Arisha Terraces construction progress

The registered completion date for Arisha Terraces in Dubai Studio City is October 2027. At the last site inspection, in August 2026, it was 34% built. The developer is Qube Development.

34%

Built, at the site inspection of 19 August 2026

Running behind its date

Registered completion date
October 2027
Finish at recent pace
December 2028
Construction started
October 2024
First registered
October 2024
Units
420
Escrow bank
Commercial Bank of Dubai
Name in Arabic
أريشا تيراسيس
Project number
3216
Site inspections
7

Schedule

Between November 2025 and August 2026 the site added about 2.4 points a month. At that rate it would finish around December 2028, more than three months after its registered date of October 2027.

0%25%50%75%100%202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

19 August 2026

34%+5.3 pts

  • Arisha Terraces construction site, inspection photo 1, 19 August 2026
  • Arisha Terraces construction site, inspection photo 2, 19 August 2026
  • Arisha Terraces construction site, inspection photo 3, 19 August 2026
  • Arisha Terraces construction site, inspection photo 4, 19 August 2026

14 May 2026

29%+11 pts

  • Arisha Terraces construction site, inspection photo 1, 14 May 2026
  • Arisha Terraces construction site, inspection photo 2, 14 May 2026
  • Arisha Terraces construction site, inspection photo 3, 14 May 2026
  • Arisha Terraces construction site, inspection photo 4, 14 May 2026

12 February 2026

18%+5.8 pts

  • Arisha Terraces construction site, inspection photo 1, 12 February 2026
  • Arisha Terraces construction site, inspection photo 2, 12 February 2026
  • Arisha Terraces construction site, inspection photo 3, 12 February 2026
  • Arisha Terraces construction site, inspection photo 4, 12 February 2026

11 November 2025

12%+4.3 pts

  • Arisha Terraces construction site, inspection photo 1, 11 November 2025
  • Arisha Terraces construction site, inspection photo 2, 11 November 2025
  • Arisha Terraces construction site, inspection photo 3, 11 November 2025

7 August 2025

8.0%+4.7 pts

  • Arisha Terraces construction site, inspection photo 1, 7 August 2025
  • Arisha Terraces construction site, inspection photo 2, 7 August 2025
  • Arisha Terraces construction site, inspection photo 3, 7 August 2025
  • Arisha Terraces construction site, inspection photo 4, 7 August 2025

26 April 2025

3.3%+3.3 pts

  • Arisha Terraces construction site, inspection photo 1, 26 April 2025
  • Arisha Terraces construction site, inspection photo 2, 26 April 2025

6 August 2024

0%

  • Arisha Terraces construction site, inspection photo 1, 6 August 2024
  • Arisha Terraces construction site, inspection photo 2, 6 August 2024
  • Arisha Terraces construction site, inspection photo 3, 6 August 2024

All 44 site photos, by inspection date

Context

Dubai Studio City has 8 projects under construction, 53% built on average.

Qube Development has 3 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Arisha Terraces?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Arisha Terraces handover date?
The registered completion date is October 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around December 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Arisha Terraces?
Arisha Terraces was 34% built at the site inspection on 19 August 2026. The site has been inspected 7 times since August 2024. The Land Department took 44 site photos at its inspections.
Is Arisha Terraces delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of October 2027.
Who is building Arisha Terraces?
The registered developer is Qube Development. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for Arisha Terraces?
Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.