Arisha Terraces construction progress
Arisha Terraces in Dubai Studio City is 34% built at the Land Department inspection of August 2026. Developer Qube Development. Completion registered for October 2027.
34%
Built, at the Land Department site inspection of 19 August 2026
Running behind its date
- Completion date (Land Department)
- October 2027
- Finish at recent pace
- December 2028
- Construction started
- October 2024
- Registered with the Land Department
- October 2024
- Developer
- Qube Development
- Community
- Dubai Studio City
- Units
- 420
- Escrow bank
- Commercial Bank of Dubai
- Name in Arabic
- أريشا تيراسيس
- Land Department project number
- 3216
- Land Department site inspections
- 7
Schedule
Between November 2025 and August 2026 the site added about 2.4 points a month. At that rate it would finish around December 2028, more than three months after the October 2027 date registered with the Land Department.
Site inspections
19 August 2026
34%+5.3 pts
14 May 2026
29%+11 pts
12 February 2026
18%+5.8 pts
11 November 2025
12%+4.3 pts
7 August 2025
8.0%+4.7 pts
26 April 2025
3.3%+3.3 pts
6 August 2024
0%
Context
Dubai Studio City has 8 projects under construction, 51% built on average.
Qube Development has 2 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Arisha Terraces?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Arisha Terraces be completed?
- The completion date registered with the Dubai Land Department is October 2027. At the pace of its recent inspections the site would reach 100% around December 2028. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Arisha Terraces is built?
- 34%, measured at the Land Department site inspection on 19 August 2026. The Land Department engineers have inspected the site 7 times since August 2024.
- Is Arisha Terraces delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of October 2027.
- Who is building Arisha Terraces?
- The registered developer is Qube Development. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for Arisha Terraces?
- Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- ElireAlso by Qube Development. 8.2%.
- Samana MykonosNearby in Dubai Studio City. 91%, Due April 2026, passed.
- Laya CourtyardNearby in Dubai Studio City. 51%, Due December 2026.
- Beach Oasis 2Nearby in Dubai Studio City. 53%, Due April 2026, passed.
- Ghaff Land ResidenceNearby in Dubai Studio City. 64%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.




.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)