Arisha Terraces construction progress

Arisha Terraces in Dubai Studio City is 34% built at the Land Department inspection of August 2026. Developer Qube Development. Completion registered for October 2027.

34%

Built, at the Land Department site inspection of 19 August 2026

Running behind its date

Completion date (Land Department)
October 2027
Finish at recent pace
December 2028
Construction started
October 2024
Registered with the Land Department
October 2024
Developer
Qube Development
Units
420
Escrow bank
Commercial Bank of Dubai
Name in Arabic
أريشا تيراسيس
Land Department project number
3216
Land Department site inspections
7

Schedule

Between November 2025 and August 2026 the site added about 2.4 points a month. At that rate it would finish around December 2028, more than three months after the October 2027 date registered with the Land Department.

0%25%50%75%100%202520262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

19 August 2026

34%+5.3 pts

  • Arisha Terraces construction site, Land Department inspection photo 1, 19 August 2026
  • Arisha Terraces construction site, Land Department inspection photo 2, 19 August 2026
  • Arisha Terraces construction site, Land Department inspection photo 3, 19 August 2026
  • Arisha Terraces construction site, Land Department inspection photo 4, 19 August 2026

14 May 2026

29%+11 pts

  • Arisha Terraces construction site, Land Department inspection photo 1, 14 May 2026
  • Arisha Terraces construction site, Land Department inspection photo 2, 14 May 2026
  • Arisha Terraces construction site, Land Department inspection photo 3, 14 May 2026
  • Arisha Terraces construction site, Land Department inspection photo 4, 14 May 2026

12 February 2026

18%+5.8 pts

  • Arisha Terraces construction site, Land Department inspection photo 1, 12 February 2026
  • Arisha Terraces construction site, Land Department inspection photo 2, 12 February 2026
  • Arisha Terraces construction site, Land Department inspection photo 3, 12 February 2026
  • Arisha Terraces construction site, Land Department inspection photo 4, 12 February 2026

11 November 2025

12%+4.3 pts

  • Arisha Terraces construction site, Land Department inspection photo 1, 11 November 2025
  • Arisha Terraces construction site, Land Department inspection photo 2, 11 November 2025
  • Arisha Terraces construction site, Land Department inspection photo 3, 11 November 2025

7 August 2025

8.0%+4.7 pts

  • Arisha Terraces construction site, Land Department inspection photo 1, 7 August 2025
  • Arisha Terraces construction site, Land Department inspection photo 2, 7 August 2025
  • Arisha Terraces construction site, Land Department inspection photo 3, 7 August 2025
  • Arisha Terraces construction site, Land Department inspection photo 4, 7 August 2025

26 April 2025

3.3%+3.3 pts

  • Arisha Terraces construction site, Land Department inspection photo 1, 26 April 2025
  • Arisha Terraces construction site, Land Department inspection photo 2, 26 April 2025

6 August 2024

0%

  • Arisha Terraces construction site, Land Department inspection photo 1, 6 August 2024
  • Arisha Terraces construction site, Land Department inspection photo 2, 6 August 2024
  • Arisha Terraces construction site, Land Department inspection photo 3, 6 August 2024

All 44 site photos, by inspection date

Context

Dubai Studio City has 8 projects under construction, 51% built on average.

Qube Development has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Arisha Terraces?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Arisha Terraces be completed?
The completion date registered with the Dubai Land Department is October 2027. At the pace of its recent inspections the site would reach 100% around December 2028. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Arisha Terraces is built?
34%, measured at the Land Department site inspection on 19 August 2026. The Land Department engineers have inspected the site 7 times since August 2024.
Is Arisha Terraces delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of October 2027.
Who is building Arisha Terraces?
The registered developer is Qube Development. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Arisha Terraces?
Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.