studio City has 8 projects under construction, 53% built on average.
Prescott Real Estate Development has 6 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Verano By Prescott?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Verano By Prescott handover date?
- The registered completion date is December 2026. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around May 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Verano By Prescott?
- Verano By Prescott was 41% built at the site inspection on 29 September 2026. The site has been inspected 7 times since October 2024. The Land Department took 40 site photos at its inspections.
- Is Verano By Prescott delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
- Who is building Verano By Prescott?
- The registered developer is Prescott Real Estate Development. It has 5 other projects under construction in Dubai.
- Which bank holds the escrow account for Verano By Prescott?
- United Bank Limited. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Serene Gardens By PrescottAlso by Prescott Real Estate Development. 62%.
- Serene Gardens 2 By PrescottAlso by Prescott Real Estate Development. 70%.
- Fairway Residences By PrescottAlso by Prescott Real Estate Development. 50%.
- Legado By PrescottAlso by Prescott Real Estate Development. 23%, Due August 2027.
- Samana MykonosNearby in Dubai Studio City. 91%, Due April 2026, passed.
- Laya CourtyardNearby in Dubai Studio City. 51%, Due December 2026.
- Beach Oasis 2Nearby in Dubai Studio City. 57%, Due April 2026, passed.
- Arisha TerracesNearby in Dubai Studio City. 34%, Due October 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.