Verano By Prescott construction progress

The registered completion date for Verano By Prescott in Dubai Studio City is December 2026. At the last site inspection, in September 2026, it was 41% built. The developer is Prescott Real Estate Development.

41%

Built, at the site inspection of 29 September 2026

Running behind its date

Registered completion date
December 2026
Finish at recent pace
May 2028
Construction started
March 2025
First registered
December 2024
Units
269
Escrow bank
United Bank Limited
Name in Arabic
فيرانو من بريسكوت
Project number
3339
Site inspections
7

Schedule

Between October 2025 and September 2026 the site added about 3.0 points a month. At that rate it would finish around May 2028, more than three months after its registered date of December 2026.

0%25%50%75%100%20252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

29 September 2026

41%+8.5 pts

  • Verano By Prescott construction site, inspection photo 1, 29 September 2026
  • Verano By Prescott construction site, inspection photo 2, 29 September 2026
  • Verano By Prescott construction site, inspection photo 3, 29 September 2026
  • Verano By Prescott construction site, inspection photo 4, 29 September 2026

2 July 2026

33%+12 pts

  • Verano By Prescott construction site, inspection photo 1, 2 July 2026
  • Verano By Prescott construction site, inspection photo 2, 2 July 2026
  • Verano By Prescott construction site, inspection photo 3, 2 July 2026
  • Verano By Prescott construction site, inspection photo 4, 2 July 2026

19 March 2026

20%+5.3 pts

  • Verano By Prescott construction site, inspection photo 1, 19 March 2026
  • Verano By Prescott construction site, inspection photo 2, 19 March 2026
  • Verano By Prescott construction site, inspection photo 3, 19 March 2026
  • Verano By Prescott construction site, inspection photo 4, 19 March 2026

18 December 2025

15%+8.6 pts

  • Verano By Prescott construction site, inspection photo 1, 18 December 2025
  • Verano By Prescott construction site, inspection photo 2, 18 December 2025
  • Verano By Prescott construction site, inspection photo 3, 18 December 2025
  • Verano By Prescott construction site, inspection photo 4, 18 December 2025

16 October 2025

6.5%+4.8 pts

  • Verano By Prescott construction site, inspection photo 1, 16 October 2025
  • Verano By Prescott construction site, inspection photo 2, 16 October 2025
  • Verano By Prescott construction site, inspection photo 3, 16 October 2025
  • Verano By Prescott construction site, inspection photo 4, 16 October 2025

27 May 2025

1.7%+1.7 pts

  • Verano By Prescott construction site, inspection photo 1, 27 May 2025
  • Verano By Prescott construction site, inspection photo 2, 27 May 2025
  • Verano By Prescott construction site, inspection photo 3, 27 May 2025
  • Verano By Prescott construction site, inspection photo 4, 27 May 2025

25 October 2024

0%

  • Verano By Prescott construction site, inspection photo 1, 25 October 2024
  • Verano By Prescott construction site, inspection photo 2, 25 October 2024

All 40 site photos, by inspection date

Context

Dubai Studio City has 8 projects under construction, 53% built on average.

Prescott Real Estate Development has 6 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Verano By Prescott?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Verano By Prescott handover date?
The registered completion date is December 2026. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around May 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Verano By Prescott?
Verano By Prescott was 41% built at the site inspection on 29 September 2026. The site has been inspected 7 times since October 2024. The Land Department took 40 site photos at its inspections.
Is Verano By Prescott delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
Who is building Verano By Prescott?
The registered developer is Prescott Real Estate Development. It has 5 other projects under construction in Dubai.
Which bank holds the escrow account for Verano By Prescott?
United Bank Limited. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.