Legado By Prescott construction progress

The registered completion date for Legado By Prescott in Jumeirah Village Circle is August 2027. At the last site inspection, in September 2026, it was 23% built. The developer is Prescott Real Estate Development.

23%

Built, at the site inspection of 30 September 2026

Running behind its date

Registered completion date
August 2027
Finish at recent pace
May 2031
Construction started
September 2024
First registered
September 2024
Units
343
Escrow bank
United Bank Limited
Name in Arabic
ليجادو من بريسكوت
Project number
3210
Site inspections
7

Schedule

Between December 2025 and September 2026 the site added about 1.4 points a month. At that rate it would finish around May 2031, more than three months after its registered date of August 2027.

0%25%50%75%100%202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

30 September 2026

23%+3.2 pts

  • Legado By Prescott construction site, inspection photo 1, 30 September 2026
  • Legado By Prescott construction site, inspection photo 2, 30 September 2026
  • Legado By Prescott construction site, inspection photo 3, 30 September 2026
  • Legado By Prescott construction site, inspection photo 4, 30 September 2026

2 July 2026

20%+6.2 pts

  • Legado By Prescott construction site, inspection photo 1, 2 July 2026
  • Legado By Prescott construction site, inspection photo 2, 2 July 2026
  • Legado By Prescott construction site, inspection photo 3, 2 July 2026
  • Legado By Prescott construction site, inspection photo 4, 2 July 2026

23 March 2026

14%+3.7 pts

  • Legado By Prescott construction site, inspection photo 1, 23 March 2026
  • Legado By Prescott construction site, inspection photo 2, 23 March 2026
  • Legado By Prescott construction site, inspection photo 3, 23 March 2026
  • Legado By Prescott construction site, inspection photo 4, 23 March 2026

12 December 2025

10%+4.3 pts

  • Legado By Prescott construction site, inspection photo 1, 12 December 2025
  • Legado By Prescott construction site, inspection photo 2, 12 December 2025
  • Legado By Prescott construction site, inspection photo 3, 12 December 2025
  • Legado By Prescott construction site, inspection photo 4, 12 December 2025

18 September 2025

5.8%+3.9 pts

  • Legado By Prescott construction site, inspection photo 1, 18 September 2025
  • Legado By Prescott construction site, inspection photo 2, 18 September 2025

24 May 2025

1.9%+1.9 pts

  • Legado By Prescott construction site, inspection photo 1, 24 May 2025
  • Legado By Prescott construction site, inspection photo 2, 24 May 2025
  • Legado By Prescott construction site, inspection photo 3, 24 May 2025
  • Legado By Prescott construction site, inspection photo 4, 24 May 2025

12 August 2024

0%

  • Legado By Prescott construction site, inspection photo 1, 12 August 2024
  • Legado By Prescott construction site, inspection photo 2, 12 August 2024

All 33 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Prescott Real Estate Development has 6 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Legado By Prescott?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Legado By Prescott handover date?
The registered completion date is August 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around May 2031. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Legado By Prescott?
Legado By Prescott was 23% built at the site inspection on 30 September 2026. The site has been inspected 7 times since August 2024. The Land Department took 33 site photos at its inspections.
Is Legado By Prescott delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of August 2027.
Who is building Legado By Prescott?
The registered developer is Prescott Real Estate Development. It has 5 other projects under construction in Dubai.
Which bank holds the escrow account for Legado By Prescott?
United Bank Limited. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.